Publication period of winning-candidate lists and objection/complaint procedures for evaluation results under the Implementation Regulations (Articles 54 and 60)
For mandatory-tender projects, the tenderer shall publish the winning candidates within 3 days of receiving the evaluation report, for at least 3 days; bidders or interested parties objecting to the results shall object during the publication period, and the tenderer shall reply within 3 days of receipt and suspend the proceedings until the reply. Dissatisfied parties may complain to the administrative supervision department within 10 days of knowing or should have known; complaints on Articles 22/44/54 matters require a prior objection (objection first), whose response period is excluded from the 10 days.
Applicable Codes
- 《中华人民共和国招标投标法实施条例》(国务院令第709号,2019修订)第五十四条、第六十条
- 《中华人民共和国招标投标法》第二十四条、第四十六条
Topic Positioning
Rules of the Implementation Regulations (State Council Decree No. 709, 2019 revision) on when to publish winning candidates for mandatory-tender projects and the minimum period, the objection window and reply duty for evaluation results, and the link between objection and administrative complaint (Articles 54 and 60, original texts).
Core Conclusions
I. Publication start and minimum period (54(1)): publish within 3 days of receiving the evaluation report, for at least 3 days. The start is "the day of receiving the written evaluation report" - not the day evaluation ends or award is decided; "days" (calendar, not working days); 3 days is a floor - longer publication is allowed. II. Objection window and reply duty (54(2)): objections to the results of mandatory-tender projects shall be raised during the publication period (from publication to its expiry). The tenderer shall reply within 3 days of receipt and shall suspend the proceedings until replying. "3-day reply + suspension" is mandatory - award cannot proceed while an objection is pending. III. Complaint channel (60(1)): parties considering the activities unlawful may complain to the administrative supervision department within 10 days of knowing or should have known, with clear requests and necessary evidence. IV. Objection-first and period linkage (60(2)): complaints on Articles 22 (documents), 44 (opening), and 54 (results) require a prior objection to the tenderer; the objection-response period is excluded from the 10 days - the tenderer's response days do not consume the complaint period. V. Practice: objections not raised during publication leave only the complaint route, and Article 54 matters still need a prior objection - late objections are usually rejected (DB22/T 5036-2020: "failure to object during publication forfeits the right to object" - procedural reference); submit objections in writing with proof of service, since the 3-day reply and suspension run from "receipt"; for e-platform publication, the platform's period governs - mind the submission cutoff.
Applicable Boundaries
- Article 54 applies only to mandatory-tender projects; voluntary projects follow any contractual publication/objection arrangements.
- This card concerns objections to evaluation results (54); document objections follow Article 22 (at least 10 days before the bid deadline, in writing); opening objections Article 44 - different windows, do not mix.
- The 10-day complaint period runs from "knowing or should have known" with the objection-response time excluded; but missing both the objection window and the complaint period forfeits relief - not indefinite.
- Post-award contract timing (within 30 days of the notice) is outside this card.
Further Reading
- Implementation Regulations (Decree No. 709, 2019) Articles 54 and 60; read with Bidding Law Article 46 (contract within 30 days of the notice).
- Document-objection rules in Article 22; see also the card on tender-document vs. drawing inconsistencies.
- Other statutory bidding floors (5-day sales, 20-day bidding period) in the cited card.
- Local detail: DB22/T 5036-2020; railways: Measures for Bidding Administration of Railway Projects (MOT Order No. 13 of 2018) Article 38 (replies must state facts and basis; sustained objections affecting the award trigger re-check by the original committee per the tender documents).
Keywords
- Implementing Regulation of the Tendering and Bidding Law (State Council Decree No. 613)
- 中标候选人公示
- 评标结果异议
- 异议前置
- 投诉期限
- 公示期不得少于3日
- 国务院令709号
- 行政监督部门投诉