Old-vs-new rules on the advance payment ratio: GB/T 50500-2024 Clauses 9.2.2/9.2.3 vs GB 50500-2013 Clause 10.1.2 — the 10%–30% band and changed deduction bases
The 10%–30% payment band is retained in GB/T 50500-2024 but the deduction bases changed: the lower-bound base now deducts the provisional sum for nominated specialist subcontract works in addition to provisional sums; the upper-bound base is now 30% of the signed contract price with no deductions; the basis for computing the advance expressly deducts three items (provisional sums, dayworks amounts and the provisional sum for nominated specialist subcontract works); the lower-bound wording softens from "shall not be below" to "should preferably not be below" (the standard as a whole becoming a recommended national standard). Advances for major multi-year works are paid annually against the annual programme, with each year preferably not below 10% and not above 30% of that year's planned contract price for completion (excluding provisional sums and the provisional sum for nominated specialist subcontract works) (9.2.3).
Applicable Codes
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第 9.2.2 条、第 9.2.3 条
- GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works 第 10.1.2 条(已废止)
Topic Positioning
This card answers whether the "10%–30%" advance payment ratio band is retained in GB/T 50500-2024 and whether the basis for deducting provisional sums has changed, setting out the original clause texts of the 2013 and 2024 editions with an item-by-item comparison. It applies to drafting and reviewing advance payment clauses, checking advance payment applications, and judging transition between the old and new standards.
Core Conclusions
Current rule (GB/T 50500-2024, Clause 9.2.2): "The advance payment amount for the contract works may be determined as agreed in the contract, calculated from the contract price and the advance payment percentage. The advance payment percentage shall comply with the provisions of the State and of the provincial and sectoral authorities concerned, and the contract price used as the basis for calculating the advance shall deduct the provisional sums, dayworks amounts and provisional sum for nominated specialist subcontract works included in the total contract price." "For works where the contractor supplies both labour and materials, the advance payment percentage should preferably not be below 10% of the signed contract price (less provisional sums and the provisional sum for nominated specialist subcontract works), and should preferably not be above 30% of the signed contract price."
Major multi-year works (GB/T 50500-2024, Clause 9.2.3): "The advance payment for major works extending over more than one year may be paid annually against the annual programme of works; the advance payment percentage for each year should preferably not be below 10% of that year's planned contract price for completion (excluding provisional sums and the provisional sum for nominated specialist subcontract works), and should preferably not be above 30% of that year's planned contract price for completion."
Old rule (GB 50500-2013, Clause 10.1.2, repealed and superseded): for works where the contractor supplies both labour and materials, the advance payment percentage shall not be below 10% of the signed contract price (less provisional sums), and should preferably not be above 30% of the signed contract price (less provisional sums).
Item-by-item comparison:
| Item | GB 50500-2013 (repealed) | GB/T 50500-2024 (current) |
|---|---|---|
| Band | 10%–30% | 10%–30% (retained) |
| Lower-bound wording | shall not be below | should preferably not be below |
| Lower-bound deductions | provisional sums | provisional sums + provisional sum for nominated specialist subcontract works |
| Upper-bound base | signed contract price (less provisional sums) | signed contract price (no deduction; 30% of the contract price) |
| Basis of calculation | not specified | expressly deducts three items: provisional sums, dayworks amounts, provisional sum for nominated specialist subcontract works |
| Major multi-year works | no separate annual basis | annual base excludes provisional sums and the provisional sum for nominated specialist subcontract works (9.2.3) |
Practice points: (1) The lower-bound base is smaller — the 2024 edition deducts one further item, the provisional sum for nominated specialist subcontract works, so the absolute 10% floor is slightly lower at the same contract price; the upper-bound base conversely makes no deduction, so the absolute 30% cap is slightly relaxed. (2) "Should preferably" is not "shall not" — the 2024 edition as a whole has become a recommended national standard (GB to GB/T), but 9.2.2 also requires the payment percentage to "comply with the provisions of the State and of the provincial and sectoral authorities concerned"; where ministerial or local documents apply (for example Caijian [2004] No. 369, the Interim Measures for Settlement of Construction Project Payments, which provide that the percentage shall in principle be not below 10% and not above 30% of the contract amount), those provisions must still be followed, and in practice the floor should not be breached merely on the ground that the wording is "should preferably".
Applicable Boundaries
- Applies to works where the contractor supplies both labour and materials; labour-only works (contractor supplying labour but not materials) fall outside this percentage clause and are handled separately under the contract and the relevant provisions.
- The 2024 edition is a recommended standard; "should preferably" has no mandatory force, but it is constrained by Clause 9.2.2, which requires compliance with the provisions of the State and of the provincial and sectoral authorities concerned — where ministerial rules or local regulations impose mandatory requirements on the advance payment percentage, those requirements prevail.
- For advances on major multi-year works, the annual base must first be decomposed from the project execution plan (construction methodology and site organization) approved by the Employer and the annual programme of works and the contract price in the bill of quantities (first part of 9.2.3), after which the 10%–30% band is applied.
- This card compares the payment percentage and deduction bases only; the nature of the advance (ring-fenced use, non-interest-bearing), the payment procedure, the guarantee, recovery and so on are dealt with in the other clauses of §9.2 and in related cards.
Further Reading
- GB/T 50500-2024, Standard for Pricing on a Bill of Quantities Basis for Construction Projects, Chapter 9 "Interim Payment of Contract Price", Section 9.2: 9.2.1 nature of the advance and ring-fenced use; 9.2.2 payment percentage and deduction bases; 9.2.3 annual advances for major multi-year works; 9.2.4 notice to pay / suspension of the works / claims for late payment; 9.2.5 advance payment guarantee amount decreasing as recovery proceeds and released on full recovery; 9.2.6 methods of recovery (a single recovery or recovery in instalments against progress payments where the contract is silent).
- Old edition GB 50500-2013, Code of Valuation with Bill of Quantities of Construction Works, Clause 10.1.2 (repealed, superseded by GB/T 50500-2024).
- Related rules: progress payment percentage should preferably not be below 80% of the cumulative value of the works completed (9.1.7); interim settlement by construction stage should not be below 80% (10.2.4); the advance for statutory safety provisions shall not be recovered from progress payments (9.3.2).
Keywords
- 预付款支付比例
- provisional sums
- provisional sum for nominated specialist subcontract works
- GB/T 50500-2024
- GB 50500-2013
- 跨年度重大工程
- 签约合同价
- 9.2.2