Identifying and pricing additional works from the settlement-review and construction cost expert assessment perspective: supplementary agreements first, no supplementary agreement does not automatically bind the original contract's pricing principles, rate build-up classified by the original pricing method, and the burden of proof (T/ZBD 100.5-2023 clause 3.1.10; T/ZBD 100.4-2023 clause 4.8.3)

Per T/ZBD 100.5-2023 clause 3.1.10 and T/ZBD 100.4-2023 clause 4.8.3: works executed by the contractor at the employer's instruction outside the contractual scope are reviewed and priced as additional works; where both parties jointly determine the cost, it adjusts as determined; otherwise identification follows the contract-scope level (project or single project -> an added single project; single project -> ancillary works outside scope or independently tenderable specialist works; specialist subcontract -> other specialist works outside scope). Pricing: a supplementary agreement fixing the principles governs; without one and without evidence of agreed principles, the original contract's principles do not automatically apply - additional works lie outside the contract and are free of its price and duration terms, in principle priced at negotiated rates, the contractor bearing the burden of explaining and proving them.

Applicable Codes

  • T/ZBD 100.5-2023 第3.1.10条
  • T/ZBD 100.4-2023 第4.8.3条
  • GB/T 50500-2024 第8.10节
  • GB/T 50500-2024 第7.7.1条

Positioning

From the third-party review and expert assessment standpoint: how works outside the contractual scope are identified, on what principles priced, and who proves what. Basis: T/ZBD 100.5-2023 (settlement review guide) clause 3.1.10 and T/ZBD 100.4-2023 (cost expert assessment guide) clause 4.8.3 - the review-stage landing of GB/T 50500-2024 clause set 8.10.

Core conclusions

1. Identification (3.1.10). Works executed at the employer's instruction outside the agreed scope are reviewed as additional works and the contract price adjusted. Jointly determined costs adjust as determined; failing that, any of the following identifies additional works unless the contract provides otherwise:

  1. contract scope covering a project or single project - an added single project;
  2. scope covering a single project - ancillary works outside scope or specialist works capable of independent tendering;
  3. scope covering a specialist subcontract - other specialist works outside scope.

2. Pricing principles (3.1.10, 4.8.3). Unless the contract provides otherwise: 1) with a supplementary agreement fixing the pricing principles and methods, they govern; 2) without one and without evidence of agreed principles, the original contract's principles do not automatically apply. Assessment note: additional works lie outside the contract and are not bound by its price and duration terms; the parties may or may not adopt the contract rates, or adjust them; the additional works are in principle priced at rates negotiated between contractor and employer, the contractor bearing the burden of necessary proof and explanation for any adjusted rate.

3. Rate build-up classified by the original pricing method (3.1.10).

  1. Original contract priced on industry or local budget quotas: reference the corresponding quotas; where the contractor claims the supporting fee norms' rates, adopt a reasonable rate after comparing quota-matching rates with the contract's rates, explaining in the review report.
  2. BOQ-priced original contract: analyse on the applicable all-in unit rates of the original work items and compute the preliminaries caused by the additional works on the facts and evidence.
  3. Claiming rate adjustment: prove the unit prices of labour, materials and plant (or hire), analyse the price difference between the additional-works period and the original contract date, and adjust the factor prices.
  4. Claiming adjusted consumption or price levels in the rate build-up: weigh the original quantities against the additional works' scale and analyse the necessity and reasonableness of the adjustment.
  5. Contractor claiming that competitive tendering left the original rates below the then-market level, making continuation plainly unreasonable or loss-making: require reasons and evidence; a rate adjustment factor may be reasonably considered.
  6. Lump-sum original contract without priced bid detail: the contractor proves the composition - labour, materials, plant, overheads, profit - and the price is fixed after analysing its reasonableness.

4. Review / assessment method. Characterise first (outside-scope additional works by scope level), then fix the pricing principle (supplementary agreement > negotiation > reference to the original contract), then the build-up method (by the original pricing method); the burden lies on the claiming party; the opinion must state the reasons for every rate and price chosen.

Applicable boundaries

Applies at settlement review and expert assessment for works outside the agreed scope, and by reference to party negotiation. Preconditions: "outside the agreed scope" and "at the employer's instruction"; in-scope variations, BOQ errors and quantity deviations run under GB/T 50500-2024 clause sets 8.9 and 8.2 - never the additional-works basis. Express contractual terms on additional works govern; the two T/ZBD guides are industry practice aids, not substitutes for contract or national standards.

Further reading

T/ZBD 100.5-2023 clause 3.1.10; T/ZBD 100.4-2023 clauses 4.8.3-4.8.4; GB/T 50500-2024 clauses 8.10.1~8.10.5, 7.7.1, clause set 8.9; and the contract's particular conditions on out-of-scope works, dayworks and provisional sums.