Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-25

Labour cost pricing basis within the all-in unit rate: norm-based labour cost (base-period workday rate) versus current-period published labour price information and labour market prices, the applicable rules at the tender price ceiling and tender stages, and the test that the labour cost differential and the labour cost inside the all-in unit rate are not adjusted twice

Labour cost in the all-in unit rate = norm (budget) labour consumption x the current-period labour rate (published price information or a market price confirmed by the parties): consumption is locked to the quota manual while the rate is opened to the current-period market (GB/T 51095-2015, clause 5.3.9). The base-period workday rate published with the quota manuals is not itself the pricing input for BOQ rate build-up; it is a component of norm-based labour cost and the comparison base of the labour cost differential. At the tender price ceiling stage the published labour rates / published price information take precedence (GB/T 50500-2024, clauses 5.2.1 and 5.2.8); the tender is priced freely by the tenderer on its in-house norms and the market, but not below cost and not above the tender price ceiling (clauses 6.1.1, 6.1.3, 6.2.1). Differentials caused by changes in costs carry VAT only, not overheads or profit (clause 3.3.5); the same labour differential may be taken once only, in either the current-period-price pricing system or the base-period-price-plus-differential system, and must not be stacked on the labour cost already inside the all-in unit rate.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准 第2.0.9、3.1.6、3.3.5、5.2.1、5.2.4、5.2.8、6.1.1、6.1.3、6.2.1、8.6.3、8.7.1条,App. A.2.1、A.2.4
  • GB/T 51095-2015 建设工程造价咨询规范 第5.3.9条、App. C
  • TB 10801-2024 铁路基本建设工程设计概(预)算编制办法 第3.1.1~3.1.5条、第4.1.1~4.1.2条
  • TB 10811 铁路基本建设工程设计概(预)算费用定额
  • 陕西省建设工程费用规则(2025)第4.1、4.2节、第6.1节
  • 湖北省建筑安装工程费用定额(2024)第十部分 建设工程计价活动中定额人工费动态管理
  • 京建法〔2021〕11号 费用计算程序(量、价、费的确定原则)

Topic Positioning

This card resolves a frequent dispute in BOQ-based pricing: whether the labour cost inside an all-in unit rate takes the workday rate published with the quota manuals (base-period price) or the current-period published labour price information / observed labour market price. It gives a character comparison of the two bases, the applicable tests at the tender price ceiling and tender stages, and the rule for deciding whether a separately adjusted labour cost differential duplicates the labour cost already inside the all-in unit rate, all with clause numbers and document names.

Core Conclusions

1. Basic rate build-up structure: consumption from the quota manuals, rate from the current period

Clause 5.3.9 of GB/T 51095-2015, code for construction cost consultancy: 'The all-in unit rate of each line item may be determined through the budget quota manual and its companion on-cost norms. Labour, material and plant costs shall be determined from the labour, material and plant element consumption of the corresponding budget quota line items together with the market prices of those elements in the report preparation period; overheads, profit, statutory levies and taxes shall be determined from the on-cost norms or percentage-rate standards companion to the budget quota manual, and from the actual conditions and market level of the proposed project in the report preparation period. When compiling a building works budget, an all-in unit rate analysis sheet shall be compiled simultaneously.' The same clause states that the rate build-up may follow Annex C of that code, the all-in unit rate analysis sheet.

That is: the quota manual governs quantity (labour consumption / workdays) while current-period prices govern the rate (labour rate). Norm-based labour cost = base-period workday rate x quota consumption; it is a standard cost amount and a charging base. Published labour price information / market price is the current-period rate. The difference between the two is the labour cost differential.

2. Pricing character of labour cost in the all-in unit rate (tax treatment)

Term 2.0.9 of GB/T 50500-2024, standard for valuation with bill of quantities: 'All-in unit rate ... the cost required to complete one unit quantity of a BOQ item. The all-in unit rate of a BOQ item comprises labour cost, material cost, plant and small tools cost, overheads, profit and risk allowances within a defined range, and excludes VAT.' 'VAT is a price-exclusive tax; the all-in unit rate does not contain VAT.'

Clause 3.1.6: 'The all-in unit rate and the lump price of BOQ items shall be fully inclusive pre-tax prices excluding VAT, composed of labour cost, material cost, plant and small tools cost, overheads and profit, including risk allowances within the range agreed for or reasonably attributable to the item and the costs of indispensable auxiliary work; the taxes of BOQ items shall be entered as VAT, except that provisional sums for nominated specialist works in the bill of other charges already contain VAT, and the corresponding tax shall not be charged again in the VAT of the bill of quantities.'

Corollary: when a published price information figure enters the all-in unit rate, it must be the net-of-tax labour rate, aligned with the fully inclusive pre-tax all-in unit rate.

3. Comparison of the two bases

Dimension Basis A: workday rate published with the quota manuals (base-period price) Basis B: published labour price information / observed labour market price (current-period price)
Character Standard cost amount at social average level (norm-based labour cost) Element price reflecting current market conditions (published price information, enquiry, price confirmed by both parties)
Cost boundary Packaged basis covering basic wages, allowances and subsidies, auxiliary wages, staff welfare, labour protection and social insurance (railway basis: TB 10801-2024, clause 3.1.4); local rules may charge the employer-paid social insurance separately without overheads or profit Fluctuates with trade, region and quarter; the cost boundary must first be aligned with norm-based labour cost, otherwise the two are not comparable
Source Published with quota / on-cost norms (railway all-in labour rates follow TB 10811, norms of costs for design estimates and budgets of railway capital construction projects; TB 10801-2024 clause 3.1.5; base-period labour workday rate tables issued under provincial cost rules) Published labour price information / labour rates issued by construction cost administration agencies, tender winning prices from trading centres, enquiry prices confirmed by both parties (GB/T 50500-2024 clause 5.2.8 items 5 and 6; clause 8.6.3)
Entry into the all-in unit rate Enters norm-based direct cost and the charging base as 'base-period labour cost', with the differential listed separately Used directly as the pricing rate: quota consumption x current-period rate = labour cost inside the all-in unit rate
Function Cost-cap control, charging base, comparison base for differentials Pricing input for rate build-up, tendering and ceiling compilation
Typical systems Railway estimates and budgets (TB 10801-2024 clauses 3.1.2, 3.1.3); 'base-period price + dynamic differential' cost rules of some provinces; Hubei manages norm-based labour cost dynamically via a composite labour cost index Building and municipal BOQ pricing at current-period market prices (GB/T 51095-2015 clause 5.3.9)

Where no priced all-in unit rate is available for dayworks, the pricing sequence is: the price information source agreed in the contract; then net-of-tax market price information for labour, materials and plant rental published by cost administration agencies or the industry; then the contractor's purchase rate confirmed by both parties (GB/T 50500-2024, clause 8.6.3).

4. Applicable tests by contracting stage

(1) Tender price ceiling compilation - use published rates / published price information; the ceiling must not be arbitrarily depressed with negotiated market prices.

  • The eight compilation bases in clause 5.2.1 include item 3, 'rules on measurement and valuation of the works issued by national, provincial and sectoral construction authorities', and item 7, 'works price information and cost intelligence, cost data and indices'.
  • Clause 5.2.8: prices of BOQ items may be compiled with 'reasonable works prices obtained through market enquiry for labour, materials, plant and BOQ all-in unit rates' (item 5) and 'recent market prices of labour, materials and plant in use, and related price indices or tender price indices' (item 6).
  • Clause 5.2.4: 'The all-in unit rates of BOQ items in the tender price ceiling may be determined under clauses 3.1.6 and 3.1.7 of this standard, with the valuation method stated in the explanatory notes.'
  • Local practice basis: the cost calculation procedure of Jing Jian Fa [2021] No. 11 (principles for fixing quantity, price and charge) - 'Price: for unit rates of construction production elements in the tender price ceiling, the employer preferably relies on published cost information (the labour workday rate not below the lower bound of the applicable band); where no published price information exists, market enquiry applies. In the tender, all element prices are enquired freely by the tenderer and may reasonably reference published price information'; 'Quantity: all shall be calculated under the Budget Consumption Standard ... self-made adjustments cannot be treated as pricing under the consumption standard'; 'Charge: for preliminaries and charge items that cannot be measured precisely in the tender price ceiling, the employer must make its own assessment and take no less than the midpoint of the charge index band'.
  • Shaanxi Province construction works cost rules (2025): 'Labour rates are calculated from the labour rates and dynamic adjustment documents published by the provincial construction cost authority; material prices follow the material published price information issued by provincial and municipal cost authorities, and materials not covered by that published information are priced by reference to market prices; plant machine-shift rates follow the plant machine-shift rate norms and the dynamic adjustment documents published by the provincial cost authority.'

(2) Tender (priced offer) - the tenderer enquires prices freely, but is doubly constrained by cost and the ceiling.

  • Clause 6.1.1: 'The tender shall be compiled by the tenderer or a cost consultant entrusted by it. The tenderer shall determine the tender freely under the relevant measurement and valuation rules and its own conditions, and bears the risks of unreasonable pricing.'
  • Clause 6.2.1: the compilation bases include item 7, 'the tenderer's in-house norms, cost data, market price information and price movement expectations, plant and management level, and cost intelligence', and require 'reasonably determining a tender that both reflects the tenderer's own productivity and remains competitive'.
  • Clause 6.1.3: 'The tenderer's tender shall not be below cost and shall not exceed the tender price ceiling published by the employer. The tenderer's tender shall be neither below the works cost nor above the tender price ceiling; the works cost may be reasonably determined by reference to similar projects.'

5. Relationship between the labour cost differential and the labour cost inside the all-in unit rate (duplication test)

General test: look at whether the labour cost in the all-in unit rate was built from current-period prices or base-period prices - if built from current-period prices, the differential is already inside the rate and no separate labour differential is listed; only when built from base-period prices is a separate labour differential calculated. The same differential must not be taken once under the rate and once under the differential item.

  • Railway system (base-period price + differential): TB 10801-2024 clause 3.1.2, 'labour cost = sum of quota labour consumption x all-in labour rate'; clause 3.1.3, 'the difference between current-period and base-period labour cost is listed as a labour cost differential'; clause 4.1.2 item 1, 'labour differential adjustment method: calculated as the labour consumption counted under the quota manuals (excluding labour inside plant machine-shifts) multiplied by the difference between the current-period and base-period all-in labour rates'.
  • Adjustment for changes in costs during performance (GB/T 50500-2024, clause 3.3.5): 'Adjustment of differentials in labour cost, material cost and the fuel and power within plant and small tools cost carries VAT and does not carry overheads or profit.' 'Differentials caused by changes in costs carry VAT only; the risk of overheads and profit is to be allowed for by the tenderer as risk cost in the tender.'
  • Clause 8.7.1: the adjustment relies on 'the price movement reflected by the market price information published by the source agreed in the contract, covering labour cost, material cost and the fuel and power within plant and small tools cost, between the contract base date and the adjustment period', calculating the differential beyond the risk band agreed in the contract and adjusting it under clauses 8.7.2-8.7.4.
  • Annex A.2.1, adjustment based on published price information: delta P is the price adjustment amount (the current adjustment amount calculated per measurement period) and delta C the adjustable factor differential; the base price C0 is 'the market price 28 days before the tender submission deadline (for non-tendered works, 28 days before contract signature)', which may come from the market price used by the employer when setting the tender price ceiling, the quarterly (monthly) published price information issued by the cost administration agency, or tender winning prices published within the previous month for similar conditions by the trading centre at the project location; Ci is the market price in the measurement period; Q is the quantity of the adjustable factor; r is the risk band coefficient, 'positive when delta C > 0 and negative when delta C < 0'. The pricing method, source and confirmation of the base and current prices and the risk band coefficient shall be assessed and fixed by the employer and stated in the tender documents.
  • Annex A.2.4, three cases of beyond-band adjustment on a published price information base: where the tenderer's rate is below the base price, rises are measured from the base price and falls from the tender, with the part beyond the agreed risk band adjusted as actual; where the rate is above the base price, falls are measured from the base price and rises from the tender; where the rate equals the base price, both rises and falls are measured from the base price; in each case only the part beyond the band is adjusted as actual.
  • Hubei basis (Hubei Building and Installation Works Cost Norms (2024), Part 10): 'Norm-based labour cost in construction works is expressed as a charge, not showing workday rates or workday consumption. Norm-based labour cost is managed dynamically through a composite labour cost index', 'the composite labour cost index is calculated on the base period and reflects the change of the measurement period relative to the base period', and 'the adjusted part of labour cost carries VAT only'.

6. Trigger conditions of the dynamic labour adjustment mechanism

  • Contract level: items agreed to be adjustable for changes in costs (premise of clause 3.3.5, 'items whose price is agreed to be adjustable for changes in costs'); and actual movement beyond the risk band agreed in the contract (clause 8.7.1, Annex A.2.4).
  • Administrative publication level: publication of labour rates, dynamic adjustment coefficients or a composite labour cost index by the provincial cost authority triggers a base update - Shaanxi rules section 6.1: 'Labour cost adjusts with market changes. Cost authorities of each city measure the adjustment coefficient or labour rate within their jurisdiction, published uniformly by the provincial cost authority ... construction-drawing based budgets and tender price ceilings shall use the labour rate or dynamic adjustment coefficient published by the provincial cost authority'; the same rules confirm that the difference between the dynamically published rate and the base-period rate goes into the labour differential item, and that 'the tenderer determines it freely when compiling the tender'.
  • Any difference between the current period and the base period is listed as a differential (railway TB 10801-2024 clauses 3.1.3 and 4.1.1, 'differential adjustment of design estimates and budgets means the reasonable adjustment of prices from the base period to the design estimate (budget) preparation period').

Applicability Boundaries

  • The point in time of the current-period basis must be evidenced: in the contract adjustment system the base price is fixed at 'the market price 28 days before the tender submission deadline (for non-tendered works, 28 days before contract signature)', and how it is determined must be stated in the tender documents, otherwise no beyond-band base can be fixed in a dispute.
  • Systems must not be crossed: building and municipal BOQ pricing uses 'current-period market price rate build-up plus contract-agreed adjustment'; railway estimates and budgets use 'base-period price plus current-period differential'; some provinces use 'base-period price plus dynamically published differential'. Copying the pricing method of system A into system B causes duplicated or missed differentials.
  • Differential adjustment carries VAT only, not overheads or profit; risk cost already taken into the all-in unit rate at tender stage must not be charged again as a differential.
  • The all-in unit rate is a fully inclusive pre-tax price; when taking published price information the net-of-tax figure must be used; provisional sums for nominated specialist works in the bill of other charges already contain VAT and are not taxed again.
  • This card contains no region-specific workday rates or percentage figures; actual pricing must follow the labour rates / published price information current at the preparation period.
  • The fallback sequence where published price information is missing (published price information first, then market enquiry / price confirmed by both parties) applies to ceiling compilation and contract adjustment; at tender stage the tenderer may enquire everything freely, unconstrained by this sequence.

Further Reading

  • GB/T 50500-2024, standard for valuation with bill of quantities: clause 2.0.9 (all-in unit rate term), clause 3.1.6 (what makes up the fully inclusive pre-tax price), clause 3.3.5 (changes in costs carry VAT only), clauses 5.2.1/5.2.4/5.2.8 (tender price ceiling compilation bases and price information), clauses 6.1.1/6.1.3/6.2.1 (tender autonomy and the upper and lower bounds), clause 8.6.3 (dayworks rate pricing sequence), clause 8.7.1 (differential adjustment basis), Annex A.2.1 (published price information adjustment formula and base price definition), A.2.4 (three beyond-band cases), Annex G.2 (schedule of price-adjustable key materials).
  • GB/T 51095-2015, code for construction cost consultancy, clause 5.3.9 and Annex C all-in unit rate analysis sheet.
  • TB 10801-2024, compilation rules for design estimates and budgets of railway capital construction projects, clauses 3.1.1-3.1.5 (labour cost composition and differential listing) and 4.1.1-4.1.2 (base-period to current-period differential adjustment method), with the companion TB 10811 norms of costs for design estimates and budgets of railway capital construction projects.
  • Shaanxi Province construction works cost rules (2025), section 4.1 (BOQ pricing principles, all-in unit rate definition), section 4.2 (labour rates, material published price information and plant machine-shift rates for tender price ceiling compilation), the labour differential / dynamic material differential / dynamic plant differential items in the valuation procedure, and section 6.1 (labour cost composition, base-period workday rate and dynamic management).
  • Hubei Building and Installation Works Cost Norms (2024), Part 10, dynamic management of norm-based labour cost in construction pricing (composite labour cost index principle and 'the adjusted part of labour cost carries VAT only').
  • Jing Jian Fa [2021] No. 11 cost calculation procedure (principles for fixing quantity, price and charge): ceiling element rates preferably follow published cost information, the labour workday rate is no less than the lower bound of the applicable band, market enquiry applies where no published price information exists, and tender element prices are all freely enquired.