Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Whether site instruction and certified records can directly serve as the basis for the final account: statutory status, the four preconditions for 'direct adoption', and the review/recheck mechanism

Site instruction and certified records are among the statutory bases for the final account (GB/T 50326-2017 18.3.3, GB/T 51095-2015 8.3.4, GB/T 50500-2024 7.1.8), but 'direct adoption' requires four preconditions: (1) certification and sign-off by both parties (or their authorized representatives); (2) the signatory has authority within the scope of duties; (3) the content is true (unless proven false); (4) raised within the time limit and complete in form. Final account review and construction cost expert assessment (judicial appraisal) treat site instruction and certified records as 'rechecked rather than accepted wholesale' — where quantities are inconsistent with actuals, calculate at actual completed quantities; where inconsistent with drawing facts, written clarification and adjustment based on the facts are required.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • GB/T 51262-2017 建设工程造价鉴定规范
  • GB/T 51095-2015 建设工程造价咨询规范
  • GB/T 50326-2017 建设工程项目管理规范
  • GB/T 50875-2013 工程造价术语标准
  • T/ZBD 100.5-2023 建设工程结算审核作业指引

Topic Positioning

Answers whether site instruction and certified records can directly serve as the basis for the final account: statutory status, the four preconditions for direct adoption, and the recheck mechanism.

Core Conclusions

Site instruction and certified records are among the statutory bases for the final account (GB/T 50326-2017 18.3.3, GB/T 50500-2024 7.1.8). 'Direct adoption' requires four preconditions: (1) certification and sign-off by both parties — a unilateral signature or a mere 'received' without consent should not be directly adopted (GB/T 51262-2017 5.9.2); (2) the signatory is authorized — only signatures within the scope of duties are valid pricing vouchers, unless proven false (12.2.1); (3) the content is true — inflated portions produce no pricing effect; (4) raised within the time limit and complete in form — 28 days if the contract is silent (8.11.3). Final account review and construction cost expert assessment (judicial appraisal) treat site instruction and certified records as 'rechecked rather than accepted wholesale': the review checks legality, timeliness, truthfulness, accuracy, and the logical sequence of signature dates (T/ZBD 100.5-2023 2.2.3); where the quantity in a site instruction / variation record is inconsistent with actual completion, it is calculated at the actual completed quantity (5.9.1); where inconsistent with drawings and facts, both parties shall clarify in writing and adjust according to the facts (GB/T 51095-2015 8.3.6).

Applicable Boundaries

Addresses 'the qualification and validity of site instruction and certified records as a basis for the final account'; graded pricing where prices are missing, the effect of unilateral signatures, and remedies for completed work without a site instruction / variation record are in dedicated cards; where the contract contains special provisions, those provisions prevail.

Further Reading

GB/T 50500-2024 Clauses 7.1.8, 8.11.3, 12.2.1; GB/T 51262-2017 Section 5.9; GB/T 51095-2015 Clause 8.3.6; GB/T 50875-2013 Clause 3.4.8.