How to build up rates for additional works with no applicable quota norms: the progressive path of apply → convert → cost-plus-profit → market price enquiry
For additional works or variation items with no quota norms to apply, rate build-up follows the progression "identical items use the contract unit rate → similar items are converted and adjusted → quota norms for similar technology are adjusted in applying quota items, or supplementary quota items are compiled → rates are re-derived on a cost-plus-profit basis → confirmed by market price enquiry → a supplementary agreement is negotiated and signed by both parties"; the order of price sources is contract-agreed information sources → published price information (government guidance prices) issued by the construction cost administration or industry bodies (tax-exclusive) → contractor procurement unit prices confirmed by both parties; additional works are works outside the contract and are not necessarily bound by the original contract unit rates — submit for review before implementation, with the contractor bearing the burden of proof.
Applicable Codes
- GB/T 50500-2024 第8.9节、第8.10节、第8.6.3条
- GB/T 50319-2013 第6.3.3条
- T/ZBD 100.4-2023 第4.6.2、4.8.3、4.8.4条
- T/ZBD 100.5-2023 第3.1.10条
- DL/T 5464-2013 第4.1.5条
- DB11/T 1597-2018 第5.4.8条
- DB37/T 5028-2022 第9.3.2条
Topic Positioning
This card answers "how to build up rates for additional works / variation items with no applicable quota norms", setting out the progressive path of apply first → then convert → then negotiate → finally fall back, together with the order of price sources and the procedural requirements. It applies to BOQ-based pricing and construction cost expert assessment (judicial appraisal) scenarios where the quota manuals have no item and no similar sub-item can be applied.
Core Conclusions
- Identical/similar items first: where the priced BOQ or the contract contains identical items, the contract unit rate applies; where there is no identical item but a similar one exists, convert and adjust by reference to the similar unit rate (GB/T 50500-2024 Clause 8.9.1; the same approach applies for supervision, GB/T 50319-2013 Clause 6.3.3, DB37/T 5028-2022 Clause 9.3.2).
- Work items not covered by the quota manuals: prefer adjustment in applying quota norms for similar construction technology; where no similar sub-item exists, compile supplementary quota items from similar-project data and use them after approval by the industry quota administration (DL/T 5464-2013 Clause 4.1.5).
- Cost-plus-profit fallback: where neither identical nor similar items exist, compute the reasonable cost from the materials submitted by the contractor and add the contract-agreed management-fee and profit percentage rates to determine the new all-in unit rate (T/ZBD 100.4-2023 Clause 4.6.2).
- Order of price sources: contract-agreed market-price information sources → price information published by the construction cost administration at the project location or by industry bodies (tax-exclusive) → contractor procurement unit prices confirmed by both parties (GB/T 50500-2024 Clause 8.6.3); where no similar quota norms exist, it is preferable to build up rates on the basis of market prices (DB11/T 1597-2018 Clause 5.4.8).
- Procedure: additional works are works outside the contract and are not necessarily bound by the original contract unit rates; in principle the rates are determined by negotiation, with the contractor bearing the burden of proof; before implementation, submit the construction method statement, the programme (of works) and the quotation for the employer's review, and implement only after negotiating the duration, unit rates and total price and signing a supplementary agreement (T/ZBD 100.4-2023 Clause 4.8.3; GB/T 50500-2024 Clauses 8.10.2, 8.10.6).
Applicable Boundaries
Applies to variations, additional works, dayworks and other scenarios with no quota norms to apply; where quota line items exist and the work content is already synthesized, this path must not be taken directly (first judge whether conversion is possible); where the original contract stipulates that unit rates are not to be adjusted or agrees on adjustment rules, the contract governs, and construction cost expert assessment (judicial appraisal) likewise gives priority to the contract.
Further Reading
See GB/T 50500-2024 Section 8.9 (determining the all-in unit rate), Section 8.10 (additional works), Clause 8.6.3 (dayworks rate build-up); T/ZBD 100.4-2023 Clauses 4.6.2, 4.8.3, 4.8.4; T/ZBD 100.5-2023 Clause 3.1.10; GB/T 50319-2013 Clause 6.3.3; DL/T 5464-2013 Clause 4.1.5; DB11/T 1597-2018 Clause 5.4.8. For consumption measurement and base-price composition of supplementary unit-rate build-up schedules, see the related cards on compiling supplementary quota items.
Keywords
- 无定额组价
- 新增项目组价
- 成本加利润
- supplementary quota items
- 工程变更组价
- market price enquiry
- 综合单价确定
- 合同外工程