The full workflow of quality retention money retention and return (cap, retention methods, defects liability period commencement, and return procedure)
The retention money is reserved from payable amounts, capped at 3% of the total settlement price (the same cap applies to bank guarantees substituting for it); where performance security has been provided, or guarantee security or quality insurance is adopted, no further retention is allowed. Retention may be made in instalments from the first payment period or in one lump sum at final account; the computed base excludes prepayments and price-adjustment amounts. The defects liability period is generally 1 year and 2 years at most, running from the date of taking-over (completion acceptance) (where the employer causes delay in acceptance, it starts automatically 90 days after submission of the completion report). On expiry, and after verification, the money is returned within 14 days; failure to reply within that time is deemed acceptance of the application; no interest accrues on the returned remaining retention money.
Applicable Codes
- 建质〔2017〕138号 建设工程质量保证金管理办法
- GB/T 50500-2024 建设工程工程量清单计价标准 第10.5节
- GB/T 50319-2013 建设工程监理规范 第5.3.1条
Topic Positioning
Compliance essentials of the full retention-money workflow: cap, mutual-exclusion preconditions, retention methods, commencement of the defects liability period, and return procedure.
Core Conclusions
The retention money is funds reserved from payable project amounts under the contract to secure repair obligations during the defects liability period — generally 1 year, 2 years at most. Mutual-exclusion red lines: where performance security has been provided, no further retention before completion; where guarantee security or quality insurance is adopted, no retention; bank guarantees may substitute — the amount never exceeding 3% of the total settlement price. Retention may be in instalments from the first payment period until the cap is reached, or in one lump sum at final account; the base excludes prepayments and price-adjustment amounts. The defects liability period runs from the date of taking-over (completion acceptance); where the contractor causes delay, from the actual date of acceptance; where the employer causes delay, it starts automatically 90 days after submission of the completion report. On expiry the contractor applies for return; the employer verifies within 14 days and returns the money as agreed if there is no objection; failure to reply within that time, even after demand, is deemed acceptance; no interest accrues on the return of the remaining retention money or guarantee, and repair costs for defects caused by others may not be deducted from it.
Applicable Boundaries
Applies to building, municipal and other employer-contractor works under Jian Zhi [2017] No. 138 and GB/T 50500-2024; 3% is a cap, not a mandatory ratio — the contract sets it (and must specify the retention/return method, ratio and period, whether interest applies, the defects liability period, and dispute handling — seven items). Government-invested projects follow treasury centralized payment rules; privately invested projects may agree third-party financial-institution custody.
Further Reading
Jian Zhi [2017] No. 138 "Measures for the administration of construction quality retention money", Articles 2-11; GB/T 50500-2024 "Standard for valuation of construction works by bill of quantities", Section 10.5; GB/T 50319-2013 "Code for construction project supervision", Clause 5.3.1.
Keywords
Related Cards
- →
Determining the progress-payment ratio and the payment sign-off procedure (GB/T 50500-2024 §9.1/§9.4 + GB/T 50319-2013 §5.3.1)
The ratio is set by three layers — "contract agreement first -> national-standard floor -> local mandates": absent agreement, no less than 80% of cumulative completed value (9.1.7); current payable = cumulative completed price - cumulative paid - current deductions (9.1.6, 9.4.9); the work-safety measure advance is not recovered from progress payments (9.3.2); the procedure runs contractor applies -> specialty supervision rechecks -> chief supervision engineer endorses -> employer approves -> chief supervision engineer issues the certificate (GB/T 50319-2013 §5.3.1); the retention base excludes advances and price-adjustment amounts.
- →
Setting rules and compliance red lines for the performance security and the quality retention (retention money): 10%/3% caps, mutual exclusivity before completion, and the boundary allowing coexistence at final settlement
The performance security guarantees contract performance, capped at 10% of the awarded contract amount (Implementation Regulations of the Tendering and Bidding Law, Article 58); over-collection may be ordered to correct and fined up to RMB 50,000 (Article 66). The retention money guarantees repair obligations during the defect liability period, capped at 3% of the total project price settlement amount (GB/T 50500-2024 Clause 10.5.1 and Jianzhi [2017] No. 138 Article 7, with a bank guarantee substitute also capped at 3%); the defect liability period is generally 1 year, 2 years maximum. The mutual-exclusivity red line is time-divided: before completion a retention must not be reserved while a performance security has been paid; but at final settlement a retention of up to 3% of the total settlement price may still be reserved (the performance security covers construction-period performance while the retention covers defect-period repairs — different guaranteed objects may coexist); where an engineering quality guarantee or quality insurance is adopted, the employer must not further reserve retention money. At the end of the defect liability period, final clearance is handled, the remaining retention is returned, and interest should not be calculated (GB/T 50500-2024, Clause 10.5.5).
- →
Full workflow of agreeing and paying construction advance payments (GB/T 50500-2024 Section 9.2): nature, proportion, procedure, guarantee, and recovery
The construction advance payment (materials advance) is paid by the Employer before commencement for the Contractor's materials preparation - earmarked and interest-free. For labour-and-material contracts, the payment proportion should not be less than 10% of the signed contract price (net of provisional sums, dayworks and provisional sums for nominated specialist subcontract works) and should not exceed 30% of the signed contract price (for major multi-year projects, prepaid annually at the same proportion in accordance with the annual plan). The Contractor applies -> the Employer reviews and pays (an equal-value guarantee may be agreed); recovery is made as agreed in the contract, or, if not agreed, in one or more instalments; on termination of the contract, any unrecovered portion is recovered in full.
Cited By
- ←
Whether the quality retention money (3% retention) can be brought within the contractor's priority right to payment out of the construction project price, and the accounting method of back-computing, from the defects liability period plus the return-verification procedure period, whether the 18-month preclusive period has expired
Retention money is 'withheld from the works price payable' and forms part of the works price; it can be brought within the priority scope, but only subject to quality of the works passing (Fa Shi [2020] No. 25, Article 38), the return condition maturing on expiry of the defects liability period, and the 18-month exercise period not being exceeded (Article 41); interest and liquidated damages for late return of retention money enjoy no priority (Article 40, item (2)). The 18 months is a preclusive period; the 'date payment falls due' is approximately the defects liability period (12 months where agreed at 1 year, or 24 months at the statutory 2-year cap) plus the return-verification procedure period (14 days verification plus, absent agreement, 14 days return after verification, about 0.5-1 month). Back-computed from 36 months after delivery: with a 1-year period the due date is around month 12.5, about 23.5 months ago, already exceeded by about 5.5 months; with a 2-year period the due date is around month 24.5, about 11.5 months ago, leaving a window of about 6.5 months.
- ←
The employer deducting site fines and repair costs (repair expenses) from the works payment: distinguishing their legal nature, the constitutive requirements of the deduction, the amount caps and the set-off notice procedure, and the old/new transition between Article 16 of Interpretation (II) on Construction Contract Disputes (Fa Shi [2026] No. 12) and Article 12 of the former Fa Shi [2020] No. 25
Yes, deduction is allowed, but the two categories differ in nature and in requirements. A site fine is in substance liquidated damages - the employer has no administrative penalty power (Administrative Penalty Law, Article 17) - and requires the coexistence of: 'an express contract stipulation of the fineable events, standards and computation method' + 'evidenced facts of breach' + 'an amount not excessively higher than the actual loss (an excess of more than 30% over the loss is generally deemed excessive, Fa Shi [2023] No. 13, Article 65)' + 'notice of set-off given to the other party (Civil Code, Article 568; the notice takes effect on arrival; set-off may not be made conditional or subject to a time limit)'. Repair costs require the coexistence of: 'a defect attributable to the contractor' + 'notice to repair with a reasonable period given' + 'the contractor refusing to repair or failing to repair to conformity within the reasonable period' + 'the employer having actually repaired at reasonable cost' - Fa Shi [2026] No. 12, Article 16, paragraph 2; a request that the contractor pay repair costs up front without notice to repair is not supported (paragraph 1 of the same article). Defects not caused by the contractor may not be deducted from the retention money (GB/T 50500-2024, Clause 10.5.4; Jian Zhi [2017] No. 138, Article 9, paragraph 2).
- ←
The statutory red lines on the permissible range of security deposits in construction works and identification of violation types: only four categories may be collected -- tender security, performance security, works quality retention and migrant worker wage security -- and any other deposit collected under any name is unlawful; restriction to cash is banned, guarantees from financial institutions must be accepted, and deposits must be accounted for and refunded at expiry; plus unreasonable deposit restrictions at the levels of tender documents and policy documents, with the matching liability clauses
Article 13 of the Regulation on Ensuring Payment to Small and Medium-sized Enterprises (State Council Order No. 802): apart from the lawfully established tender security deposit, performance security deposit, works quality retention money and migrant worker wage security deposit, no other security deposit may be collected in any form in construction; deposits may not be restricted to cash, and where an SME provides security by a guarantee issued by a financial institution or the like it must be accepted; after the security period expires, timely accounting with the SME and refund are required. Violations are pursued under Article 31(5) (on refusal to correct, responsible leaders and directly liable personnel are sanctioned); at the policy-document level, Article 11 of the Fair Competition Review Rules for the Tendering and Bidding Field applies in addition -- no demands for deposits beyond the four categories, no restriction of the form of payment, no requirement that guarantees (insurance) be issued by a specified institution, and no refund preconditions set outside the tender documents.
- ←
Repair responsibility for quality defects within the defects liability period and the warranty period, bearing of repair costs and the retention money deduction rules (GB/T 50500-2024 Clauses 10.5.2-10.5.4 and 10.3.13 + Jianzhi [2017] No. 138 Article 9 + Regulation on Quality Management of Construction Projects)
Divided by cause of the defect: for defects or damage caused by the contractor, the contractor repairs and bears the appraisal and repair costs; where the contractor refuses to repair, or still fails to repair within a reasonable period after written notice from the employer, the employer may repair itself or engage a third party, the costs are borne by the contractor and may be deducted from the retention money or the quality warranty bond, and any excess over the retained amount is claimed from the contractor under GB/T 50500-2024 Clause 8.11.18 (Clauses 10.5.2 and 10.5.3; Jianzhi [2017] No. 138 Article 9). For defects not caused by the contractor, the employer organises the repair and bears the costs, and nothing may be deducted from the retention money (Clause 10.5.4). At settlement, repair and rework costs may be deducted in the final account under Clause 10.3.13. Within the warranty period the construction enterprise shall perform its warranty duty and bear liability for losses caused (Regulation on Quality Management of Construction Projects, Article 41); failure or delay attracts an order to rectify and a fine of no less than CNY 100,000 and no more than CNY 200,000 (Article 66).
- ←
Rules for deducting from the works payment or discounted compensation for construction quality defects: the three layers of failed acceptance, quality not conforming to the agreement, and the defects liability and warranty layer; deduction caps and the repair-notice precondition; and the negative scenarios where deduction is not supported
Deduction is possible, but only conditionally and within limits: qualified quality is the precondition for claiming the works payment or discounted compensation; quality defects may be deducted only within the 'price attributable to the defect' or the 'reasonable repair costs', and only where the defect is attributable to the contractor, repair was notified, and the costs were actually incurred or determined by expert assessment; an employer who has not notified the contractor to repair cannot obtain an advance order for repair costs (Fa Shi [2026] No. 12 Article 16(1)); where the works still fail acceptance after repair, the contractor has no right to discounted compensation (Civil Code Article 793(2), item 2); defects not caused by the contractor may not be deducted from retention money; retention is capped at 3% of the total settled price of the works (Jian Zhi [2017] No. 138 Article 7).
- ←
The elements, structure of proof and scope of deduction of the employer's 'quality problems' defence in retention money return disputes (Fa Shi [2020] No. 25 Art. 17 + Fa Shi [2026] No. 12 Arts. 14, 16 and 23 + Jian Zhi [2017] No. 138 + GB/T 50500-2024 Clauses 10.5)
The right to return of the retention money arises on expiry of the defects liability period, and a refusal by the employer pleading merely 'the works have quality problems' is in principle not sustained. The defence is partially sustained only where the three elements are all present - the defect is attributable to the contractor + repair has been demanded (GB/T 50500-2024 requires a written demand) and the contractor refused or failed to repair within a reasonable period + a reasonable repair cost has actually been incurred or can be determined by expert assessment - and its effect is only deduction of that reasonable repair cost from the retention money or guarantee with return of the balance, the excess being claimed separately; and return does not release the warranty obligations (Article 17(2) of Fa Shi [2020] No. 25). The start of the return period and the withholding base follow Article 14 of Fa Shi [2026] No. 12 (where the contract is terminated or void and the works incomplete, the period runs from the contractor's exit from site, and the base becomes the construction price payable to the contractor / the discounted-price compensation).
- ←
The base for computing works retention money under a fixed lump-sum construction contract: the total settled project price (including contractually adjustable items and excluding unused provisional sums) rather than the signed contract price, capped at 3%; on rescission or void incomplete works the base shifts to the price due to the contractor or the discounted compensation due
For a fixed lump-sum contract the retention money base is 'the total settled project price', not the signed contract price: total settled price = the fixed contract price + contractually adjustable additions (variations, site instruction records, claims, provisional price adjustments, provisional sums actually incurred, cost fluctuation adjustment, changes in laws and policies, etc.) - deductions such as unused provisional sums; both the retention percentage and the guarantee amount are capped at 3% of that total (Jian Zhi [2017] No. 138 Article 7; GB/T 50500-2024 Clause 10.5.1), not computed on the signed price, the audit conclusion or the unpaid balance. Exception: in first-instance cases newly accepted after 30 June 2026, where the construction contract is rescinded the base is the price due to the contractor, and where the contract is void and the works incomplete the base is the discounted compensation due, with the return period running from site demobilisation (Fa Shi [2026] No. 12 Article 14).
- ←
Start point, calculation base and length of the retention money return period after termination of a construction contract (or invalidity with the works unfinished) - aligning Fa Shi [2026] No. 12 Article 14 with Fa Shi [2020] No. 25 Article 17 and Jian Zhi [2017] No. 138
Fa Shi [2026] No. 12, Article 14: where the construction contract is terminated, the retention money return period runs from the date the contractor withdrew from the site; where the contract is terminated after the contractor has withdrawn, it runs from the date of termination; where the contract is invalid and the works are unfinished (the base changing to the discounted compensation payable), it likewise runs from the withdrawal date. The article changes only the start point and the base (the project price payable / the discounted compensation, not the total contract price), not the length - the defects liability period is generally 1 year and at most 2 years (Jian Zhi [2017] No. 138, Article 2), and the retention cap remains 3% of the settled total project price (Article 7). The interpretation took effect on 30 June 2026 and applies only to first-instance cases newly accepted after that date (Article 23).
- ←
Rules for the start point of the defects liability period (the period secured by retention money): the statutory deemed start 90 days after submission of the completion-acceptance report where the employer delays or fails to organise completion acceptance, and a comparison of the start points for normal acceptance, contractor-caused delay, premature use of the works without taking-over, and early acceptance of units or sections
Where for reasons attributable to the employer the works cannot undergo completion acceptance within the prescribed period, the defects liability period is entered automatically 90 days after the contractor submits the completion-acceptance report (Article 8 of Jian Zhi [2017] No. 138); the base is thus 'submission date plus 90 days' - it runs neither from the date of actual passing of acceptance nor immediately from the submission date. In the normal case it runs from the date of passing completion acceptance; where the contractor is the reason, from the date of actual passing; the period is generally 1 year, 2 years at most.
- ←
Validity of a quality retention money percentage exceeding the 3% cap, and routes for return or payment of the excess (including expiry of the defects liability period, substitution by performance security or a guarantee bond, and the time-point distinctions for contract termination and for a void contract with incomplete works)
The 3% cap comes from Jian Zhi [2017] No. 138 Article 7 and GB/T 50500-2024 Clause 10.5.1; the former is a departmental normative document and the latter a recommended national standard, and neither is a mandatory validity provision of a law or administrative regulation, so an agreed 5% is not thereby invalid in general - it creates only the administrative regulatory risk of unlawful retention; during the defects liability period the contractor cannot demand early return of the difference merely because it 'exceeds 3%', but after the period expires the full amount must be returned (less the actual repair costs of defects due to the contractor); where a performance security was paid before completion, or a quality guarantee or quality insurance was provided, or the actual retention exceeds the agreed percentage, the excess must be returned or paid as works payment.
- ←
The duration cap of the defects liability period (generally 1 year, no more than 2 years, i.e. 24 months) against the start events for each situation: taking-over, taking-over delayed by the contractor or by the employer, prior taking-over of unit works, premature use with transfer of possession, extension for defect repair, and the three-way distinction from the retention money return period and the warranty period
The defects liability period is capped at 24 months (2 years): Article 2 of Jian Zhi [2017] No. 138 - 'the defects liability period is generally 1 year and may not exceed 2 years at most, as agreed by the employer and the contractor in the contract'; the model general conditions further state 'not exceeding 24 months at most' and 'including the extension, it may not exceed 24 months in total'. Start: generally from the date the works pass taking-over (completion acceptance); where the contractor causes failure to take over on schedule, from the date the works actually pass taking-over; where the employer causes it, the works automatically enter the defects liability period 90 days after the contractor submits the taking-over report; where a unit work is taken over first, from the date that unit work passes taking-over; where the employer uses the works without taking-over, from the date of transfer of possession. The defects liability period is not the retention money return period and not the warranty period (the latter under Article 40 of the Regulation on Quality Management of Construction Works: 5 years for waterproofing, the design working life for the main structure).
- ←
Commencement of the defects liability period in all scenarios: where the employer uses the works prematurely without completion acceptance, the period runs from transfer of possession, distinguished from the 90-day automatic-entry rule and from the contractor's exit on termination or invalidity of the contract (Jian Zhi [2017] No. 138, Article 8 + Fa Shi [2020] No. 25, Article 9 + Fa Shi [2026] No. 12, Article 14)
Where the employer uses the works prematurely without completion acceptance, the defects liability period runs from 'the date of transfer of possession of the works' (expressly so provided in GF-2017-0201, Clause 15.2.1, and GF-2020-0216, Clause 11.2; under Fa Shi [2020] No. 25, Article 9(3), the date of transfer of possession is deemed the completion date); the duration follows the contract, generally one year and at most two years. Jian Zhi [2017] No. 138, Article 8, provides only three commencement points - 'the date of passing completion acceptance / the date of actually passing completion acceptance / 90 days after submission of the completion report' - and does not list premature use, so the 90-day rule cannot be transplanted to premature use. Where the contract is terminated, or is void and the works are incomplete, Fa Shi [2026] No. 12 (effective from 30 June 2026), Article 14, instead runs the time limit for return of the retention money from the date of the contractor's exit from site (or from the date of termination where the contract is terminated after exit).
- ←
The boundary between the defects liability period (secured by retention money) and the warranty period: differences of length and start, whether funds are held, and refunding retention does not release the warranty duty
Retention money secures only the defects liability period (normally 1 year, 2 years at most, Jian Zhi [2017] No. 138 Article 2); the warranty period follows Article 40 of the Quality Management Regulation for Construction Works: foundations and main structure for the reasonable service life in the design documents; roof waterproofing, watertight bathrooms, rooms and external walls 5 years; heating and cooling 2 heating/cooling seasons; electrical wiring, water supply and drainage pipes, equipment installation and fit-out 2 years - all from the date of passing completion acceptance. Expiry of the defects liability period and refund of retention do not affect the contractor's continuing warranty duty; within the warranty scope and period the contractor performs repairs and compensates losses caused (Article 41).
- ←
Full process of construction payment: advance payment, safety-measures fee, progress payment, interim settlement by construction stage, final account, retention money and final settlement (GB/T 50500-2024 Chapters 9-10)
Payment along the timeline in six segments: advance payment (for works with contractor-procured materials, neither below 10% nor above 30% of the contract price after deducting provisional sums etc., prepaid before commencement, recovered as agreed) → statutory safety provisions (at least 50% prepaid within 28 days after commencement; not deducted from progress payments, recovered once at the final account) → progress payments (amount due = cumulative completed − cumulative paid − deductions; not less than 80% of the cumulative completed value where the contract is silent) → interim settlement by construction stage (new in 2024: signed stage settlements enter the final account without re-pricing; stage payments not below 80%) → final account (thirteen heads; failure to check or to certify in time is deemed acceptance) → retention money (3% cap) and final closure (defects liability period generally 1 year, 2 at most). The chain runs on contract-agreed time limits with a 28-day backstop; judicial enforcement of "accepted at the submitted price" requires an express contractual provision.