GB/T 50500-2024 comparison of specialist-work provisional amounts (VAT-inclusive) and material provisional prices (VAT-exclusive): listing, taxation, and adjustment rules
Under GB/T 50500-2024 "Standard for BOQ pricing of construction works": the specialist-work provisional amount is a VAT-inclusive price (listed in other items, deducted from the VAT computation base to avoid double taxation, replaced wholesale by the successful VAT-inclusive subcontract price at adjustment); the material provisional price is a VAT-exclusive pre-tax unit price (entered into the comprehensive rate of a work-section item, VAT charged normally on the VAT line, adjustment limited to the pre-tax material difference within the comprehensive rate). The two have opposite tax calibers and differ in listing, taxation, and adjustment — mixing them double-counts or omits VAT.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准(第2.0.14、2.0.15、3.1.6、3.2.11、6.2.5、8.4.1、8.4.6、8.4.7、8.10节,App. ETable E.1.1、Table E.2.3、Table E.4.3)
Topic Positioning
This card systematically compares the two provisional pricing categories of GB/T 50500-2024 "Standard for BOQ pricing of construction works" — "specialist-work provisional amount" and "material provisional price": tax caliber, listing position, inclusion method, VAT treatment, and adjustment rules — for bidding, budgeting, contract price adjustment, and settlement reconciliation.
Core Conclusions
The two have opposite tax calibers: the specialist-work provisional amount is VAT-inclusive; the material provisional price is VAT-exclusive (pre-tax).
- Definition (Clause 2.0.15): the specialist-work provisional amount is "the VAT-inclusive specialist-works cost estimated by the employer in the BOQ where the specific requirements and price cannot be fixed at tendering", and "excludes specialist works directly awarded by the employer".
- Tax caliber (Clause 8.4.1): "The material provisional price is a pre-tax unit price (VAT-exclusive), but the specialist-work provisional amount is a tax-inclusive price (VAT-inclusive)."
- Listing and inclusion: the specialist-work provisional amount is listed in other items (detailed in Table E.4.3, one whole item); bidders include the amount wholesale in the tender total, not spread into comprehensive rates. The material provisional price sits inside a work-section item: the stated VAT-exclusive unit price enters that item's comprehensive rate (Clause 6.2.5; also listed in Appendix E.2 Table E.2.3).
- VAT treatment (Clause 3.2.11): "VAT shall take as its base the totals of the work-section, measures, and other items BOQs (excluding specialist-work provisional amounts)"; "the other-items total used for VAT shall deduct the specialist-work provisional amount contained" — i.e., no VAT is charged on the specialist provisional amount (avoiding double taxation); the material provisional price is part of the pre-tax all-in comprehensive rate (Clause 3.1.6), its VAT charged normally on the VAT line. Table E.1.1 note 1 concurs: "the specialist-work provisional amount is a tax-inclusive price and shall not be included in the VAT computation base".
- Adjustment (mandatory tendering, Clause 8.4.1): materials — "replace the original pre-tax provisional price with the successful pre-tax purchase price"; specialist works — "replace the original tax-inclusive provisional amount with the successful tax-inclusive price".
- Adjustment (non-mandatory tendering, Clause 8.4.7): specialist works — determine a VAT-inclusive price per Section 8.10 or by joint tendering, replacing the provisional amount; materials — the contractor inquires and purchases per the contract, confirmed by the employer, then replaces.
- Adjustment scope (Clause 8.4.6): material adjustment "adjusts only the material provisional price (pre-tax) within the comprehensive rate"; labor, plant, management, and profit in the rate should not be adjusted; the adjusted rate serves Sections 8.2, 8.3, 8.9 (BOQ defects, provisional sums, variations); the specialist provisional amount is replaced wholesale as a tax-inclusive amount.
Applicable Boundaries
Applies to the whole BOQ pricing process under GB/T 50500-2024 (tender lists, bids, adjustments, settlement). The specialist-work provisional amount excludes employer-awarded specialist works (2.0.15); the material provisional price covers engineering equipment and is a delivered-site VAT-exclusive price (2.0.14). This card compares the two under GB/T 50500-2024; where industry standards (highway, railway) differ, their provisions prevail. Excludes provisional sums and other other-items contents.
Further Reading
See GB/T 50500-2024: Clause 2.0.15 (specialist provisional term), 2.0.14 (material provisional term), 3.1.6 (comprehensive rate = pre-tax all-in price), 3.2.11 (VAT base deducts specialist provisional), 6.2.5 (material provisional enters the rate pre-tax; Appendix E.2 Table E.2.3), 8.4.1 (mandatory-tendering replacement and the caliber difference), 8.4.6 (adjust only the material provisional; adjusted rate reused in 8.2/8.3/8.9), 8.4.7 (non-mandatory replacement), Section 8.10 (VAT-inclusive specialist price determination), Appendix E Table E.1.1 note 1 and Table E.4.3. Material price-difference and VAT adjustment details in the referenced Section 8.4 card.