Measurement of the works rules in Chapter 8 of GB 50500-2013: measurement basis and mandatory provisions, verification of completed-works quantity reports and deemed approval upon lapse of the period, notice procedure for on-site measurement and consequences of absence, and review of objections to measurement results
Chapter 8 of GB 50500-2013: quantities must be calculated under the rules of measurement of the current national measurement codes and determined by the quantities of the work the contractor has actually completed and that are to be measured (clauses 8.1.1 and 8.2.1 are mandatory provisions; tender BOQ quantities are only estimates). The contractor submits the completed-works quantity report each agreed period; the employer verifies within 7 days of receipt and notifies the contractor; where verification is not done within the agreed time, the quantities in the report are deemed the quantities actually completed by the contractor (8.2.3). On-site measurement verification requires notice to the contractor 24 hours before measurement; if the contractor is absent it is deemed to approve the employer's verification result, and if the employer fails to notify as agreed so that the contractor cannot attend, the verification result is invalid (8.2.4). A contractor disputing the verified result must raise written objections within 7 days of notice with calculation records attached, and the employer reviews within 7 days; continuing disputes follow the contract's dispute resolution (8.2.5). Under the current GB/T 50500-2024, clauses 7.1.7 and 7.1.8: measurement results signed and confirmed by both parties serve as the basis for contract price adjustment and settlement.
Applicable Codes
- GB 50500-2013 建设工程工程量清单计价规范(第8.1.1、8.2.1、8.2.3、8.2.4、8.2.5条)
- GB/T 50500-2024 建设工程工程量清单计价标准(第7.1.7、7.1.8条)
Topic Positioning
This card organises the provisions on measurement of the works in Chapter 8 of GB 50500-2013: the mandatory measurement basis (calculation under the rules of the current national measurement codes, determination by quantities actually completed and to be measured), the verification period for completed-works quantity reports and deemed approval upon lapse of the period, the notice procedure and absence consequences of on-site measurement verification, the two-level review of objections to measurement results, and the current GB/T 50500-2024 rules on the effect of signed measurement results.
Core Conclusions
1. Mandatory measurement basis (two mandatory provisions)
- Clause 8.1.1: 'Quantities must be calculated under the rules of measurement set by the current national measurement code applicable to the relevant works.' Commentary: correct measurement is the precondition and basis of the employer's payment of the contract price to the contractor; the clause makes clear that whatever the pricing method, quantities must be calculated under those rules. This is a mandatory provision and must be strictly executed.
- Clause 8.2.1: 'Quantities must be determined by the quantities of the contract works that the contractor has completed and that are to be measured.' Key commentary points: the quantities listed in the tender BOQ are estimated quantities, at once the common basis of tenderers' pricing and the common platform of tender review; the quantities for the final account between employer and contractor are determined by the quantities actually completed and to be measured, calculated under the rules of measurement of the current national measurement codes, not by the quantities listed in the tender BOQ. This is a mandatory provision and must be strictly executed.
2. Measurement procedure and consequences of lapse
- Report and verification (clause 8.2.3): 'The contractor shall submit the completed-works quantity report for the period to the employer at the measurement period and time agreed in the contract. The employer shall verify within 7 days of receipt and notify the contractor of the verified measurement result. Where the employer does not verify within the agreed time, the quantities listed in the contractor's measurement report are deemed the quantities actually completed by the contractor.'
- On-site measurement verification (clause 8.2.4): 'Where the employer considers on-site measurement verification necessary, it shall notify the contractor 24 hours before the measurement; the contractor shall provide conveniences for the measurement and send personnel to attend. Where both parties agree the verification result, both shall sign and confirm the record. If the contractor, after receiving the notice, sends no one to attend the measurement, it is deemed to approve the employer's verified measurement result. If the employer fails to notify the contractor at the agreed time so that the contractor cannot attend, the verified measurement result is invalid.' The notice procedure is a two-way check: contractor absence means deemed approval; employer failure to notify invalidates the result.
- Objection to measurement results (clause 8.2.5): 'Where the contractor considers the employer's verified measurement result wrong, it shall submit written comments to the employer within 7 days of receiving the result notice, attaching the measurement result it considers correct and detailed calculation records. On receiving the written comments, the employer shall review the contractor's measurement result within 7 days and notify the contractor. Where the contractor still objects to the reviewed result, the dispute is handled under the method agreed in the contract.'
3. Current standard position (GB/T 50500-2024)
- Clause 7.1.7: 'The employer and the contractor shall sign and confirm the measurement results of the relevant works on which agreement is reached. Where checking, review and re-examination still fail to produce agreement, the dispute may be resolved under the method set in Chapter 11 of this standard.'
- Clause 7.1.8: 'The measurement results of the works signed and confirmed by the employer and the contractor serve as the basis of contract price adjustment and works settlement, except where the contract provides otherwise, or the parties expressly limit them to the basis of progress payment, or the measurement results are rough estimates.' That is, signed measurement results in principle lock in the settlement basis, the only exceptions being contrary contract terms, express limitation to progress payment, and rough estimates.
Applicability Boundaries
- The 7-day and 24-hour periods of clauses 8.2.3-8.2.5 presuppose the measurement period and times agreed in the contract, and specific days may be agreed otherwise; invoking deemed approval upon lapse against an employer in practice depends on whether the contract expressly agrees the implied term and on judicial attitudes to it.
- Deemed approval of quantities upon lapse in measurement and deemed approval of the submitted price where the employer fails to answer final account documents in time are two different levels of question: the latter must meet the three requirements of Article 21 of Fa Shi [2020] No. 25, and implied approval in measurement cannot directly extend to approval of the whole settlement price.
- Measurement settles the factual confirmation of quantity, not rates or charges; the same measurement confirmation cannot replace the price confirmation of a site instruction record, nor does it waive the valuation procedure for site instruction records and variations.
- This card covers BOQ-based pricing only; under lump-sum contracts only the agreed adjustable content is measured, and cost-plus contracts are charged by the agreed method.
Further Reading
- GB 50500-2013, code of valuation with bill of quantities: clause 8.1.1 (mandatory rules of measurement), clause 8.2.1 (determination by quantities actually completed and to be measured), clause 8.2.3 (report submission, 7-day verification, deemed approval upon lapse), clause 8.2.4 (on-site verification, 24-hour notice, consequences of absence and of no notice), clause 8.2.5 (7-day written objection and 7-day review).
- GB/T 50500-2024, standard for valuation with bill of quantities: clauses 7.1.7 and 7.1.8 (signing confirmation of measurement results, their effect and exceptions as settlement basis), Chapter 11 (dispute resolution).
- Companion reading: section 9.14 of GB 50500-2013 (site instruction record procedure); Chapter 5 of GB/T 51262-2017, code for construction cost expert assessment (assessment of measurement disputes); clause 4.3.6 of T/ZBD 100.4-2023 (ranking of signed confirmations in quantity dispute assessment).
- Article 21 of Fa Shi [2020] No. 25 of the Supreme People's Court (three requirements for deemed approval of final account documents upon failure to answer in time).
Keywords
- measurement of the works
- 已完工程量报告
- deemed approval upon lapse of the response period
- 计量核实
- 计量核实结果无效
- 计量成果签认
- mandatory provisions of codes
- GB 50500-2013 第8章