The duration cap of the defects liability period (generally 1 year, no more than 2 years, i.e. 24 months) against the start events for each situation: taking-over, taking-over delayed by the contractor or by the employer, prior taking-over of unit works, premature use with transfer of possession, extension for defect repair, and the three-way distinction from the retention money return period and the warranty period

The defects liability period is capped at 24 months (2 years): Article 2 of Jian Zhi [2017] No. 138 - 'the defects liability period is generally 1 year and may not exceed 2 years at most, as agreed by the employer and the contractor in the contract'; the model general conditions further state 'not exceeding 24 months at most' and 'including the extension, it may not exceed 24 months in total'. Start: generally from the date the works pass taking-over (completion acceptance); where the contractor causes failure to take over on schedule, from the date the works actually pass taking-over; where the employer causes it, the works automatically enter the defects liability period 90 days after the contractor submits the taking-over report; where a unit work is taken over first, from the date that unit work passes taking-over; where the employer uses the works without taking-over, from the date of transfer of possession. The defects liability period is not the retention money return period and not the warranty period (the latter under Article 40 of the Regulation on Quality Management of Construction Works: 5 years for waterproofing, the design working life for the main structure).

Applicable Codes

  • 《建设工程质量保证金管理办法》(建质〔2017〕138号,2017修订)第二条、第三条、第七条、第八条
  • 《建设工程施工合同(示范文本)》GF-2017-0201 通用合同条款 14.4、15.1、15.2、15.3
  • 《建设项目工程总承包合同(示范文本)》GF-2020-0216 通用合同条件 11.1、11.2
  • 《建设工程质量管理条例》(国务院令第714号,2019修订)第四十条
  • 法释〔2020〕25号 第十七条
  • 法释〔2026〕12号 第十四条、第二十三条(2026年6月30日施行)
  • https://zjt.hubei.gov.cn/zfxxgk/zc/qtzdgkwj/202601/t20260106_5849739.shtml
  • https://zjt.jiangxi.gov.cn/jxszfhcxjst/flfgg/pc/content/content_1765229153287335936.html
  • https://zjj.wenzhou.gov.cn/art/2022/1/20/art_1229206191_4050839.html
  • http://sxcj.sx.gov.cn/art/2025/3/28/art_1229396854_60261250.html

Positioning

The duration cap of the defects liability period in construction works and the start events for each situation. Based on the Measures for the Administration of Construction Works Quality Retention Money (Jian Zhi [2017] No. 138), the general conditions of the Model Construction Contract GF-2017-0201 and the Model Project EPC Contract GF-2020-0216, and Fa Shi [2020] No. 25 and Fa Shi [2026] No. 12, it also draws the boundary among the defects liability period, the retention money return period and the warranty period.

Core conclusions

1. Duration cap: 24 months at most (2 years)

Article 2 of the Measures for the Administration of Construction Works Quality Retention Money (Jian Zhi [2017] No. 138): 'The construction works quality retention money under these Measures (retention money) means the funds agreed by the employer and the contractor in the construction contract, withheld from the payable works payments, to secure the contractor's repair of defects arising in the works during the defects liability period.' 'Defects mean non-conformity of the works quality with the compulsory standards for construction projects, the design documents, or the agreed terms of the contract.' 'The defects liability period is generally 1 year and may not exceed 2 years at most, as agreed by the employer and the contractor in the contract.' The model contracts follow the same line and lock the cap including extensions:

  • GF-2017-0201 general conditions 15.2.1: 'The defects liability period is calculated from the date the works pass taking-over (completion acceptance). The parties shall agree in the particular conditions on the specific length of the defects liability period, but that period may not exceed 24 months.'
  • GF-2017-0201 general conditions 15.2.2: 'The employer may require the contractor to extend the defects liability period and shall issue an extension notice before the original defects liability period expires. But the defects liability period (including the extension) may not exceed 24 months in total.'
  • GF-2020-0216 general conditions 11.2: 'The defects liability period is in principle calculated from the date the works pass taking-over, and the parties shall agree in the particular conditions on the specific length of the defects liability period, but that period may not exceed 24 months.' Practice: 12 months is the ordinary agreement, 24 months the compliance ceiling, and even with an extension the total may not exceed 24 months.

2. Start events compared

# Situation Start point / period Basis
1 General situation (works pass taking-over) From the date the works pass taking-over First sentence of Article 8 of Jian Zhi [2017] No. 138; GF-2017-0201 15.2.1
2 Contractor causes failure to complete taking-over within the prescribed period From the date the works actually pass taking-over Second sentence of Article 8; GF-2017-0201 15.2.1
3 Employer causes failure to complete taking-over within the prescribed period The works automatically enter the defects liability period 90 days after the contractor submits the taking-over report Third sentence of Article 8; GF-2017-0201 15.2.1
4 Employer uses the works without taking-over (premature use) From the date of transfer of possession of the works GF-2017-0201 15.2.1; GF-2020-0216 11.2 (model contract supplement, not provided by the 138 Measures)
5 A unit work (section) is taken over and put into use before the whole works The defects liability period of that unit work (section) runs from the date it passes taking-over GF-2017-0201 15.2.1; GF-2020-0216 11.2
6 Extension for defects attributable to the contractor requiring re-inspection, testing or repair The employer must issue the extension notice before the original defects liability period expires; total including the extension no more than 24 months GF-2017-0201 15.2.2; GF-2020-0216 11.2
7 Construction contract terminated (works incomplete) - start of the retention money return period From the date the contractor leaves the site; where termination occurs after the contractor has left, from the date of termination Paragraph 1 of Article 14 of Fa Shi [2026] No. 12
8 Contract invalid and works incomplete - start of the retention money return period From the date the contractor leaves the site (base: the price-discount compensation due) Paragraph 2 of Article 14 of Fa Shi [2026] No. 12
9 Retention money return period agreed On the day the agreed return period expires Item (1) of Article 17 of Fa Shi [2020] No. 25
10 No agreed return period Two years after the works pass taking-over Item (2) of Article 17 of Fa Shi [2020] No. 25
11 Employer-caused delay in taking-over plus no agreed return period Two years after 90 days from submission of the taking-over report Item (3) of Article 17 of Fa Shi [2020] No. 25
12 Contrast: warranty period (not the defects liability period) From the date of passing taking-over, with statutory minimum periods Article 40 of the Regulation on Quality Management of Construction Works

The 138 Measures govern only start events 1 to 3; premature use and prior taking-over of unit works are supplementary rules of the model general conditions, premised on the contract incorporating them; events 7 and 8 are new rules added in 2026 by judicial interpretation on the start of the retention money return period and must not be mixed with the start of the defects liability period.

3. The defects liability period is not the retention money return period and not the warranty period

  • Defects liability period: the longest period securing the retention money, 24 months; on expiry the employer issues the certificate of termination of the defects liability period and returns the retention money (GF-2017-0201 15.2.4, 15.3).
  • Retention money return period: may run with the defects liability period or be agreed otherwise; absent agreement, Article 17 of Fa Shi [2020] No. 25: two years after the works pass taking-over; where the employer caused delay in taking-over, two years after 90 days from submission of the taking-over report.
  • Warranty period: Article 40 of the Regulation on Quality Management of Construction Works (State Council Order No. 714, 2019 revision): '(1) for foundation works and main structural works of infrastructure projects and building works, the design working life of the project stated in the design documents; (2) for roof waterproofing works, and toilets, rooms and exterior walls with waterproofing requirements, 5 years; (3) for heating and cooling systems, 2 heating periods and 2 cooling periods; (4) for electrical wiring, water supply and drainage pipes, equipment installation and fit-out works, 2 years. Warranty periods for other items are agreed by the employer and the contractor. The warranty period of a construction project is calculated from the date of passing taking-over.' Expiry of the defects liability period and return of the retention money do not release the warranty obligation - GF-2017-0201 15.1: 'on expiry of the defects liability period the contractor shall still bear the warranty obligations for each part of the works for the warranty periods agreed in the contract'; final paragraph of Article 17 of Fa Shi [2020] No. 25: 'return of the works quality retention money by the employer does not affect the contractor's performance of the works warranty obligations under the contract or under law.'

4. Link with the withholding of retention money

  • Withholding cap: Article 7 of the 138 Measures: 'The employer shall withhold the retention money in the manner agreed in the contract; the total withheld may not exceed 3% of the total settled price of the works. Where the contract provides that the contractor replaces the withheld retention money with a bank guarantee, the guarantee amount may not exceed 3% of the total settled price of the works.'
  • Required contract terms: Article 3 requires the employer to make the withholding, return and similar content of the retention money clear in the tender documents and to agree with the contractor in the contract terms on: (1) the method of withholding and return; (2) the rate and period; (3) whether interest is paid and how it is computed; (4) the length and computation of the defects liability period; (5) the procedures for handling disputes over withholding, return, repair quality and costs; (6) how claims for defects within the defects liability period are made; (7) the liquidated damages for late return and the liability. The length and computation of the defects liability period are mandatory agreed terms; their absence invites start-date disputes.

5. Practice points (procedural time limits)

  • Exercise of the extension right: the extension notice must be issued before the original defects liability period expires; a notice issued late cannot extend it (GF-2017-0201 15.2.2).
  • Expiry procedure: unless otherwise agreed in the particular conditions, the contractor shall issue an expiry notice to the employer within 7 days after the defects liability period expires; the employer verifies performance of the repair obligations within 14 days of receipt and issues the certificate of termination of the defects liability period within 14 days (15.2.4).
  • Link to final closure of accounts: the contractor submits the final closure application within 7 days after issue of the certificate of termination, stating the retention money, the retention money to be deducted, and the increases and decreases incurred during the defects liability period (14.4.1); the employer completes approval within 14 days of receipt and issues the final closure certificate, and pays within 7 days after issue of the certificate (14.4.2).

Boundaries of application

  • Articles 2 and 7 of Jian Zhi [2017] No. 138 are compulsory caps of a ministerial normative document ('generally 1 year, not exceeding 2 years at most'; 'not higher than ... 3%'); where the contract agrees more than 24 months, the excess lacks normative basis, and the contractor may claim return of the retention money on expiry relying on the model contract cap clauses and Article 17 of Fa Shi [2020] No. 25; the effect of the specific contract still needs to be judged on the agreement and the individual case.
  • The 138 Measures provide only three start events (taking-over; contractor-caused delay; employer-caused delay); premature use and prior taking-over of unit works are rules of the GF-2017-0201 / GF-2020-0216 general conditions and apply only where the contract adopts that model text or incorporates the corresponding clauses; where the particular conditions agree otherwise, that agreement governs.
  • The cap rules serve quality retention money management for building and municipal infrastructure works; where highway, railway, water and other sectors have separate provisions, those sectoral provisions and the contract govern.
  • Article 23 of Fa Shi [2026] No. 12: 'This Interpretation takes effect on 30 June 2026. First-instance construction contract dispute cases newly accepted by the people's courts after this Interpretation takes effect apply this Interpretation. Earlier judicial interpretations of the Supreme People's Court inconsistent with this Interpretation yield to it.' The start rules on retention money for terminated or invalid incomplete works thus apply only to first-instance cases newly accepted after 30 June 2026.
  • Do not confuse the defects liability period with the warranty period: 5 years for waterproofing and the design working life of the main structure are statutory warranty minimums, far longer than 24 months.