Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

Composition of progress-payment application documents and the submission-signoff procedure (GB/T 50500-2024 §9.4, Appendix F; T11 IESB 0001-2017 Tables 4.1.8/4.1.11; GB/T 50319-2013 §5.3.1)

Application documents fall into four blocks: (1) forms (the Progress Payment Application (Approval) Form F.3.1 in quadruplicate, signed and sealed by the compiler and a Level-1 registered cost engineer + the supervision review form); (2) measurement documents (supervision-signed qualifying completed quantities, BOQ statistical reports, physical progress, quality acceptance; the T11 IESB 0001-2017 caliber: the measurement period runs from the 26th of the previous month to the 25th of the current month, reported by the 26th); (3) price computation (six items: the cumulative completed value of 11 components + cumulative recovered advances + cumulative payable + prior cumulative payments + employer deductions + current payable; the applied amount = in-contract price + change additions/reductions + approved claims - advance/retention and other deductions); (4) construction workers' wages listed separately (wage sheets self-signed; labor-cost disbursement at most monthly). Procedure: contractor submits -> specialty supervision rechecks quantities -> chief supervision engineer endorses for employer approval -> chief supervision engineer issues the payment certificate; disputed items paid first on undisputed parts.

Applicable Codes

  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第9.4.9条、第9.4.11条、App. FTable F.3.1
  • T11 IESB 0001-2017《建筑电气工程施工资料管理规程》表4.1.8、表4.1.11
  • GB/T 50319-2013 · Code for Construction Project Supervision 第5.3.1条
  • 《保障农民工工资支付条例》(国务院令第724号)第24、26、29、31、35条

Topic Positioning

The documents a contractor must submit for progress-payment (interim payment) applications, the measurement-period caliber, and the supervision sign-off procedure, per GB/T 50500-2024 Chapter 9 and Appendix F, T11 IESB 0001-2017 Tables 4.1.8/4.1.11, and GB/T 50319-2013 Clause 5.3.1.

Core Conclusions

Four blocks of application documents:

  1. Forms: the "Progress Payment Application (Approval) Form" (GB/T 50500-2024 Appendix F Table F.3.1) plus the "Monthly Progress Payment Review" / "Payment Application" forms to supervision (T11 IESB 0001-2017 Tables 4.1.8, 4.1.11). Form F.3.1 in quadruplicate, completed by the contractor and held by the employer, supervision, cost consultant, and contractor respectively; signed and sealed by the compiler and a Level-1 registered cost engineer; signed or sealed by the contractor's representative, the supervision engineer, and the employer's representative.
  2. Measurement documents: current-period qualifying quantities signed by supervision (BOQ statistical reports), work-item acceptance documents, physical progress; unaccepted parts are not measured. Period caliber (T11 IESB 0001-2017 Table 4.1.8): quantities measured monthly, the period running from the 26th of the previous month to the 25th of the current month; the contractor reports the monthly completed quantities by the 26th based on actual progress and the supervision-signed work items; supervision verifies the report, negotiating and listing differences where necessary; the measured quantities are supervision-signed and approved by the chief supervision engineer (subject to the contract).
  3. Price computation (GB/T 50500-2024 Clause 9.4.9): the contractor shall submit the payment application by each contract-agreed measurement period / payment verification date, stating the amounts it considers due — including the application amounts for construction workers' wages and the progress payments of specialty subcontractors — with computation bases. The application includes: (1) cumulative completed value — cumulative contract BOQ price; BOQ-defect adjustments (re-measurement adjustments under unit-price contracts, provisional-quantity adjustments under lump-sum contracts); provisional sums; provisional-price adjustments (material provisional prices; contractor-executed specialty-work provisional prices); main-contractor service fee adjustments; dayworks; price-change adjustments; regulation/policy-change adjustments; variations; additional works; claims; (2) cumulative recovered advances (including the current recovery); (3) cumulative payable progress payment; (4) prior cumulative payments; (5) employer deductions; (6) current payable. Progress payments are computed as the difference between the cumulative completed price and the cumulative paid price, with the current construction workers' wages separately stated. T11 IESB 0001-2017 Table 4.1.11 caliber: the applied amount = in-contract price + variation additions/reductions + approved claims - advances, retention, and other contract-agreed deductions; attaching supervision-accepted BOQ statistical reports priced at supervision-signed quantities and the unit prices of the contract-agreed quotas (or other pricing methods); other payment proofs attached as annexes.
  4. Construction workers' wages: stated separately in the application, wage sheets confirmed by the workers' own signatures, labor-cost disbursement at most monthly ("Regulations on wage payment to migrant workers"). Procedure: contractor submits -> specialty supervision rechecks quantities -> chief supervision engineer endorses for employer approval -> chief supervision engineer issues the payment certificate (GB/T 50319-2013 Clause 5.3.1); for disputed BOQ items, certify and pay first on undisputed parts (GB/T 50500-2024 Clause 9.4.11).

Applicable Boundaries

For general contractors' interim progress-payment applications. The period caliber "26th of previous month to 25th of current month, reported by the 26th" is from T11 IESB 0001-2017 (an industry document rule for building electrical works) — the construction contract prevails. Advance recovery follows §9.2; the work-safety measure advance is prepaid per §9.3 and not recovered from progress payments; process-stage settlement (§10.2) and final-account (§10.3) application listings follow their own clauses — do not mix. Railway verification-payment systems differ — do not mix.

Further Reading

GB/T 50500-2024: 9.4.9 (six application items and the 11-component value), 9.4.11 (undisputed-first payment), 9.1.6-9.1.8 (computation and the 80% floor), Appendix F Table F.3.1 (progress payment application (approval) form); T11 IESB 0001-2017 "Rules for management of building electrical works construction documents": Table 4.1.8 (monthly progress payment review and the measurement period), Table 4.1.11 (payment application completion requirements); GB/T 50319-2013 "Code for construction supervision" Clause 5.3.1 (measurement and payment sign-off procedures, retention); "Regulations on wage payment to migrant workers" (State Council Order No. 724) Articles 24, 26, 29, 31, 35 (labor-cost disbursement at most monthly, dedicated accounts, employer advance liability).