Establishing material sample-sealing and quality-and-price confirmation ledgers in decoration projects: samples govern quality, confirmed prices govern price, ledgers keep traceability
Sample-sealing governs quality, price confirmation governs price, ledgers keep traceability — a trinity: the sample-sealing ledger scopes per GB 50210-2018 Clause 3.3.8 + GB/T 50500-2024 Clause 3.7.2, with four-party confirmation, three-party sealing, and entry-comparison traceability; the price-confirmation ledger completes signing per the DB37/T 5096-2017 inquiry-pricing procedure before procurement — after-the-fact supplementary signing carries weak evidentiary weight in construction cost expert assessment (judicial appraisal) (GB/T 51262-2017 Clause 5.6.4); the two ledgers merge into one material control master ledger; provisional-sum material replacement adjusts the material cost only, with VAT counted separately (GB/T 50500-2024 Clauses 8.4.5/8.4.6).
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准
- GB 50210-2018 建筑装饰装修工程质量验收标准
- GB/T 51262-2017 建设工程造价鉴定规范
- DB37/T 5096-2017 建设工程项目管理咨询规范
- DBJ/T 15-153-2019 广东省建设项目全过程造价管理规范
- DB37/T 5164-2020 建筑施工现场管理标准
Topic Positioning
The method and implementation points for establishing "material sample sealing + quality-and-price confirmation" ledgers in decoration projects: samples govern quality, confirmed prices govern price, ledgers keep traceability — strung into a traceable evidentiary chain at settlement.
Core Conclusions
Sample-sealing ledger: scope covers materials whose color/gloss/pattern are hard to describe (stone, tiles, wallpaper, paint, etc., GB 50210-2018 Clause 3.3.8), main materials confirmed by the employer (GB/T 50500-2024 Clause 3.7.2), and subcontractor self-purchased materials requiring sealing (DB37/T 5164-2020 Clause 8.3.11). Process: submission review → sample delivery → four-party confirmation → three-party sealing → entry comparison → results recorded in the ledger; labels must contain name, brand, specification/model, color number, origin, batch number, supplier, sealing date, signatures, and location of use. Price-confirmation ledger: first prepare the inquiry-pricing implementation plan (DB37/T 5096-2017 Clause 6.5.1), organize market inquiries and form countersigned records (Clause 6.5.2), the cost agency proposes pricing recommendations and the construction employer approves (Clause 6.5.3), then both parties sign; it must be completed before procurement — after-the-fact supplementary signing is handled at the contract-agreed price in construction cost expert assessment (judicial appraisal) (GB/T 51262-2017 Clause 5.6.4). Key points: published prices must not be applied directly (DBJ/T 15-153-2019 Clause 7.6.4); tax calibers (pre-tax/tax-inclusive) and the attribution of freight and procurement-keeping stated clearly; provisional-sum material replacement adjusts the material cost only, other costs unchanged, VAT counted separately (GB/T 50500-2024 Clauses 8.4.5/8.4.6). Recommended to merge into one material control master ledger: material code/sample number/confirmation number/contract price/confirmed price/location of use/entry comparison/settlement adjustment, linked with the entry inspection ledger and the supervisor's ledger.
Applicable Boundaries
Applies to the dual quality-price control of decoration works during construction — sample sealing, price confirmation, and ledger traceability must be used together. Not applicable to: pure market procurement without provisional sums or brand agreements; specialist-works provisional sums (wholesale replacement at tax-inclusive prices, different rules); individual cases already in construction cost expert assessment (judicial appraisal) (items must be determined per contract and evidence).
Further Reading
GB/T 50500-2024 Clauses 3.7.2, 8.4.5, 8.4.6; GB 50210-2018 Clause 3.3.8; GB/T 51262-2017 Clause 5.6.4; DB37/T 5096-2017 Clauses 6.5.1~6.5.3; DBJ/T 15-153-2019 Clause 7.6.4; DB37/T 5164-2020 Clause 8.3.11; T/GAEC 201-2018 ledger Clause 6.2.1; T/HAEC 006-2023 Clause 5.5.13.
Keywords
- 材料封样
- certification of material quality and price
- 认价台账
- 封样台账
- 材料询价定价
- 暂估价材料
- 材料管控台账
- 装饰装修造价管理