Engineering Knowledge Cards.

defects liability period

13 knowledge cards · sorted by most recently updated

Concept Guide

Concept

The defects liability period is the window after completion during which the contractor remains responsible for remedying defects in the works, and during which the employer's security — typically retention money — is held. Chinese practice ties the period directly to the quality retention money regime: the period is agreed in the contract, follows acceptance of the works, and its expiry governs release of retention.

Starting point and duration. In China the defects liability period runs from the date the works pass completion acceptance, and is generally capped at two years; the actual length is agreed by the parties.

Obligations and security. During the period the contractor must remedy notified defects. If it fails to do so, the employer may engage others and recover the cost from retention money or other sums due. This creates a three-part structure: period, obligation, security.

Effect at expiry. Where the contractor has discharged its remedial obligations, retention money is released; outstanding defects may justify deduction.

Practical points. Confirm the completion acceptance documentation that fixes the start date; define defect identification and notice procedures, response times and cost allocation in the contract; and keep the concept separate from the warranty period in payment and claim documents.

FIDIC Mapping

Corresponding term. The FIDIC Red Book and Yellow Book 2017 use the Defects Notification Period (DNP), defined in Sub-Clause 1.1.27, with remedial obligations in Sub-Clause 11.1, extension in Sub-Clause 11.3, and issue of the Performance Certificate at expiry in Sub-Clause 11.9. Chinese texts often render it as "缺陷责任期"; the looser English expression defects liability period is functionally similar but is not the defined term in the 2017 editions.

Key differences. Start date: the DNP runs from the date of completion stated in the Taking-Over Certificate, whereas in China the period runs from the date of completion acceptance. Default length: the DNP defaults to one year if the Contract Data is silent and may be extended under Sub-Clause 11.3, whereas the Chinese period is as agreed and capped at two years. Closing mechanism: FIDIC closes the period with the Performance Certificate, which marks completion of the contractor's obligations; China closes it with release of retention money and has no equivalent certificate.

Drafting caution. Writing defects liability period into FIDIC 2017 Particular Conditions creates an undefined term; use DNP. Do not equate the Chinese completion acceptance date with the Taking-Over Certificate date, do not treat the two-year cap as the international default, and do not translate the concept as "warranty period".

Chinese TermEnglish TermFIDIC TermRelationNotes
缺陷责任期defects liability periodDefects Notification Period (DNP), Sub-Clause 1.1.27adjacent功能同构(竣工后缺陷修复窗口),但 FIDIC 以 DNP 为定义术语、自接收证书所注完工日起算;中国概念自竣工验收合格日起算,术语与起算点均不同。
履约证书(缺陷期期满签发)Performance CertificatePerformance Certificate, Sub-Clause 11.9adjacentFIDIC 以 11.9 履约证书标志承包商义务完成;中国对应节点是缺陷责任期满返还质量保证金,属付款收口,无同等证书机制。
缺陷通知期延长extension of the Defects Notification PeriodExtension of Defects Notification Period, Sub-Clause 11.3distinctDNP 可依 11.3 延长;中国缺陷责任期以合同约定为限并有法定上限,缺少对应的延长机制,涉外改约时须谨慎对齐。

Updated 2026-09-13