adjustment of provisional prices after procurement
- 01
Settlement pricing when the confirmed price of a provisionally priced material differs from published price information: the procedurally formed confirmed price (net award price, or employer-confirmed enquiry price) replaces the provisional sum, published prices serving only as the contractually agreed base or a provisional fallback in disputes
Settlement follows the confirmed price formed under the contractual proc…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.14、3.3.5、8.4.1~8.4.6、10.3.2条及App. A 第A.2.2、A.2.5条GB/T 50875-2013 · Standard glossary of project costs 第2.2.60、2.1.16条T/ZBD 100.5-2023 · Work Guideline for Settlement Audit of Construction Works 第3.1.7条2026-10-18 - 02
Full-process handling rules for prime cost (PC) sums for materials included in the all-in unit rate across tender, performance and settlement (GB/T 50500-2024)
For prime cost (PC) sums for materials (tax-exclusive unit prices), tend…
GB/T 50500-2024 建设工程工程量清单计价标准中华人民共和国招标投标法实施条例T/ZBD 100.5-2023 建设工程结算审核作业指引2026-09-25 - 03
GB/T 50500-2024 rules for adjusting price differences, management fee, and tax after the actual price of provisionally priced materials/equipment is determined (Section 8.4)
Per GB/T 50500-2024 Section 8.4, once the actual price of provisionally…
GB/T 50500-2024 第 8.4.1、8.4.5、8.4.6 条GB/T 50500-2024 第 2.0.14、3.2.11、8.1.8 条2026-09-25