final account review
Concept Guide
Concept
Final account review (结算审核, jiesuan shenhe) is a China-specific stage in construction contract administration. After completion (or completion of a defined stage), the contractor submits a final account statement, and the employer — or a cost consultancy engaged by the employer — reviews and verifies it to fix the final amount payable. The default arrangement under Chinese construction contracts is employer-led settlement: the contractor submits, the employer reviews within an agreed period, and the review conclusion becomes the payment basis.
Three features matter. First, the reviewing body varies: the employer itself, an engaged cost consultancy, or — for government-invested projects — a finance review or government audit body. Second, review is not merely confirmatory; it routinely produces disallowances (结算核减) on quantities, rates, fees and variation claims, and the size of those downward adjustments is the main source of dispute. Third, time limits and deemed acceptance: contracts and local rules often provide that if the employer fails to respond within the stipulated period, the contractor's submitted amount is deemed accepted — turning a technical exercise into a legally time-bound act.
A distinctively Chinese controversy is "audit as the basis" (以审计为准): where public funds are involved, employers often argue that the government audit conclusion governs the final account. Chinese judicial practice generally holds that an audit conclusion does not bind the civil settlement relationship unless the contract expressly says so. Final account review therefore serves three functions at once — contract performance, fiscal supervision and dispute prevention — which places it on a different institutional track from FIDIC's engineer-centred determination.
FIDIC Mapping
FIDIC contracts contain no equivalent institutional layer. At completion, the contractor submits a Statement at Completion and a draft Final Statement; the Engineer agrees or determines matters under the Contract, and the Employer makes payment against the Final Payment Certificate. Disagreement with the Engineer's agreement or determination goes to the DAAB and then to arbitration — not to an employer's unilateral review.
Term mapping and key differences:
- 竣工结算 (final account) → final account: in FIDIC terms this is better understood as the Final Statement plus Final Payment Certificate package, not an employer's unilateral review conclusion.
- 结算核减 (disallowance / downward adjustment on review): under FIDIC any deduction must rest on the Contract and on the Engineer's agreement or determination; the Employer cannot deduct under the label of an administrative review.
- 视为认可 (deemed acceptance / deemed approval): FIDIC has no deemed-submission or deemed-approval mechanism for the Final Statement (Sub-Clauses 14.11 and 14.12 contain no silence fiction); its deemed mechanics run the other way (Sub-Clause 3.7 deems a determination rejecting the claim; Sub-Clause 10.2 deems issue of the Taking-Over Certificate).
- 施工过程结算 (interim settlement by construction stage): the FIDIC analogue is interim payment on a periodic basis, not settlement by "construction stage".
Usage warning: translating 结算审核 as "audit" or "government audit" misleads English readers into assuming third-party administrative audit of contract pricing. Under FIDIC, pricing disputes are resolved by the Engineer's determination, subject to DAAB and arbitration; the Employer cannot unilaterally alter determined contractual rights under the guise of a review. If the parties intend a government audit conclusion to govern final payment, that must be expressly stated in the English contract; otherwise it is unlikely to be upheld in a FIDIC context.
| Chinese Term | English Term | FIDIC Term | Relation | Notes |
|---|---|---|---|---|
| 结算审核 | final account review | Engineer's agreement or determination (final account stage) | absent | FIDIC 无政府审计或发包人单方审核介入合同价款确定的制度层,竣工价款由工程师商定或确定,争议进入 DAAB 与仲裁。 |
| 竣工结算 | final account | Final Statement / Final Payment Certificate | adjacent | FIDIC 侧是承包人提交最终报表(Final Statement)、经工程师核认后由雇主按最终付款证书支付的组合,而非发包人单方审核结论。 |
| 结算核减 | disallowance / downward adjustment on review | deduction under the Contract following agreement or determination | adjacent | FIDIC 侧扣减须以合同约定和工程师商定或确定为依据,不能以行政审查名义单方扣减。 |
| 视为认可 | deemed acceptance / deemed approval | 无对应机制;近缘沉默拟制见 Sub-Clause 3.7(逾期视为驳回索赔的确定)、10.2(视为颁发接收证书)、20.2.2(逾期通知异议)——均非最终结算审批拟制 | adjacent | FIDIC 无最终报表「视为提交/视为批准」机制(14.11/14.12 无沉默拟制);工程师侧沉默拟制(3.7 等)方向为驳回主张而非认可主张,受益方与中国规则相反。 |
Updated 2026-09-13
- 01
Rules for handling contract price adjustment for cost fluctuation in final account review and construction cost expert assessment: routing by contract type, price-dating principles for delay periods, the exception for government-priced materials, and the eight categories of costs not adjusted for changes in costs listed in GB/T 50500-2024 clause 8.7.6
Final account review and expert assessment proceed on two levels. (i) Ro…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第3.3.6条、第8.7.2条、第8.7.3条、第8.7.6条GB/T 51262-2017 · Code for Construction Cost Appraisal 第5.6.2条T/ZBD 100.5-2023 · Work Guideline for Settlement Audit of Construction Works 第3.1.7条2026-10-29 - 02
Identifying and pricing additional works from the settlement-review and construction cost expert assessment perspective: supplementary agreements first, no supplementary agreement does not automatically bind the original contract's pricing principles, rate build-up classified by the original pricing method, and the burden of proof (T/ZBD 100.5-2023 clause 3.1.10; T/ZBD 100.4-2023 clause 4.8.3)
Per T/ZBD 100.5-2023 clause 3.1.10 and T/ZBD 100.4-2023 clause 4.8.3: wo…
T/ZBD 100.5-2023 第3.1.10条T/ZBD 100.4-2023 第4.8.3条GB/T 50500-2024 第8.10节2026-10-18 - 03
Pricing channels for works outside the contract scope and unforeseen works: recognising and pricing additional works, when dayworks apply, and the rules for using provisional sums
Where the contractor, at the employer's request, completes additional wo…
GB/T 50500-2024 建设工程工程量清单计价标准 第8.10.1条GB/T 50500-2024 第7.5.2条GB/T 50500-2024 第8.3.2条2026-09-26 - 04
The five-dimension method for systematically checking design changes at final account: four-way reconciliation across ledger, drawings, settlement, and site
Checking design changes at final account uses "ledger - drawings - settl…
T/ZBD 100.5-2023 建设工程结算审核作业指引DB37/T 5130-2018 建设工程造价咨询服务规范GB/T 50500-2024 建设工程工程量清单计价标准2026-09-25 - 05
Impact of incomplete signatures on construction documents on final account payment, and remediation paths
Incomplete signatures do not void the final account as a whole, but the…
T ZBD 100.5-2023 建设工程结算审核作业指引GB/T 50500-2024 建设工程工程量清单计价标准DB62/T 25-3016 建筑工程资料管理规程2026-09-25 - 06
Bases for determining final account quantities: completed qualifying quantities + measurement certification and sign-off lock-in + measurement method by contract type
The final account quantity (in FIDIC contexts, the Final Statement plus…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 51095-2015 建设工程造价咨询规范GB/T 50326-2017 建设工程项目管理规范2026-09-25 - 07
Mandatory review checklist for final account review deliverables (T/ZBD 100.5-2023 clause 5.0.11, 14 items)
Final account review deliverable review follows T/ZBD 100.5-2023 5.0.11'…
T/ZBD 100.5-2023 建设工程结算审核作业指引2026-09-25 - 08
The role of as-built drawings in construction payment settlement: statutory basis status and graphical benchmark for audit quantity checks
As-built drawings are a statutory basis for the final account and the gr…
GB/T 50326-2017GB/T 51095-2015GB/T 50328-20142026-09-25 - 09
Correction windows and settlement handling for obviously abnormal (over-high/over-low) tendered all-in unit rates: tender-stage clarification/rejection vs settlement-stage contract price lock-in
The correction window for abnormal unit prices (incl. unbalanced bidding…
GB/T 50500-2024 建设工程工程量清单计价标准 第3.5.3、6.1.2、6.1.11、8.9.1、8.9.2条T/ZBD 100.5-2023 建设工程结算审核作业指引 第3.1.6条铁路工程建设项目招标投标管理办法(交通运输部令2018年第13号)第三十二条2026-09-25 - 10
Settlement review vs fiscal appraisal vs audit: subject, nature, object, and effect
The final account is a civil-contract act of employer and contractor (ch…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 51095-2015 建设工程造价咨询规范最高人民法院〔2008〕民一他字第4号答复2026-09-25 - 11
Claim costs in the final account: settlement line item + 28-day procedure chain + review and determination rules
Claim costs enter the final account only where both procedural complianc…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 51262-2017 建设工程造价鉴定规范DBJ41/T 208-2018 建设工程监理工作标准2026-09-25 - 12
Identifying duplicate measurement in subcontract final accounts: a four-layer investigation method — contract interfaces, stage settlements during construction, measurement rules, and cost composition
Identify duplicate measurement in subcontract final accounts by investig…
T/ZBD 100.5-2023 工程结算审核作业指引GB/T 50500-2024 建设工程工程量清单计价标准DB37/T 5130-2018 建设工程造价咨询服务规范2026-09-25 - 13
Final account: basis of preparation, review essentials, and review time limits (a cross-standard summary)
Final account basis of preparation centres on contract documents, as-bui…
GB/T 51095-2015 建设工程造价咨询规范GB/T 50326-2017 建设工程项目管理规范DB37/T 5130-2018 建设工程造价咨询服务规范2026-09-25 - 14
Document verification in subcontract final account disputes: a five-tier order of evidentiary weight (contract sets the tone → certification and sign-off lock quantities → drawings verify quantities → price evidence verifies prices → supporting evidence validates)
Documents in subcontract final account disputes are checked in tiers of…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 51262-2017 建设工程造价鉴定规范T/ZBD 100.4-2023 建设工程造价鉴定作业指引2026-09-25 - 15
Six-step method for reviewing the reasonableness of all-in unit rates: rate build-up basis -> labour/materials/plant -> on-costs -> special items -> horizontal comparison -> arithmetic
Reviewing an all-in unit rate means breaking down and verifying the thre…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 51095-2015 建设工程造价咨询规范T/ZBD 100.5-2023 建设工程结算审核作业指引2026-09-25 - 16
Can final account review/audit adjust awarded all-in unit rates? — rate locking under re-measurable contracts, statutory exceptions, and the limits of audit authority
In principle, no. Under a re-measurable (unit-rate) contract, awarded al…
T/ZBD 100.5-2023 · Work Guideline for Settlement Audit of Construction Works 第1.1.7条、第3.1.6条GB/T 51095-2015 · Code for construction cost consultation 第8.2.5条GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.1.1条、第8.2.1条、第8.9.1条、第8.9.2条、第10.3.10条、第10.3.12条2026-09-25 - 17
Settlement effect of retrospective site instructions and evidence preservation for verbal instructions: five-attribute review, the 7-day certification rule, and the determination ladder in construction cost expert assessment
Retrospectively certified site instructions are not automatically invali…
GB/T 50500-2024 建设工程工程量清单计价标准 第12.2.1/7.5.5/8.1.3条T/ZBD 100.5-2023 建设工程结算审核作业指引 第2.2.3条GB/T 51262-2017 建设工程造价鉴定规范 第5.4.2/5.9节2026-09-25 - 18
Master framework for cost review, re-check, and anomaly identification: the cross-footing main line, three-layer progression, six focus points, and three axioms
The first principle of anomaly identification is the cross-footing relat…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 51095-2015 建设工程造价咨询规范GB/T 51262-2017 建设工程造价鉴定规范2026-09-25