Final account: basis of preparation, review essentials, and review time limits (a cross-standard summary)

Final account basis of preparation centres on contract documents, as-built drawings and variation documents, pricing documents and the bill of quantities (BOQ), and site instructions/variation records and claim materials — cross-standard checklists agree; preparation methods differ by contract type (lump-sum/re-measurable (unit-rate)/cost-plus-fee); review focuses on authenticity and accuracy, method of measurement, fee recovery and taxes and duties (VAT under the current standard), employer-supplied (free-issue) materials, price adjustment, and the reasonableness of variations and site instructions/variation records; the employer's failure to respond within the final account review period is deemed acceptance, 28 days absent contractual agreement (Ministry of Construction Order No. 107, Article 16); the review period runs from receipt of complete final account materials (Cai Jian [2004] No. 369, Article 16).

Applicable Codes

  • GB/T 51095-2015 建设工程造价咨询规范
  • GB/T 50326-2017 建设工程项目管理规范
  • DB37/T 5130-2018 建设工程造价咨询服务规范
  • DB42/T 823-2021 建设工程造价咨询质量控制规范
  • 财建〔2004〕369号 建设工程价款结算暂行办法
  • 建设部令第107号 建筑工程施工发包与承包计价管理办法

Topic Positioning

The basis checklist, contract-type-specific preparation methods, and review time limits for final account preparation and review — for final account preparation, review, and cost consultancy practice.

Core Conclusions

(1) Basis of preparation: contract documents; as-built drawings and variation documents; technical data and approved material-substitution documents; pricing documents and the BOQ; site instructions/variation records and claim materials confirmed by both parties (GB/T 50326-2017, Clause 18.3.3); extended to laws and regulations, construction/subcontract/procurement contracts, tender documents, construction drawings and as-built drawings, approved project execution plans (construction methodology and site organization), design changes/negotiations/claims/site instructions and variation records, meeting minutes, material/equipment price-confirmation sheets, mutually confirmed added or deducted amounts, and commencement/completion and suspension/resumption reports (GB/T 51095-2015, Clause 8.2.4; DB37/T 5130-2018, Clause 8.2.4; DB42/T 823-2021, Clause 8.2.3). (2) Preparation by contract type: lump-sum contracts adjust the contract price for the agreed adjustable contents; re-measurable (unit-rate) contracts keep all-in unit rates fixed within the agreed risk range and measure/price per actually completed quantities; cost-plus-fee contracts compute cost, fee, and taxes and duties per the agreed method (DB42/T 823-2021, Clause 8.2.4). (3) Review essentials: authenticity, accuracy, and completeness of deliverables; execution against the preliminary estimate; conformity with the method of measurement; compliance of quota norms selection and application, fee recovery, and taxes and duties; consistency of employer-supplied (free-issue) materials with the design; material prices adjusted per contract; consistency of the final account with as-built drawings/site instructions and variation records; reasonableness of major variations, site instructions/variation records, and claims (DB37/T 5130-2018, Clause 8.3.8). (4) Review time limits: the employer checks and reviews within the prescribed or agreed period after receiving the final account report and complete final account materials; failure to respond within the prescribed time is deemed acceptance, the period running from the cost consultancy's receipt of complete materials (Cai Jian [2004] No. 369, Article 16); absent contractual agreement, the agreed time limits for every stage—submission, response, negotiation and review—are all deemed to be 28 days, and the employer's failure to respond within the prescribed time is deemed acceptance of the final account documents (Ministry of Construction Order No. 107, Article 16).

Applicable Boundaries

Applies to final account of general contracting works in building construction and municipal engineering; contract agreements prevail; completeness of final account materials is the precondition for the review period — incomplete materials must first be submitted for verification and completed/corrected; where local provisions are more detailed, they prevail.

Further Reading

GB/T 51095-2015, Clauses 8.2.2 (final account document composition, per Appendix F), 8.2.4, 8.3.4; GB/T 50326-2017, Clause 18.3.3; DB37/T 5130-2018, Clauses 8.2.4, 8.3.8; DB42/T 823-2021, Clauses 8.1.8, 8.2.3, 8.2.4; Cai Jian [2004] No. 369, Article 16; Ministry of Construction Order No. 107, Article 16.