Procedure and time limits of site instruction records under GB 50500-2013 section 9.14: written instruction by the employer -> contractor submits the record report within 7 days -> employer verifies and confirms within 48 hours (no confirmation and no comment on lapse is deemed acceptance) -> price computed within 7 days after completion and paid with the progress payment, plus the non-recordable scope and the consequences of proceeding without a record

Under GB 50500-2013 clause 9.14.2, the contractor shall submit the site instruction record report within 7 days of receiving the instruction from the employer, and the employer shall verify the report within 48 hours of receipt and confirm it or comment; 'where the employer neither confirms nor comments within 48 hours of receiving the site instruction record report of the contractor, the site instruction record report submitted by the contractor is deemed accepted'. Clause 9.14.5 provides that within 7 days after the recorded work is completed the contractor shall compute the price from the record content and, after submission to and confirmation by the employer, the price is added to the contract price and paid with the progress payment; clause 9.14.4 provides that where the contractor proceeds without record confirmation by the employer, the cost falls on the contractor unless the written consent of the employer is obtained.

Applicable Codes

  • GB 50500-2013 建设工程工程量清单计价规范 第 9.14.1、9.14.2、9.14.4、9.14.5、9.14.6 条
  • GB/T 50500-2024 建设工程工程量清单计价标准 第 8.11.3、12.2.1 条
  • T/SDJZXH 004.1-2022 城市轨道交通工程监理工作标准(通用篇) 第 10.6.1 条

Topic positioning

Procedure and time limits across the four stages of a site instruction record (works record) - initiation, submission, confirmation and pricing - plus recordable situations, the non-recordable scope and the consequences of proceeding without a record. For analysing whether a record stands at settlement, whether it is out of time, and whether it is deemed accepted.

Core conclusions

1. Initiation and submission (GB 50500-2013 clauses 9.14.1 and 9.14.2)

  • Clause 9.14.1: 'Where the contractor, at the request of the employer, carries out sundry projects outside the contract or work on events not attributable to the contractor, the employer shall promptly issue a written instruction to the contractor and provide the required documents; after receiving the instruction, the contractor shall promptly raise a site instruction record request with the employer.'
  • Clause 9.14.2: 'The contractor shall submit the site instruction record report to the employer within 7 days of receiving the instruction; the employer shall verify the report content within 48 hours of receipt and confirm it or comment. Where the employer neither confirms nor comments within 48 hours of receiving the site instruction record report of the contractor, the site instruction record report submitted by the contractor is deemed accepted.' -> Time chain: written instruction -> record report within 7 days -> verification and confirmation within 48 hours -> no confirmation and no comment on lapse is deemed acceptance.

2. Pricing and payment (clause 9.14.5) 'Within 7 days after the site instruction record work is completed, the contractor shall compute the price according to the record content; after submission to the employer for confirmation, the price is added to the contract price and paid with the progress payment.' -> The recorded price is not settled separately; it is paid with the progress payment.

3. Records where site conditions or ground and hydrological conditions disagree (clause 9.14.6) 'During construction, where the content of the contract works is found inconsistent with the site conditions, the ground and hydrological conditions, or the requirements of the employer, the contractor shall provide the required documents and submit them to the employer for record confirmation, as the basis for adjusting the contract price.'

4. Consequences of proceeding without a record (clause 9.14.4) 'Where a site instruction record matter occurs in the contract works and the contractor proceeds without record confirmation by the employer, the cost incurred shall be borne by the contractor unless the written consent of the employer is obtained.'

5. Non-recordable scope and record content requirements (T/SDJZXH 004.1-2022 clause 10.6.1) The project supervision body shall review the reasonableness of the site instruction record matters submitted for review by the contractor, report them to the employer for confirmation after sign-off by the chief supervising engineer, and the quantities of the recorded matters are confirmed as actually incurred. Beyond contract agreement, the non-recordable scope covers: (1) increases in quantities or rework arising from problems the contractor could have found through normal construction experience or comparison with relevant professional texts but failed to raise before construction; (2) preliminaries the contractor could foresee from construction experience; (3) costs from construction method changes made without the required review and approval procedures; (4) extra costs caused by the contractor itself, such as not building to drawing, unreasonable construction organisation measures or rule violations. A record should state the recorded item, its basis, the calculation process and result; measurement data, sketches and site photos or video should be attached where necessary.

6. The force of a record as a pricing voucher (GB/T 50500-2024 clause 12.2.1) 'The employer and the contractor shall agree in the contract the scope of duties of their respective site management personnel; written documents signed and confirmed by the site management personnel of both parties within their scope of duties shall be valid vouchers for construction pricing, except where other valid evidence proves, or it is proven, that they are false.'

Applicability boundaries

  • The 7-day and 48-hour limits come from GB 50500-2013 section 9.14, which has been replaced by GB/T 50500-2024; follow the new edition or the periods agreed in the contract - the new claim period is 'the period agreed in the contract (28 days where the contract is silent)' (clause 8.11.3), and whether a late notice forfeits the claim is left to the contract. Where the contract sets other record time limits, the contract prevails.
  • 'Deemed acceptance after 48 hours without confirmation' settles procedural effect only, not substantive evidence: the quantities and prices in the record still need support from calculation sheets, drawings and measurement records, or settlement review or cost expert assessment may still refuse to admit them.
  • Discrepancies between site or ground and hydrological conditions and the contract may be recorded; but where they stem from errors in the original data or reference information provided by the employer, they are at the same time employer risk events (GB/T 50500-2024 clause 3.3.2 item 2) and can go through the variation or claim routes; where the contractor should have foreseen them or they are self-inflicted, even a signed record may be found within the non-recordable scope.

Further reading

GB 50500-2013 clauses 9.14.1, 9.14.2, 9.14.4, 9.14.5 and 9.14.6 (full site instruction record flow); GB/T 50500-2024 clause 8.11.3 (periods for the Notice of Claim and claim reports), clause 12.2.1 (valid pricing vouchers); T/SDJZXH 004.1-2022 clause 10.6.1 (site instruction record management and the non-recordable scope).