Full-process handling rules for prime cost (PC) sums for materials included in the all-in unit rate across tender, performance and settlement (GB/T 50500-2024)

For prime cost (PC) sums for materials (tax-exclusive unit prices), tenderers must include them in the all-in unit rate as stated in the BOQ without unilateral alteration, and separately include safekeeping, secondary handling and loss costs and list them in Table E.2.3; during performance, after the winning tender price or the employer's approval of material prices, only the material PC sum item within the all-in unit rate is replaced, with other costs not adjusted; such items are not subject to the general adjustment for cost fluctuation under Clauses 8.7.2–8.7.4; for settlement and construction cost expert assessment (judicial appraisal), the material price confirmation sheet / winning tender basis serves as the price-adjustment voucher.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • 中华人民共和国招标投标法实施条例
  • T/ZBD 100.5-2023 建设工程结算审核作业指引
  • T/ZBD 100.4-2023 建设工程造价鉴定作业指引

Topic Positioning

Handling of prime cost (PC) sums for materials in the all-in unit rate runs through three stages — tender pricing, contract performance, and settlement/construction cost expert assessment (judicial appraisal); this card gives the operating rules and voucher requirements for each stage.

Core Conclusions

(1) Tender pricing (GB/T 50500-2024 Clause 6.2.5): where the BOQ states a PC sum for materials, the tenderer shall include it in the all-in unit rate at the stated material PC unit price, excluding value added tax (VAT), and must not alter it unilaterally; in addition to the PC sum, costs of procurement, storage, safekeeping, secondary handling and construction loss shall be fully included in the tender, and the material PC unit prices are listed in Table E.2.3 of Appendix E.2. (2) Performance adjustment (Section 8.4): only the material PC sum item within the all-in unit rate is adjusted; price difference = (confirmed tax-exclusive unit price − material PC tax-exclusive unit price) × quantity; other costs — labour cost, machinery cost, management fee and profit — are not adjusted; for items subject to statutory mandatory tendering, replace with the tax-exclusive procurement winning tender price; for those not subject to mandatory tendering, replace with the tax-exclusive inquiry price/own quotation price confirmed by the employer, and adjust value added tax (VAT) in step with the price difference. (3) Relation to general adjustment (Clause 8.7.5): material PC sum items are not subject to the general adjustment rules for cost fluctuation under Clauses 8.7.2–8.7.4; they follow the dedicated path under Section 8.4. (4) Settlement and expert assessment: in settlement, the PC sum is replaced by the price confirmed by both the employer and contractor or by the winning tender price; in construction cost expert assessment (judicial appraisal), the unit price certified and signed off by the employer or the actual tender winning unit price may replace the PC sum; where the employer has neither certified and signed off nor promised an adjustment, no adjustment shall be made.

Applicable Boundaries

Applies to building works and general installation works priced under GB/T 50500-2024; PC sums for materials are tax-exclusive and adjust only the material item, whereas provisional sums for nominated specialist subcontract works are tax-inclusive and replaced as a whole — the rules differ and must not be mixed; where the contract expressly provides otherwise, those provisions prevail; railway, highway and other sectors follow their sector-specific pricing rules.

Further Reading

See GB/T 50500-2024 Clause 6.2.5 (inclusion in tender pricing), Clauses 8.4.1/8.4.5/8.4.6 (replacement and adjustment), Clause 8.7.5 (not subject to general adjustment for cost fluctuation), Appendix E.2 Table E.2.3; "Implementation Regulations of the Bidding Law" Article 29 (definition of provisional sum and mandatory tendering); T/ZBD 100.5-2023 Clause 3.1.6 and T/ZBD 100.4-2023 Clause 4.4.4 (settlement and construction cost expert assessment (judicial appraisal) basis); DB11/T 382-2017 Clause 5.3.3 (joint inquiry and confirmation before implementation).