legal and evidentiary force of site records
- 01
Site instruction / variation record signed only by the supervising engineer without the employer's signature: effectiveness for settlement and remedy of the defect
A site instruction / variation record bearing only the supervising engin…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50875-2013 工程造价术语标准GB/T 51262-2017 建设工程造价鉴定规范2026-09-25 - 02
Determining validity when a site instruction / variation record conflicts with meeting minutes: the three-tier cascade of certification and sign-off validity -> formation time -> actual completion
When a site instruction / variation record conflicts with meeting minute…
GB/T 51262-2017 · Code for Construction Cost Appraisal 第5.9节、第5.9.1条T/GAEC 201-2018 · Guideline for Compilation and Management of Supervision Documents of Construction Projects 第5.1.4条GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第12.2.1条2026-09-25 - 03
Validity of retroactively supplemented site instructions and certified records (supplementary/back-dated signing): the three tests of authenticity, mutual consent, and timeliness
A retroactively supplemented site record is not automatically invalid —…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 51262-2017 建设工程造价鉴定规范GB/T 50875-2013 工程造价术语标准2026-09-25 - 04
Whether site instruction and certified records can directly serve as the basis for the final account: statutory status, the four preconditions for 'direct adoption', and the review/recheck mechanism
Site instruction and certified records are among the statutory bases for…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 51262-2017 建设工程造价鉴定规范GB/T 51095-2015 建设工程造价咨询规范2026-09-25 - 05
A site instruction / variation record signed only by the employer: determination of validity and remedying defects (signing with approval vs merely acknowledging receipt)
A site instruction / variation record signed only by the employer is a p…
GB/T 51262-2017 建设工程造价鉴定规范 5.9DB37/T 5130-2018 建设工程造价咨询服务规范 9.3.7/9.3.8GB/T 50875-2013 工程造价术语标准 3.4.82026-09-25 - 06
Site instructions and certified records overview: applicable matters and prohibited items, the five-node handling procedure, graded signing authority, the 2024 standard basis and settlement application
Certification runs a five-node closed loop: assess reasonableness before…
GB/T 50500-2024 建设工程工程量清单计价标准(第7.5、8.6、8.9、8.10、12.2.1条)GB/T 51262-2017 建设工程造价鉴定规范(第5.9节)T/CAEC 006-2024 建筑工程监理文件资料管理标准(第7.2.8、7.2.9条)2026-09-25 - 07
Settlement effect of retrospective site instructions and evidence preservation for verbal instructions: five-attribute review, the 7-day certification rule, and the determination ladder in construction cost expert assessment
Retrospectively certified site instructions are not automatically invali…
GB/T 50500-2024 建设工程工程量清单计价标准 第12.2.1/7.5.5/8.1.3条T/ZBD 100.5-2023 建设工程结算审核作业指引 第2.2.3条GB/T 51262-2017 建设工程造价鉴定规范 第5.4.2/5.9节2026-09-25