Whether increased pipeline quantities caused by BIM coordinated layout can adjust the work quantities: determined by attribution in the deepening design (contractor's own deepening design — no adjustment; only where it constitutes a variation is adjustment made)
Whether the quantities of pipelines increased by BIM coordinated layout can be adjusted depends on attribution: differences arising from the contractor's own deepening design are generally not adjusted (GB/T 50500-2024, Clause 3.3.9; T/ZBD 100.4-2023, Clause 4.4.6), except where the contract provides for settlement on the basis of the deepened drawings; where the employer so requires, or where it constitutes a variation confirmed upon review by the original designer, adjustment is made per Chapters 7/8/9, and where the quantity difference exceeds 15%, the unit rate is adjusted per Clause 8.9.2.
Applicable Codes
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第3.3.9条、第2.0.25条、第7.4.1~7.4.4条、第8.2.1条、第8.9.1~8.9.2条
- GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works 第9.3.1条、第9.3.2条、第9.6.2条
- T/ZBD 100.4-2023 · Work Guideline for Construction Cost Appraisal 第4.4.4条、第4.4.6条、第4.6节
- GF-2017-0201《建设工程施工合同(示范文本)》第10.1~10.4条
- T/CIAS-5-2022《数据中心机电工程技术规程》第4.3.8条
- T/CIAS-2-2020《建筑机电施工图深化设计技术标准》第3.2.1条、第4.2.2条
Topic Positioning
An attribution-decision framework for whether work quantities can be adjusted when pipelines increase or lengthen due to BIM coordinated layout (deepening design): first qualify (whose requirement caused the increase), then quantify (the 15% deviation rule), so as to avoid mistaking "deepening-design responsibility" for a "variation".
Core Conclusions
- General principle (GB/T 50500-2024, Clause 3.3.9): where the contractor performs construction deepening design of the contract drawings as required by the contract and differences arise between the deepened drawings and the contract drawings, the contract price shall not be adjusted unless otherwise agreed in the contract or otherwise required by the employer; however, where the differences constitute a variation required by the employer, the adjustment is calculated per Chapters 7~9.
- Construction cost expert assessment approach (T/ZBD 100.4-2023, Clause 4.4.6): where the contractor performs deepening design and requests adjustment of all-in unit rates, the expert assessor generally does not adjust, except where the contract stipulates that the contractor's deepened design drawings serve as the basis for settlement. Where the employer's deepening design constitutes a variation, it is assessed as a variation (Clause 4.4.4).
- Adjustable situations: employer's variation instructions / design change drawings; the BIM deepened model implemented through formal variation procedures after review and confirmation by the original design unit (T/CIAS-5-2022, Clause 4.3.8); the contract stipulates the deepened drawings as the basis for settlement.
- Quantification: once it constitutes a variation, measure per Clause 7.4.1; not exceeding 15% (inclusive) per Clause 8.9.1 (contract unit rate / conversion from analogous items / negotiated rate build-up); exceeding 15% (exclusive) per Clause 8.9.2 — the increased portion may have its unit rate reasonably reduced in light of procurement discounts, and the decreased portion reasonably increased.
- Boundaries: BIM pipeline coordination is content the contractor should digest through layout optimization; the deepening-design principle is that main systems follow the original design (T/CIAS-2-2020, Clause 3.2.1), and changes in hydraulic capacity, current-carrying capacity, etc. caused by rerouting must be checked under the original design conditions (Clause 4.2.2); the quantity, specifications and routing of cable trays must not be arbitrarily increased or altered.
Applicable Boundaries
Applies to disputes over measured work quantities of divisional and sub-divisional works caused by BIM/deepening design under re-measurable (unit-rate) contracts; under lump-sum contracts, errors and omissions in the BOQ are not adjusted (Clause 7.4.1). "Attribution qualification" and "15% deviation" are two separate steps: if it does not constitute a variation, the 15% rate adjustment does not even arise. Not applicable to charging deepening-design/consulting fees (a cost-attribution issue), and does not cover special BIM service fees separately commissioned by the employer.
Further Reading
GB/T 50500-2024 "China national pricing standard for BOQ" Clauses 3.3.9, 7.4.1, 8.2.1, 8.9.1, 8.9.2; T/ZBD 100.4-2023 "Guidelines for construction cost expert assessment practice" Clauses 4.4.4, 4.4.6; T/CIAS-5-2022 "Technical regulation for mechanical and electrical engineering of data centres" Clause 4.3.8; T/CIAS-2-2020 "Technical standard for deepening design of building MEP construction drawings" Clauses 3.2.1, 4.2.2.