Determining the all-in unit rate of additional works (outside the contract-agreed scope of works) (GB/T 50500-2024 Section 8.10)

The all-in unit rate of additional works follows the dual path of 'contract unit rates first, negotiated rate build-up as fallback': (1) list and measure per the contract-agreed measurement and pricing rules, and price by combining contract unit rates and tender price levels; (2) where no applicable unit rate exists, the employer and contractor renegotiate the measurement and pricing rules. Conversion of contract unit rates must consider four factor groups: labour/material/machinery price differences, bulk-procurement effects, correction of under/over-priced items, and differences between competition-formed and negotiated rates; before implementation, submit the quotation for review and sign a supplementary agreement before proceeding; further variations to additional works are priced per Section 8.9, and Clauses 8.2.2/8.2.3 (BOQ errors/omissions) should not apply. Construction cost expert assessment (judicial appraisal) position: works outside the contract are not necessarily bound by the original contract; the contractor bears the burden of proof.

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准 第8.10.1~8.10.6条、第8.7节、第8.8节、第8.9节、第7.7.1条
  • T/ZBD 100.4-2023 建设工程造价鉴定作业指引 第4.8.3条、第4.8.4条

Topic Positioning

This card covers how the all-in unit rate of 'additional works' outside the contract-agreed scope of works is determined — the dual path of 'contract unit rates first, negotiated rate build-up as fallback' of GB/T 50500-2024 Section 8.10, the differing factors for converting contract unit rates, procedural requirements, plus the construction cost expert assessment (judicial appraisal) position.

Core Conclusions

  • Dual path (8.10.1): (1) list and measure per the national and industry measurement standards and supplementary calculation rules agreed in the contract, and compute the price of additional works by combining contract unit rates and tender price levels; (2) the employer and contractor renegotiate the measurement and pricing rules. The contractor may compile a BOQ for the additional works and quote prices; the preliminaries in the BOQ shall include costs for extended-use or newly added preliminary items.
  • Conversion of contract unit rates (8.10.3) must consider four differing factors: differences between labour/material/machinery unit rates and the market-reasonable prices at the time the additional works are executed; bulk or small-quantity procurement effects caused by quantity differences; correction of contract unit rates that are too low or too high; differences between competition-formed contract unit rates and negotiated rates.
  • Procedure (8.10.2, 8.10.6): before implementation the contractor submits the project execution plan (construction methodology and site organization)/implementation scheme, programme, and quotation (divisional/sub-divisional + bill of preliminaries) for the employer's review; it is recommended to first negotiate the duration, unit rates, and total price of the additional works and sign a supplementary agreement before implementing.
  • Further variations to the additional works themselves (8.10.5): priced per the all-in unit rates in the employer-reviewed quotation and the Section 8.9 rules; Clauses 8.2.2 and 8.2.3 (BOQ error/omission price adjustment) should not be applied to additional works pricing.
  • Construction cost expert assessment (judicial appraisal) position (T/ZBD 100.4-2023): additional works are works outside the contract, not necessarily bound by the original contract's price and duration agreements; whether to adopt or adjust contract unit rates may be negotiated, with the contractor bearing the burden of proof and explanation — claiming a price adjustment requires proving the differences between factor prices at execution and at signing.

Applicable Boundaries

Applies only to 'additional works' outside the contract-agreed scope of works. Variations to works within the contract scope and BOQ errors/omissions are handled per Section 8.9 and Section 8.2 respectively — this card's dual path does not apply. Procedurally it emphasizes review of the quotation before implementation and signing before construction; 'build first, negotiate later' easily breeds pricing disputes. This card is rule-based knowledge and contains no specific amounts or factor prices.

Further Reading

GB/T 50500-2024 Clauses 8.10.1-8.10.6 (additional works pricing), Clauses 8.9.1-8.9.3 (three-tier pricing of variations with identical/similar/different characteristics), Clause 7.7.1 (measurement of additional works); T/ZBD 100.4-2023 Clauses 4.8.3, 4.8.4 (construction cost expert assessment (judicial appraisal) of additional works).

Keywords

  • 新增工程计价
  • GB/T 50500-2024 第8.10节
  • 合同单价差异因素
  • 协商组价
  • 新增工程变更计价
  • 报价单审定
  • 合同外工程鉴定