Tender pricing strategy: market price enquiry as the primary basis with published price information as auxiliary cross-validation — bidders price independently and are not compelled to use published price information
Tender pricing takes market price enquiry as primary and published price information as auxiliary cross-validation: GB/T 50500-2024 Clauses 6.1.1/6.2.1 require bidders to price independently per their own conditions; published price information (a reference price) has no mandatory binding force at the tendering stage; the cost floor and competitiveness can only be measured by actual enquiries — published price information is used to check abnormal enquiry results, supplement references for rare materials, and support explanations when comparing with the tender price ceiling; provisional sums and employer-supplied/specified brands follow the tender documents; enquiries must unify the basis of pricing and keep records.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准
- GB/T 50875-2013 工程造价术语标准
- T/ZBD 100.1-2022 建设工程造价数据建设通用标准
Topic Positioning
Labour/material/machinery price-taking strategy at the tender pricing stage: market price enquiry as primary with published price information as auxiliary cross-validation — bidders price independently, not compelled to use published price information.
Core Conclusions
(1) Independent pricing principle: GB/T 50500-2024 Clauses 6.1.1 and 6.2.1 require bidders to price independently per their contractor's in-house norms, market price information, and price-change expectations; published price information is a reference price published by administration agencies (GB/T 50875-2013 Clause 2.1.16) with no mandatory binding force at the tendering stage (what is mandatory is on the tender price ceiling side). (2) The primary basis is market price enquiry: the pricing floor is enterprise cost (below-cost tendering is illegal), measured by actual enquiries/purchase contracts/contractor's in-house norms; following published price information forfeits bulk-purchase and supply-chain advantages; where the contract does not allow price adjustment (for fluctuation), price risk is borne alone (6.2.2) and risk reserves must be included. (3) Auxiliary uses of published price information: cross-check abnormal enquiry results (obviously low — check the basis of pricing); serve as a reference for rare/new materials without enquiry results; serve as the comparison anchor with the tender price ceiling — large deviations need enquiry records for self-consistency. (4) Exceptions follow the tender documents: provisional sums for specified materials / nominated works are filled per the given values and adjusted after the employer's confirmation (8.4.5); employer-supplied/specified brands are enquired per the limiting conditions. Market prices, published price information, and manufacturer quotations are strictly never mixed across the three channels (T/ZBD 100.1-2022 Clause 7.2.3); keep enquiry records to answer below-cost tendering challenges.
Applicable Boundaries
Applies to price-taking decisions at the tender pricing stage; not applicable to tender price ceiling compilation or settlement price determination (priority: contract agreement > employer's approval of material prices > published price information > market price enquiry) or to filling gaps for materials without published price information.
Further Reading
GB/T 50500-2024 Clauses 6.1.1, 6.2.1, 6.2.2, 8.4.5 and Appendix A; GB/T 50875-2013 Clause 2.1.16; T/ZBD 100.1-2022 Clause 7.2.3.