Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Order of application of pricing bases for the final account: contract agreement first (agreed terms prevail); quota norms and construction cost management agency's pricing bases as fallback

Final account prices take the contract as the fundamental basis: pricing activities follow "statutory priority, agreed terms prevail" (GB/T 50500-2024 Clause 1.0.3) — where the contract provides for price determination, adjustment methods, and quantity calculation rules, the agreed terms prevail; only absent or unclear agreement are national, industry, and local pricing bases (including quota norms) referenced (T/ZBD 100.5-2023 Clause 1.4.2). In construction cost expert assessment (judicial appraisal) of price disputes, the fallback order is fair market price → pricing quota norms → cost data + on-cost level (T/ZBD 100.4-2023 Clause 3.1.6).

Applicable Codes

  • GB/T 50500-2024 建设工程工程量清单计价标准
  • T/ZBD 100.5-2023 建设工程结算审核作业指引
  • T/ZBD 100.4-2023 建设工程造价鉴定作业指引
  • DB42 T 823—2021 建设工程造价咨询质量控制规范
  • 建设部令第107号 建筑工程施工发包与承包计价管理办法

Topic Positioning

The order of application of pricing bases for the final account: contract first, quota norms as fallback — reusable for final account preparation, review, and dispute handling.

Core Conclusions

(1) Master principle "statutory priority, agreed terms prevail" (GB/T 50500-2024 Clause 1.0.3): where the contract provides, it governs — the contract is the fundamental basis for the final account; quota norms are not a parallel option. (2) Where the contract provides for price determination, adjustment methods, and quantity calculation rules, the agreed terms prevail; only absent or unclear agreement are national, industry, and local pricing bases (including quota norms) referenced (T/ZBD 100.5-2023 Clause 1.4.2). (3) Where the contract prices by quota norms + published price information (government guidance prices), the quota norms' force derives from the contract — still "by agreement". (4) The final account price leads with the contract BOQ total, followed by adjustments for errors and omissions in the BOQ, provisional sums, price/regulation changes, variations, claims, liquidated damages, etc. (Clause 10.3.2). (5) Construction cost expert assessment (judicial appraisal) fallback: fair market price → pricing quota norms → cost data + market on-cost level (T/ZBD 100.4-2023 Clause 3.1.6).

Applicable Boundaries

For final account "basis selection"; contract terms violating mandatory provisions or departing materially from the tender's substantive content are invalid, reverting to statutory bases; compilation methods vary by contract type (lump-sum / re-measurable (unit-rate) / cost-plus). Adjustment formulas, measurement rules, and procedural deadlines are out of scope.

Further Reading

GB/T 50500-2024 Clauses 1.0.3, 10.3.1-10.3.4; T/ZBD 100.5-2023 Clause 1.4.2; T/ZBD 100.4-2023 Clause 3.1.6; DB42/T 823-2021 Clause 8.2.4; Ministry of Construction Order No. 107 Article 16.