defects liability period
Concept Guide
Concept
The defects liability period is the window after completion during which the contractor remains responsible for remedying defects in the works, and during which the employer's security — typically retention money — is held. Chinese practice ties the period directly to the quality retention money regime: the period is agreed in the contract, follows acceptance of the works, and its expiry governs release of retention.
Starting point and duration. In China the defects liability period runs from the date the works pass completion acceptance, and is generally capped at two years; the actual length is agreed by the parties.
Obligations and security. During the period the contractor must remedy notified defects. If it fails to do so, the employer may engage others and recover the cost from retention money or other sums due. This creates a three-part structure: period, obligation, security.
Effect at expiry. Where the contractor has discharged its remedial obligations, retention money is released; outstanding defects may justify deduction.
Practical points. Confirm the completion acceptance documentation that fixes the start date; define defect identification and notice procedures, response times and cost allocation in the contract; and keep the concept separate from the warranty period in payment and claim documents.
FIDIC Mapping
Corresponding term. The FIDIC Red Book and Yellow Book 2017 use the Defects Notification Period (DNP), defined in Sub-Clause 1.1.27, with remedial obligations in Sub-Clause 11.1, extension in Sub-Clause 11.3, and issue of the Performance Certificate at expiry in Sub-Clause 11.9. Chinese texts often render it as "缺陷责任期"; the looser English expression defects liability period is functionally similar but is not the defined term in the 2017 editions.
Key differences. Start date: the DNP runs from the date of completion stated in the Taking-Over Certificate, whereas in China the period runs from the date of completion acceptance. Default length: the DNP defaults to one year if the Contract Data is silent and may be extended under Sub-Clause 11.3, whereas the Chinese period is as agreed and capped at two years. Closing mechanism: FIDIC closes the period with the Performance Certificate, which marks completion of the contractor's obligations; China closes it with release of retention money and has no equivalent certificate.
Drafting caution. Writing defects liability period into FIDIC 2017 Particular Conditions creates an undefined term; use DNP. Do not equate the Chinese completion acceptance date with the Taking-Over Certificate date, do not treat the two-year cap as the international default, and do not translate the concept as "warranty period".
| Chinese Term | English Term | FIDIC Term | Relation | Notes |
|---|---|---|---|---|
| 缺陷责任期 | defects liability period | Defects Notification Period (DNP), Sub-Clause 1.1.27 | adjacent | 功能同构(竣工后缺陷修复窗口),但 FIDIC 以 DNP 为定义术语、自接收证书所注完工日起算;中国概念自竣工验收合格日起算,术语与起算点均不同。 |
| 履约证书(缺陷期期满签发) | Performance Certificate | Performance Certificate, Sub-Clause 11.9 | adjacent | FIDIC 以 11.9 履约证书标志承包商义务完成;中国对应节点是缺陷责任期满返还质量保证金,属付款收口,无同等证书机制。 |
| 缺陷通知期延长 | extension of the Defects Notification Period | Extension of Defects Notification Period, Sub-Clause 11.3 | distinct | DNP 可依 11.3 延长;中国缺陷责任期以合同约定为限并有法定上限,缺少对应的延长机制,涉外改约时须谨慎对齐。 |
Updated 2026-09-13
- 01
Whether the quality retention money (3% retention) can be brought within the contractor's priority right to payment out of the construction project price, and the accounting method of back-computing, from the defects liability period plus the return-verification procedure period, whether the 18-month preclusive period has expired
Retention money is 'withheld from the works price payable' and forms par…
《民法典》第八百零七条法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第三十六条、第三十八条、第四十条、第四十一条、第四十五条法释〔2026〕12号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》第十四条、第十七条、第二十一条、第二十三条2026-10-31 - 02
Burden-of-proof allocation and element checklist for the employer alleging construction quality defects: the five elements - defect exists, attributable to the contractor, prior notice to repair, reasonable repair cost, within the liability period - plus the consequences of failure of proof and the rules on appraisal elucidation
An employer alleging construction quality defects (price reduction / cou…
《中华人民共和国民法典》第五百八十二条、第七百九十三条、第七百九十九条、第八百零一条法释〔2026〕12号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》第十六条、第二十三条(2026年3月17日审判委员会第1969次会议通过,2026年6月30日施行)https://www.court.gov.cn/fabu/xiangqing/504221.html法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第十二条、第十三条、第十四条、第十六条、第三十二条2026-10-29 - 03
Repair responsibility for quality defects within the defects liability period and the warranty period, bearing of repair costs and the retention money deduction rules (GB/T 50500-2024 Clauses 10.5.2-10.5.4 and 10.3.13 + Jianzhi [2017] No. 138 Article 9 + Regulation on Quality Management of Construction Projects)
Divided by cause of the defect: for defects or damage caused by the cont…
GB/T 50500-2024 建设工程工程量清单计价标准 第10.3.13条、第10.5.2条、第10.5.3条、第10.5.4条、第8.11.18条建质〔2017〕138号 建设工程质量保证金管理办法(2017修订)第九条建设工程质量管理条例(国务院令第714号,2019修订)第四十条、第四十一条、第六十六条2026-10-29 - 04
Start point, calculation base and length of the retention money return period after termination of a construction contract (or invalidity with the works unfinished) - aligning Fa Shi [2026] No. 12 Article 14 with Fa Shi [2020] No. 25 Article 17 and Jian Zhi [2017] No. 138
Fa Shi [2026] No. 12, Article 14: where the construction contract is ter…
最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)(法释〔2026〕12号)第十条、第十四条、第十五条、第二十三条,2026年6月30日施行,https://www.court.gov.cn/fabu/xiangqing/504221.html最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)(法释〔2020〕25号)第十七条,2021年1月1日施行,https://www.court.gov.cn/zixun/xiangqing/282111.html建设工程质量保证金管理办法(建质〔2017〕138号,2017修订)第二条、第七条、第八条、第十条、第十一条2026-10-29 - 05
Rules for the start point of the defects liability period (the period secured by retention money): the statutory deemed start 90 days after submission of the completion-acceptance report where the employer delays or fails to organise completion acceptance, and a comparison of the start points for normal acceptance, contractor-caused delay, premature use of the works without taking-over, and early acceptance of units or sections
Where for reasons attributable to the employer the works cannot undergo…
建质〔2017〕138号《建设工程质量保证金管理办法》(2017修订)第二条、第七条、第八条、第十一条最高人民法院法释〔2020〕25号《关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第九条、第十七条建市〔2020〕96号《建设项目工程总承包合同(示范文本)》GF-2020-0216 通用合同条件第11.2款2026-10-29 - 06
The duration cap of the defects liability period (generally 1 year, no more than 2 years, i.e. 24 months) against the start events for each situation: taking-over, taking-over delayed by the contractor or by the employer, prior taking-over of unit works, premature use with transfer of possession, extension for defect repair, and the three-way distinction from the retention money return period and the warranty period
The defects liability period is capped at 24 months (2 years): Article 2…
《建设工程质量保证金管理办法》(建质〔2017〕138号,2017修订)第二条、第三条、第七条、第八条《建设工程施工合同(示范文本)》GF-2017-0201 通用合同条款 14.4、15.1、15.2、15.3《建设项目工程总承包合同(示范文本)》GF-2020-0216 通用合同条件 11.1、11.22026-10-29 - 07
The boundary between the defects liability period (secured by retention money) and the warranty period: differences of length and start, whether funds are held, and refunding retention does not release the warranty duty
Retention money secures only the defects liability period (normally 1 ye…
建质〔2017〕138号《建设工程质量保证金管理办法》第二条、第八条、第九条、第十条、第十一条《建设工程质量管理条例》(2017修订)第四十条、第四十一条GB 55032-2022 · General Code for Construction Quality Control of Building and Municipal Engineering 第5.0.2条2026-10-18 - 08
The full workflow of quality retention money retention and return (cap, retention methods, defects liability period commencement, and return procedure)
The retention money is reserved from payable amounts, capped at 3% of th…
建质〔2017〕138号 建设工程质量保证金管理办法GB/T 50500-2024 建设工程工程量清单计价标准 第10.5节GB/T 50319-2013 建设工程监理规范 第5.3.1条2026-09-25 - 09
FIDIC Defects Notification Period vs the domestic "defect liability period": same name, different regime - mechanism skeleton and the domestic habits to shed
The domestic defect liability period and FIDIC DNP are "terminological c…
FIDIC Conditions of Contract for Construction (Red Book), 2nd Edition 2017: Sub-Clause 1.1.27, Clause 11, Sub-Clause 14.9GB/T 50358-2017 建设项目工程总承包管理规范 第2.0.32条建质〔2017〕138号 建设工程质量保证金管理办法 第二条2026-09-25 - 10
Full process of construction payment: advance payment, safety-measures fee, progress payment, interim settlement by construction stage, final account, retention money and final settlement (GB/T 50500-2024 Chapters 9-10)
Payment along the timeline in six segments: advance payment (for works w…
GB/T 50500-2024 建设工程工程量清单计价标准(第9.1~9.4、10.1~10.3、10.5节)财建〔2004〕369号 建设工程价款结算暂行办法建质〔2017〕138号 建设工程质量保证金管理办法2026-09-25 - 11
Setting rules and compliance red lines for the performance security and the quality retention (retention money): 10%/3% caps, mutual exclusivity before completion, and the boundary allowing coexistence at final settlement
The performance security guarantees contract performance, capped at 10%…
2026-09-25 - 12
Return of the quality retention money: timing, procedure, and the final account interface (Jian Zhi [2017] No. 138 + GB/T 50500-2024 §10.5)
The retention money is returned when the defect liability period (genera…
建质〔2017〕138号 建设工程质量保证金管理办法GB/T 50500-2024 建设工程工程量清单计价标准 第10.5节2026-09-25 - 13
The FIDIC Performance Certificate (Red Book Clauses 11.9/11.10) mapped against the domestic completion acceptance - defect liability period - final settlement system: correspondences and differences
Performance Certificate is not Performance Bond. FIDIC Red Book 11.9: th…
FIDIC 红皮书 1999 第 11.9~11.10 条FIDIC 红皮书 2017 第 2 版第 11.9~11.10 条GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第 10.5.5、10.5.8 条2026-09-25