Organizing the certification of material quality and price for installation materials and equipment: four applicable situations, a six-step implementation process, situation-based rules for employer approval of material prices, and dispute fallbacks

Certification of material quality and price is organized as 'lock quality first, then lock price, then lock evidence': the employer ultimately confirms the price; the contractor submits for approval before procurement; the supervisor reviews quotations, undertakes witnessed sampling and testing, and joins market price enquiries; the project-management body prepares the market price enquiry and pricing implementation plan; contractually adjustable materials must be jointly subject to market price enquiry and the price agreed by the employer, contractor and supervisor before procurement; follow the six steps 'prepare plan -> enquire and compare -> confirm price -> seal samples -> entry inspection -> settlement adjustment'; retroactively supplemented certifications of material quality and price carry weak weight in construction cost expert assessment (judicial appraisal).

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • T/ZBD 100.4-2023 建设工程造价鉴定作业指引
  • T/ZBD 100.5-2023 建设工程结算审核作业指引
  • GB/T 51262-2017 建设工程造价鉴定规范
  • DB37/T 5096-2017 建设工程项目管理咨询规范
  • DB11/T 382-2017 建设工程监理规程
  • T/SCIA 002-2020 建设工程全过程质量控制管理规程
  • GB/T 50319-2013 建设工程监理规范
  • T/HAEC 003-2020 工程监理资料管理标准化与信息化工作指南

Topic Positioning

The organizational method for 'certification of material quality and price' of installation materials and equipment: defining which materials require the employer's approval of material prices, the division of responsibilities among the parties, the six-step implementation process, situation-based rules for employer approval of material prices, and dispute fallbacks — used for preventing and handling material price disputes before settlement.

Core Conclusions

Organized by 'lock quality first, then lock price, then lock evidence'. Four applicable categories: provisional sums for specified materials/equipment; contractually adjustable materials; new materials introduced by variations; materials whose brand/grade deviates from the contract and need repricing. Responsibilities: the employer ultimately confirms prices and approves the implementation plan; the contractor submits for approval before procurement; the supervisor reviews the reasonableness of quotations, undertakes witnessed sampling and testing, performs parallel inspection, and participates in joint market price enquiries; the project-management body prepares the market price enquiry and pricing implementation plan (enquiry background, item name/specification/quantity/estimated price, supplier scope, organization and responsibilities, enquiry method, procedures, schedule, etc.) and submits it to the employer for approval. Key node: for contractually adjustable materials, the employer, contractor and supervisor should jointly conduct market price enquiry before procurement and agree the price — approve the price first, then procure, then bring the materials to site. Six steps: (1) prepare the plan -> (2) written enquiry and comparison -> (3) price confirmation, forming the material quality and price certification form -> (4) seal samples -> (5) entry inspection (self-check -> submission form -> appearance check -> witnessed sampling and testing/parallel inspection -> certification and sign-off if qualified, removal from site if not) -> (6) settlement adjustment per the contract rules. Situation-based rules: for provisional sums for specified materials that are not subject to mandatory tendering, the pre-tax price confirmed by the employer replaces the provisional sum and only the provisional sum item is adjusted; where the employer participated in procurement and approved the price, adjust per the approved price; if it did not participate or approve, no adjustment; where the employer requires a brand higher than contracted, re-approve the price and adjust upwards; if lower than contracted, adjust downwards; if the contractor upgrades on its own initiative, no upwards adjustment. Dispute fallbacks: where the employer gave written sign-off before procurement, the signed-off price governs; where no certification of material quality and price was submitted, the contract-agreed price governs; where approval is refused, the price agreed by both parties governs, and quality disputes are separately submitted for expert assessment.

Applicable Boundaries

Applies to organizing certification of material quality and price and settlement of materials/equipment under the contracting model of installation (including decoration and installation) works; free-issue materials (by the employer) are outside all-in unit rates and follow separate rules; provisional sums for specified materials that are subject to mandatory tendering are replaced by the awarded bid price, not by a material quality and price certification form; operational details such as the number of suppliers invited for market price enquiry follow the documents of the project location.

Further Reading

GB/T 50500-2024 Clauses 8.4.5, 8.4.6 (substitution of provisional sums and adjustment for price differentials); T/ZBD 100.4-2023 Clause 4.4.7 (expert assessment of price adjustment for materials not subject to a provisional sum); T/ZBD 100.5-2023 Clauses 3.1.5, 3.1.6 (brand and unit rate review); GB/T 51262-2017 Clause 5.6.4 (price dispute expert assessment); DB37/T 5096-2017 Clause 6.5.1 (implementation-plan elements); DB11/T 382-2017 Clause 5.3.3 (joint market price enquiry before procurement); T/SCIA 002-2020 Clause 7.3.5 (sample sealing); GB/T 50319-2013 Table B.0.6 and T/HAEC 003-2020 Clause 10.16.1 (entry-inspection procedures).