Who bears the costs of organising tendering and of cooperation for provisionally priced materials and provisionally priced specialist works, in three scenarios (employer as tenderer / contractor as tenderer / joint tendering) (GB/T 50500-2024, 8.4.2-8.4.4 + GF-2020-0216, 13.4.1)
Under GB/T 50500-2024, 8.4.2-8.4.4: where the employer acts as tenderer, the employer bears the costs of organising the tendering work, and where the contractor's cooperation is needed the contractor bears its own cooperation costs; where the contractor acts as tenderer, the contractor bears the costs of organising the tendering work and these costs 'shall be deemed already included in the contractor's tender total price (the contract price at signing)', and where the employer's cooperation is needed the employer bears its own; where both parties act jointly as tenderers, each bears its corresponding costs (the split as agreed in the particular conditions). Common principle: organising and cooperation costs are borne by each party itself, the contractor's share is deemed included in its tender price and cannot be charged separately. GF-2020-0216, 13.4.1 matches this (the costs of contractor-organised tendering deemed included in the contract price at signing); for provisional-price items not subject to mandatory tendering, replacement prices are determined by enquiry or joint tendering under 8.4.7.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准 第8.4.2条、第8.4.3条、第8.4.4条、第8.4.7条
- 建设项目工程总承包合同(示范文本)GF-2020-0216 通用合同条件第13.4.1项、第13.4.2项及专用合同条件第13.4条
- 中华人民共和国招标投标法实施条例 第二十九条
Scope
This card resolves a concrete cost-allocation question that arises when tendering provisionally priced materials and provisionally priced specialist works: whether the costs of organising the tendering work and the other party's cooperation costs fall on the employer or the contractor, and whether those costs can be charged separately. Basis: GB/T 50500-2024, 8.4.2-8.4.4 and GF-2020-0216, 13.4.1.
Core conclusions
General rule: whoever acts as tenderer bears the costs of organising the tendering work; the cooperating party bears its own cooperation costs; and the costs borne on the contractor's side are in every case deemed included in its tender price (the contract price at signing) and cannot be charged separately.
Employer as tenderer - GB/T 50500-2024, 8.4.2: where the employer acts as tenderer for tendering provisionally priced materials or provisionally priced specialist works, the employer shall bear the costs related to organising the tendering work. Where the contractor's cooperation is needed, the contractor shall bear its own cooperation costs. The organising and cooperation costs of tendering provisionally priced materials and provisionally priced specialist works are borne by each party itself, and the contractor's share may be deemed included in its tender price.
Contractor as tenderer - 8.4.3: where the contractor acts as tenderer for tendering provisionally priced materials or provisionally priced specialist works, the contractor shall bear the costs related to organising the tendering work, and these costs shall be deemed already included in the contractor's tender total price (the contract price at signing). Where the employer's cooperation is needed, the employer shall bear its own cooperation costs. The organising and cooperation costs are borne by each party itself, and the contractor's share may be deemed included in its tender price.
Both parties jointly as tenderers - 8.4.4: where the employer and the contractor act jointly as tenderers for tendering provisionally priced materials or provisionally priced specialist works, the parties shall each bear their corresponding costs. The organising and cooperation costs are borne by each party itself, and the contractor's share may be deemed included in its tender price.
The corresponding wording of the contract text - GF-2020-0216 General Conditions, 13.4.1: for provisional-price items subject to mandatory tendering under law, where the particular conditions provide that the contractor acts as tenderer, the tender documents, the evaluation plan and the evaluation results shall be submitted to the employer for approval; the costs related to organising the tendering work shall be deemed already included in the contractor's contract price at signing. Where the particular conditions provide that the employer and the contractor act jointly as tenderers, the costs related to organising the tendering work are as agreed in the particular conditions. The model text and the pricing standard are aligned: where the contractor organises, the organising costs sink into the contract price at signing; where the parties organise jointly, the sharing is left to the particular conditions.
Provisional-price items not subject to mandatory tendering under law - GB/T 50500-2024, 8.4.7: where specialist works given provisional prices in the bill of quantities (BOQ) are not subject to mandatory tendering under law, the VAT-inclusive specialist works price may be determined under the relevant provisions of Section 8.10 of this standard and substituted for the specialist works provisional price, or the parties may jointly tender to determine a VAT-inclusive specialist subcontract price replacing the specialist works provisional price, adjusting the contract price. Where provisionally priced materials and (or) provisionally priced specialist works are not subject to mandatory tendering under law, the contractor may enquire and procure in the manner agreed in the contract, and upon the employer's confirmation the confirmed price replaces the provisional price and adjusts the contract price. For the price adjustment of a BOQ item carrying a provisional material price, only the pre-tax provisional price of the material within the all-in unit rate is adjusted; the other costs included in the all-in unit rate shall not be adjusted. The non-mandatory route thus follows the same logic of 'whoever organises or procures bears its own costs, and the contractor's share is already in its price'.
Boundaries
- This card governs only the allocation and separability of 'tender organising and cooperation costs'; it does not change the statutory determination of 'whether tendering is mandatory', and does not address how the winning price replaces the provisional price or whether the provisional-price differential carries overheads and profit (see the cited cards on provisional price replacement and material provisional-price differentials).
- The contractor's organising and cooperation costs 'deemed included in the tender price' are a sunk treatment at the pricing level: absent a special agreement in the contract, they cannot be separately certified and priced in the name of 'provisional-price tendering costs'; if the employer is genuinely to pay them separately, this must be expressly agreed in the particular conditions or a supplementary agreement, failing which they will be found included.
- For joint tendering, the standard sets no fixed sharing ratio for 'each bearing its corresponding costs'; it must be agreed in the particular conditions or a supplementary agreement, and where the agreement is unclear, negotiated by the actual organising workload.
- Delay liability for different causes follows separate rules (GF-2020-0216, 13.4.2): where the employer causes delay in concluding and performing the provisional-price contract, the employer bears the increased costs and (or) the delayed period and pays the contractor a reasonable profit; where the contractor causes it, the contractor bears them - a cost of a different nature from the 'tender organising costs'; do not mix them.
Further reading
- GB/T 50500-2024, China national pricing standard for BOQ, Section 8.4 (adjustment of the contract price - provisional prices): 8.4.1 (replacement by the winning price), 8.4.2 (cost bearing where the employer tenders), 8.4.3 (cost bearing where the contractor tenders), 8.4.4 (cost bearing for joint tendering), 8.4.7 (price determination and replacement for provisional-price items not subject to mandatory tendering).
- Model Contract for Engineering Procurement Construction (EPC) of Construction Projects, GF-2020-0216, General Conditions 13.4.1 and 13.4.2; Particular Conditions 13.4 (the ranges in which the contractor may bid, the ranges in which it may not bid, tendering procedures and other agreements, cost-sharing agreements).
- Implementation Regulations of the Tendering and Bidding Law of the PRC, Article 29 (the definition of provisional prices and the precondition of mandatory tendering).
Keywords
- provisional sum for specified materials / nominated works
- 招标组织费用
- 配合费用
- GB/T 50500-2024
- adjustment of the contract price
- 签约合同价
- GF-2020-0216