The VAT charging base of the bill of quantities and the non-duplication of tax on provisional sums for specialist works (GB/T 50500-2024 clauses 3.2.11 and 3.1.6)
VAT = [work-item list + preliminaries list + other-items list (less the provisional sums for specialist works)] total x the VAT rate set by the authorities; the specialist provisional sums are VAT-inclusive, and no further tax may be charged on them (clauses 3.2.11 and 3.1.6). Under general taxation the construction rate is 9% (price and tax separated); under the simplified scheme the levy rate is 3% (factor prices carry input tax, the base being the tax-exclusive works cost that already includes input tax).
Applicable Codes
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第 3.1.6 条、第 3.2.11 条及条文说明
Positioning
Where VAT sits in the BOQ (the single listing point), how the charging base is fixed (why specialist provisional sums are deducted), and how the general and simplified schemes differ in price form across cost documents - for checking total prices and tax lines against double taxation.
Core conclusions
1. The single listing point: no tax inside the all-in unit rate
Clause 3.1.6: "The all-in unit rates and sums of BOQ items are fully-loaded pre-tax prices excluding VAT, composed of labour, materials, plant, overheads and profit, including the agreed or reasonable risk and indispensable ancillary work; the tax of BOQ items is entered in VAT, but the provisional sums for specialist works in the other-items list already contain VAT, and no further tax is charged on them." The commentary: rates, sums and item-priced amounts are pre-VAT full prices; their tax appears in VAT, not inside the rates or sums; specialist provisional sums are VAT-inclusive amounts.
2. Base and formula
Clause 3.2.11: "VAT is computed on the combined amounts of the work-item, preliminaries and other-items lists (specialist provisional sums excepted) x the VAT rate set by the authorities." Commentary: "the other-items total used for VAT deducts the specialist provisional sums it contains." VAT = [sum of work-item costs + sum of preliminaries + sum of other items (without specialist provisional sums)] x VAT rate
- In the base: provisional sums, dayworks, main contractor's attendance provisions, material (equipment) provisional sums at the listed pre-tax prices.
- Deducted: specialist provisional sums - VAT-inclusive already; including them is taxing the tax.
- From a tax-inclusive sum: tax = sum / (1 + rate) x rate - never sum x rate.
3. General versus simplified
- General: payable = current output tax - input tax; output = sales x 9% (construction); sales is all price and out-of-price charges. Cost documents show price-tax separation: unit prices of labour, materials and plant exclude deductible input VAT; VAT listed separately.
- Simplified: payable = sales x 3%; sales is all price and charges less subcontract payments; work-item, preliminaries and other-item costs are all input-tax-inclusive prices, the base being the "pre-tax" works cost inclusive of input tax.
- Never mix: under the simplified scheme prices already hold input tax - no 9% output tax, no duplicate input credit.
4. Three frequent errors
- VAT inside the all-in unit rate, then multiplied again at roll-up (double taxation);
- specialist provisional sums not deducted from the base - taxing VAT-inclusive prices again;
- multiplying the tax-inclusive sum by the rate to back out tax - overstating it (divide by 1 + rate first).
Applicable boundaries
- For BOQ-priced works under GB/T 50500-2024; the 2013 edition and some provincial fee norms still list "taxes and duties" with composite rates (by place of taxation) - a different basis, not to be mixed.
- 9% and 3% are the current rates / levy rate for construction - follow the authorities' current rules.
- Once a specialist provisional sum is fixed as the subcontract award, the VAT-inclusive price replaces it wholesale in other items - its tax is inside; still no separate charge.
- No coverage here of surcharges inside simplified composite rates, nor of enterprise income tax.
Further reading
- GB/T 50500-2024 clauses 3.1.6, 3.2.11 and commentaries.
- MoF / STA rules on construction VAT: general rate, simplified levy, subcontract deduction.
- Provincial fee norms, "taxes" chapter: general / simplified notes and specialist provisional sum treatment.