Return of the quality retention money: timing, procedure, and the final account interface (Jian Zhi [2017] No. 138 + GB/T 50500-2024 §10.5)
The retention money is returned when the defect liability period (generally 1 year, 2 years maximum) expires and the contractor has fulfilled its defect-repair duties, upon application; the period runs from completion acceptance, or — where acceptance is impossible for employer reasons — automatically 90 days after the contractor submits the completion acceptance report; the employer verifies within 14 days and returns within 14 days after verification absent an agreed return period; failure to respond within 14 days of the application, and again 14 days after a demand, is deemed acceptance; upon expiry, final account clearance proceeds per GB/T 50500-2024 §10.5.5, returning the guarantee or remaining retention money without interest.
Applicable Codes
- 建质〔2017〕138号 建设工程质量保证金管理办法
- GB/T 50500-2024 建设工程工程量清单计价标准 第10.5节
Topic Positioning
This card answers when the quality retention money is returned and by what procedure, per Jian Zhi [2017] No. 138 and GB/T 50500-2024, Section 10.5, linking the defect liability period commencement with the final clearance procedure.
Core Conclusions
Return timing = expiry of the defect liability period + the contractor having fulfilled its defect-repair duties within the period, with the contractor applying for return (Document No. 138, Article 10). The defect liability period is generally 1 year, 2 years maximum; normally running from the completion acceptance date; where the contractor causes delayed acceptance, from actual acceptance; where the employer causes it, automatically 90 days after the contractor submits the completion acceptance report (Article 8). Return procedure: after expiry the contractor applies -> the employer verifies within 14 days -> returned as agreed if no objection; absent an agreed return period, within 14 days after verification; failure to respond within 14 days of the application, and still failing 14 days after a demand, is deemed acceptance (Article 11). After expiry, final clearance proceeds per §10.5.5 — the guarantee or remaining retention money returned without interest; where the employer overdue fails to check or comment, it is deemed to agree and deemed to have issued the final clearance payment certificate (§10.5.8).
Applicable Boundaries
Covers only return timing and procedure; the retention cap (<= 3% of the settlement total), deduction situations, and guarantee substitution are in the cited cards. Return does not exempt the warranty obligation — the warranty period may exceed the defect liability period.
Further Reading
Jian Zhi [2017] No. 138, Articles 2, 8, 10, 11; GB/T 50500-2024, Clauses 10.5.1, 10.5.5, 10.5.8; for "overdue deemed acceptance" at settlement payment, see Clause 10.3.16.
Keywords
- retention money
- defects liability period
- 保证金返还
- 建质〔2017〕138号
- final closure of accounts after the defects period
- 返还程序
- 保证金什么时候返还
Related Cards
- →
Works put into use before completion acceptance: payment, quality liability and warranty rules (the employer's unauthorized use deemed acceptance of quality)
The employer's unauthorized use of un-accepted works equals deemed acceptance of quality (presumed qualification): the project price remains payable, with the date of transfer of possession serving as the completion date and the payment due date (interest at the 1-year LPR absent an agreed rate); quality risk passes to the employer except for foundations and the main structure (for which the contractor remains liable within the reasonable service life), and only for the parts actually used; warranty duties are not discharged - minimum warranty periods per Article 40 of the Regulations on Quality Management of Construction Works (waterproofing 5 years; heating and cooling 2 heating/cooling seasons; electrical wiring, water supply and drainage piping, equipment installation and finishing 2 years; foundations and main structure, the reasonable design life); the employer additionally bears an administrative fine of 2%-4% of the contract price (Article 58).
- →
Determining the progress-payment ratio and the payment sign-off procedure (GB/T 50500-2024 §9.1/§9.4 + GB/T 50319-2013 §5.3.1)
The ratio is set by three layers — "contract agreement first -> national-standard floor -> local mandates": absent agreement, no less than 80% of cumulative completed value (9.1.7); current payable = cumulative completed price - cumulative paid - current deductions (9.1.6, 9.4.9); the work-safety measure advance is not recovered from progress payments (9.3.2); the procedure runs contractor applies -> specialty supervision rechecks -> chief supervision engineer endorses -> employer approves -> chief supervision engineer issues the certificate (GB/T 50319-2013 §5.3.1); the retention base excludes advances and price-adjustment amounts.
- →
Calculating guarantee fees, retention money occupation costs, and financing costs for construction projects
Guarantee (letter of guarantee) fee = guaranteed amount × rate (reference 1‰–5‰, 4‰ recommended; absent agreement the guaranteed amount may take 15% of the total contract price); retention occupation cost = retention amount × occupation time × capital cost rate; capital cost = financing cost (one-off) + capital occupation cost. Red lines: performance security ≤10% of the awarded contract amount; quality (retention) money ≤3% of the total settled project price (replaceable by a bank guarantee; where performance security has been provided, no further retention before completion); overdue interest absent agreement at 0.05‰ per day. Where a guarantee is allowed to replace cash, prefer the guarantee.
- →
Setting rules and compliance red lines for the performance security and the quality retention (retention money): 10%/3% caps, mutual exclusivity before completion, and the boundary allowing coexistence at final settlement
The performance security guarantees contract performance, capped at 10% of the awarded contract amount (Implementation Regulations of the Tendering and Bidding Law, Article 58); over-collection may be ordered to correct and fined up to RMB 50,000 (Article 66). The retention money guarantees repair obligations during the defect liability period, capped at 3% of the total project price settlement amount (GB/T 50500-2024 Clause 10.5.1 and Jianzhi [2017] No. 138 Article 7, with a bank guarantee substitute also capped at 3%); the defect liability period is generally 1 year, 2 years maximum. The mutual-exclusivity red line is time-divided: before completion a retention must not be reserved while a performance security has been paid; but at final settlement a retention of up to 3% of the total settlement price may still be reserved (the performance security covers construction-period performance while the retention covers defect-period repairs — different guaranteed objects may coexist); where an engineering quality guarantee or quality insurance is adopted, the employer must not further reserve retention money. At the end of the defect liability period, final clearance is handled, the remaining retention is returned, and interest should not be calculated (GB/T 50500-2024, Clause 10.5.5).
Cited By
- ←
Whether the quality retention money (3% retention) can be brought within the contractor's priority right to payment out of the construction project price, and the accounting method of back-computing, from the defects liability period plus the return-verification procedure period, whether the 18-month preclusive period has expired
Retention money is 'withheld from the works price payable' and forms part of the works price; it can be brought within the priority scope, but only subject to quality of the works passing (Fa Shi [2020] No. 25, Article 38), the return condition maturing on expiry of the defects liability period, and the 18-month exercise period not being exceeded (Article 41); interest and liquidated damages for late return of retention money enjoy no priority (Article 40, item (2)). The 18 months is a preclusive period; the 'date payment falls due' is approximately the defects liability period (12 months where agreed at 1 year, or 24 months at the statutory 2-year cap) plus the return-verification procedure period (14 days verification plus, absent agreement, 14 days return after verification, about 0.5-1 month). Back-computed from 36 months after delivery: with a 1-year period the due date is around month 12.5, about 23.5 months ago, already exceeded by about 5.5 months; with a 2-year period the due date is around month 24.5, about 11.5 months ago, leaving a window of about 6.5 months.
- ←
Procedural rules for an employer's counterclaim for quality losses after the contractor has commenced arbitration over the project payment: legal basis of the counterclaim right, the line between defence and counterclaim, institutional counterclaim deadlines and late acceptance, out-of-scope awards and the risk of being set aside
Yes, it can be raised: Article 38 of the Arbitration Law (2025 revision) expressly provides that 'the respondent may admit or rebut the claim and has the right to file a counterclaim'. Quality breach, repair costs and compensation for quality losses are property-rights disputes under the same construction contract and fall within the arbitration agreement on which the main claim relies. But three gates must be passed: (1) the counterclaim must rest on the same arbitration agreement as the claim (matters under another contract, against another party, or administrative fines can only be pursued in a separate case); (2) it must be filed within the deadline in the institutional rules (BAC 2026 Rules Article 18: within 30 days of receipt of the notice of defence; CIETAC 2024 Rules Article 71 for domestic arbitration: within 20 days of receipt of the notice of arbitration), and if late, the arbitration institution (before constitution of the tribunal) or the tribunal (after constitution) decides whether to accept it; (3) substantively, it must satisfy contractor cause + notice to repair with a reasonable period given + refusal or failure to repair to the agreed standard + actual repair completed at reasonable cost. Merely seeking a price reduction or withholding payment is a defensive defence that can be made in the answer; once the employer demands payment from the contractor (repair costs, liquidated damages, third-party claims, delay losses), a counterclaim is mandatory, otherwise the award rules on matters beyond the arbitration agreement and risks being set aside under item (2) of paragraph 1 of Article 71 of the Arbitration Law.
- ←
Burden-of-proof allocation and element checklist for the employer alleging construction quality defects: the five elements - defect exists, attributable to the contractor, prior notice to repair, reasonable repair cost, within the liability period - plus the consequences of failure of proof and the rules on appraisal elucidation
An employer alleging construction quality defects (price reduction / counterclaimed repair costs / deduction from retention money) must prove five elements: (1) the defect objectively exists (non-conformity with the mandatory standards for engineering construction, the design documents or the construction contract); (2) the defect is attributable to the contractor; (3) the contractor was notified to repair and given a reasonable period, and refused to repair or failed within that period to repair to conformity; (4) the repair cost or loss is reasonable in amount (actually incurred or determinable by appraisal); (5) the claim is within the defects liability period or warranty period and outside the restricted scenarios - proof merely that 'the works have quality problems' falls far short of discharging the burden. Basis: Civil Code Article 801 makes 'causes attributable to the constructor' the precondition of liability; Fa Shi [2026] No. 12 Article 16(1), 'where the employer, without notifying the contractor to repair, requests a judgment that the contractor first pay the repair costs, the people's court will not support it', with paragraph 2 supporting the reasonable repair cost only after repair; the party bearing the burden of proof suffers the adverse consequences of failure of proof (Fa Shi [2015] No. 5 Article 90(2)).
- ←
The procedural timeline chain of completion taking-over of construction projects (notice for acceptance of sub-divisional works, review by the supervising engineer, taking-over organised by the employer, issue of the Taking-Over Certificate) and the contractual consequences where the employer is late in organising taking-over or issuing the certificate (deemed passing of taking-over, the certificate deemed issued, liquidated damages for delay), together with the administrative acceptance procedure requirements
Under the general conditions of GF-2017-0201, the timeline chain of completion taking-over runs: the contractor submits the application report for completion taking-over -> the supervising engineer reviews it within 14 days and forwards it to the employer -> the employer, within 28 days after receiving the report as reviewed by the supervising engineer, completes approval and organises taking-over -> where taking-over passes, the Taking-Over Certificate is issued within 14 days (where it is overdue without justified reason, it is deemed issued from the 15th day after passing). Where the employer uses the works prematurely without taking-over, the certificate must be issued within 7 days after transfer of possession and is deemed issued from the 15th day. Where the employer is late in organising taking-over or in issuing the certificate, liquidated damages are payable for each day of delay, calculated on the priced contract sum at the benchmark interest rate for loans of the same type and period published by the People's Bank of China (wording of the model text). GF-2020-0216 adds a 42-day deemed-passing rule (except where force majeure prevents taking-over). Administratively, under Article 6 of Jian Zhi [2013] No. 171 the employer must notify the project quality supervision agency in writing 7 working days before taking-over and, after receiving the completion report from the contractor, organise the acceptance group.
- ←
How the eighteen-month exercise period of the construction price priority right runs when the construction payment is paid by instalments: per-instalment accrual and separate accrual for retention money; the presumption where the payment time is not agreed; accrual where the date is varied by agreement or fixed in a settlement agreement (with the old/new boundary of Articles 21 and 23 of the 2026 Interpretation (II))
The eighteen months (Fa Shi [2020] No. 25, Article 41) is a preclusive period; the limitation rule of Civil Code Article 189 that 'for a debt performed by instalments the limitation period runs from expiry of the last instalment' does not apply. Instalment payment does not change the length of the eighteen months; it merely creates several 'dates on which payment falls due' - for each instalment the period starts on the day that instalment's payment conditions are satisfied, running and expiring instalment by instalment; the priority right for instalments whose period has expired is extinguished. Retention money accrues separately from the expiry of its return period (no agreement = two years after the works passed completion acceptance; failure to carry out acceptance due to the employer = 90 days after submission of the completion acceptance report), and may not serve as the starting point for the whole construction price.
- ←
The statutory red lines on the permissible range of security deposits in construction works and identification of violation types: only four categories may be collected -- tender security, performance security, works quality retention and migrant worker wage security -- and any other deposit collected under any name is unlawful; restriction to cash is banned, guarantees from financial institutions must be accepted, and deposits must be accounted for and refunded at expiry; plus unreasonable deposit restrictions at the levels of tender documents and policy documents, with the matching liability clauses
Article 13 of the Regulation on Ensuring Payment to Small and Medium-sized Enterprises (State Council Order No. 802): apart from the lawfully established tender security deposit, performance security deposit, works quality retention money and migrant worker wage security deposit, no other security deposit may be collected in any form in construction; deposits may not be restricted to cash, and where an SME provides security by a guarantee issued by a financial institution or the like it must be accepted; after the security period expires, timely accounting with the SME and refund are required. Violations are pursued under Article 31(5) (on refusal to correct, responsible leaders and directly liable personnel are sanctioned); at the policy-document level, Article 11 of the Fair Competition Review Rules for the Tendering and Bidding Field applies in addition -- no demands for deposits beyond the four categories, no restriction of the form of payment, no requirement that guarantees (insurance) be issued by a specified institution, and no refund preconditions set outside the tender documents.
- ←
Repair responsibility for quality defects within the defects liability period and the warranty period, bearing of repair costs and the retention money deduction rules (GB/T 50500-2024 Clauses 10.5.2-10.5.4 and 10.3.13 + Jianzhi [2017] No. 138 Article 9 + Regulation on Quality Management of Construction Projects)
Divided by cause of the defect: for defects or damage caused by the contractor, the contractor repairs and bears the appraisal and repair costs; where the contractor refuses to repair, or still fails to repair within a reasonable period after written notice from the employer, the employer may repair itself or engage a third party, the costs are borne by the contractor and may be deducted from the retention money or the quality warranty bond, and any excess over the retained amount is claimed from the contractor under GB/T 50500-2024 Clause 8.11.18 (Clauses 10.5.2 and 10.5.3; Jianzhi [2017] No. 138 Article 9). For defects not caused by the contractor, the employer organises the repair and bears the costs, and nothing may be deducted from the retention money (Clause 10.5.4). At settlement, repair and rework costs may be deducted in the final account under Clause 10.3.13. Within the warranty period the construction enterprise shall perform its warranty duty and bear liability for losses caused (Regulation on Quality Management of Construction Projects, Article 41); failure or delay attracts an order to rectify and a fine of no less than CNY 100,000 and no more than CNY 200,000 (Article 66).
- ←
The legal basis for the employer's claim to the (self-performed or third-party) cost of repair after the contractor refuses to repair quality defects, the repair pre-procedure, the constitutive requirements and the old-new judicial interpretation transition (Fa Shi [2026] No. 12, Articles 16 and 23)
Yes, but three conditions must be met simultaneously: 'non-conformity with the agreed quality attributable to the contractor + notice given with a reasonable period + repair actually carried out at reasonable cost'. Fa Shi [2026] No. 12, Article 16, paragraph 2: where the contractor refuses to repair or fails within a reasonable period to repair to conformity, and the employer, having carried out the repair, requests the contractor to bear the reasonable repair cost, the people's court shall support it; paragraph 1: where the employer requests an order that the contractor pay the repair cost in advance without notifying the contractor to repair, the people's court shall not support it. The old Fa Shi [2020] No. 25, Article 12, supported only a 'request to reduce the project price'; Article 16 of the 2026 interpretation additionally allows a counterclaim for the reasonable cost of repair, rework or alteration with consolidated hearing; the new interpretation takes effect on 30 June 2026, applies only to first-instance cases newly accepted after it takes effect, and prevails over prior interpretations where inconsistent (Article 23).
- ←
The elements, structure of proof and scope of deduction of the employer's 'quality problems' defence in retention money return disputes (Fa Shi [2020] No. 25 Art. 17 + Fa Shi [2026] No. 12 Arts. 14, 16 and 23 + Jian Zhi [2017] No. 138 + GB/T 50500-2024 Clauses 10.5)
The right to return of the retention money arises on expiry of the defects liability period, and a refusal by the employer pleading merely 'the works have quality problems' is in principle not sustained. The defence is partially sustained only where the three elements are all present - the defect is attributable to the contractor + repair has been demanded (GB/T 50500-2024 requires a written demand) and the contractor refused or failed to repair within a reasonable period + a reasonable repair cost has actually been incurred or can be determined by expert assessment - and its effect is only deduction of that reasonable repair cost from the retention money or guarantee with return of the balance, the excess being claimed separately; and return does not release the warranty obligations (Article 17(2) of Fa Shi [2020] No. 25). The start of the return period and the withholding base follow Article 14 of Fa Shi [2026] No. 12 (where the contract is terminated or void and the works incomplete, the period runs from the contractor's exit from site, and the base becomes the construction price payable to the contractor / the discounted-price compensation).
- ←
The base for computing works retention money under a fixed lump-sum construction contract: the total settled project price (including contractually adjustable items and excluding unused provisional sums) rather than the signed contract price, capped at 3%; on rescission or void incomplete works the base shifts to the price due to the contractor or the discounted compensation due
For a fixed lump-sum contract the retention money base is 'the total settled project price', not the signed contract price: total settled price = the fixed contract price + contractually adjustable additions (variations, site instruction records, claims, provisional price adjustments, provisional sums actually incurred, cost fluctuation adjustment, changes in laws and policies, etc.) - deductions such as unused provisional sums; both the retention percentage and the guarantee amount are capped at 3% of that total (Jian Zhi [2017] No. 138 Article 7; GB/T 50500-2024 Clause 10.5.1), not computed on the signed price, the audit conclusion or the unpaid balance. Exception: in first-instance cases newly accepted after 30 June 2026, where the construction contract is rescinded the base is the price due to the contractor, and where the contract is void and the works incomplete the base is the discounted compensation due, with the return period running from site demobilisation (Fa Shi [2026] No. 12 Article 14).
- ←
Start point, calculation base and length of the retention money return period after termination of a construction contract (or invalidity with the works unfinished) - aligning Fa Shi [2026] No. 12 Article 14 with Fa Shi [2020] No. 25 Article 17 and Jian Zhi [2017] No. 138
Fa Shi [2026] No. 12, Article 14: where the construction contract is terminated, the retention money return period runs from the date the contractor withdrew from the site; where the contract is terminated after the contractor has withdrawn, it runs from the date of termination; where the contract is invalid and the works are unfinished (the base changing to the discounted compensation payable), it likewise runs from the withdrawal date. The article changes only the start point and the base (the project price payable / the discounted compensation, not the total contract price), not the length - the defects liability period is generally 1 year and at most 2 years (Jian Zhi [2017] No. 138, Article 2), and the retention cap remains 3% of the settled total project price (Article 7). The interpretation took effect on 30 June 2026 and applies only to first-instance cases newly accepted after that date (Article 23).
- ←
Rules for the start point of the defects liability period (the period secured by retention money): the statutory deemed start 90 days after submission of the completion-acceptance report where the employer delays or fails to organise completion acceptance, and a comparison of the start points for normal acceptance, contractor-caused delay, premature use of the works without taking-over, and early acceptance of units or sections
Where for reasons attributable to the employer the works cannot undergo completion acceptance within the prescribed period, the defects liability period is entered automatically 90 days after the contractor submits the completion-acceptance report (Article 8 of Jian Zhi [2017] No. 138); the base is thus 'submission date plus 90 days' - it runs neither from the date of actual passing of acceptance nor immediately from the submission date. In the normal case it runs from the date of passing completion acceptance; where the contractor is the reason, from the date of actual passing; the period is generally 1 year, 2 years at most.
- ←
Rules for determining whether the contractor's warranty and compensation liabilities survive expiry of the defects liability period (after return of the retention money): separation of the two regimes, affirmative and exempted scenarios, layering of the liabilities by nature
Expiry of the defects liability period and full return of the retention money do not release the contractor from its quality warranty liability for the works. Core reason: the defects liability period is only the security period of the retention money (generally 1 year, no more than 2 years - Article 2 of Jian Zhi [2017] No. 138), whereas the warranty period is the statutory minimum quality guarantee period set by Article 40 of the Regulation on Quality Management of Construction Works (foundations and main structure: the reasonable service life specified in the design documents; waterproofing 5 years; heating and cooling 2 heating periods/cooling periods; electrical wiring, water supply and drainage pipes, equipment installation and finishing 2 years, running from the date of passing completion acceptance); Article 17 of Fa Shi [2020] No. 25 states that 'the employer's return of the project quality retention money does not affect the contractor's performance of its works warranty obligations under the contract or under law', and Article 41 of the Regulation provides that where quality problems occur within the warranty scope and warranty period the constructing enterprise shall perform the warranty obligation and bear liability to compensate the losses caused. Only the two scenarios of Article 17 of the Warranty Measures fall outside the warranty scope: defects caused by improper use or by a third party, and defects caused by force majeure.
- ←
Validity of a quality retention money percentage exceeding the 3% cap, and routes for return or payment of the excess (including expiry of the defects liability period, substitution by performance security or a guarantee bond, and the time-point distinctions for contract termination and for a void contract with incomplete works)
The 3% cap comes from Jian Zhi [2017] No. 138 Article 7 and GB/T 50500-2024 Clause 10.5.1; the former is a departmental normative document and the latter a recommended national standard, and neither is a mandatory validity provision of a law or administrative regulation, so an agreed 5% is not thereby invalid in general - it creates only the administrative regulatory risk of unlawful retention; during the defects liability period the contractor cannot demand early return of the difference merely because it 'exceeds 3%', but after the period expires the full amount must be returned (less the actual repair costs of defects due to the contractor); where a performance security was paid before completion, or a quality guarantee or quality insurance was provided, or the actual retention exceeds the agreed percentage, the excess must be returned or paid as works payment.
- ←
The duration cap of the defects liability period (generally 1 year, no more than 2 years, i.e. 24 months) against the start events for each situation: taking-over, taking-over delayed by the contractor or by the employer, prior taking-over of unit works, premature use with transfer of possession, extension for defect repair, and the three-way distinction from the retention money return period and the warranty period
The defects liability period is capped at 24 months (2 years): Article 2 of Jian Zhi [2017] No. 138 - 'the defects liability period is generally 1 year and may not exceed 2 years at most, as agreed by the employer and the contractor in the contract'; the model general conditions further state 'not exceeding 24 months at most' and 'including the extension, it may not exceed 24 months in total'. Start: generally from the date the works pass taking-over (completion acceptance); where the contractor causes failure to take over on schedule, from the date the works actually pass taking-over; where the employer causes it, the works automatically enter the defects liability period 90 days after the contractor submits the taking-over report; where a unit work is taken over first, from the date that unit work passes taking-over; where the employer uses the works without taking-over, from the date of transfer of possession. The defects liability period is not the retention money return period and not the warranty period (the latter under Article 40 of the Regulation on Quality Management of Construction Works: 5 years for waterproofing, the design working life for the main structure).
- ←
Commencement of the defects liability period in all scenarios: where the employer uses the works prematurely without completion acceptance, the period runs from transfer of possession, distinguished from the 90-day automatic-entry rule and from the contractor's exit on termination or invalidity of the contract (Jian Zhi [2017] No. 138, Article 8 + Fa Shi [2020] No. 25, Article 9 + Fa Shi [2026] No. 12, Article 14)
Where the employer uses the works prematurely without completion acceptance, the defects liability period runs from 'the date of transfer of possession of the works' (expressly so provided in GF-2017-0201, Clause 15.2.1, and GF-2020-0216, Clause 11.2; under Fa Shi [2020] No. 25, Article 9(3), the date of transfer of possession is deemed the completion date); the duration follows the contract, generally one year and at most two years. Jian Zhi [2017] No. 138, Article 8, provides only three commencement points - 'the date of passing completion acceptance / the date of actually passing completion acceptance / 90 days after submission of the completion report' - and does not list premature use, so the 90-day rule cannot be transplanted to premature use. Where the contract is terminated, or is void and the works are incomplete, Fa Shi [2026] No. 12 (effective from 30 June 2026), Article 14, instead runs the time limit for return of the retention money from the date of the contractor's exit from site (or from the date of termination where the contract is terminated after exit).
- ←
The boundary between the defects liability period (secured by retention money) and the warranty period: differences of length and start, whether funds are held, and refunding retention does not release the warranty duty
Retention money secures only the defects liability period (normally 1 year, 2 years at most, Jian Zhi [2017] No. 138 Article 2); the warranty period follows Article 40 of the Quality Management Regulation for Construction Works: foundations and main structure for the reasonable service life in the design documents; roof waterproofing, watertight bathrooms, rooms and external walls 5 years; heating and cooling 2 heating/cooling seasons; electrical wiring, water supply and drainage pipes, equipment installation and fit-out 2 years - all from the date of passing completion acceptance. Expiry of the defects liability period and refund of retention do not affect the contractor's continuing warranty duty; within the warranty scope and period the contractor performs repairs and compensates losses caused (Article 41).
- ←
FIDIC Defects Notification Period vs the domestic "defect liability period": same name, different regime - mechanism skeleton and the domestic habits to shed
The domestic defect liability period and FIDIC DNP are "terminological coincidence, institutional difference": GB/T 50358-2017 term 2.0.32 renders defect liability period literally as "defects notification period" - the same name as FIDIC 2017 Red Book 1.1.27's DNP with similar length (domestic generally 12 months, max 24; FIDIC 1 year default, extendable per 11.3) - but the cores differ: domestically it is the pledge period for retaining the quality guarantee deposit (generally 1 year, max 2 - Jianzhi [2017] No. 138 Article 2), money returned at expiry; FIDIC's DNP is the window in which the employer may notify the contractor to repair defects, with no retention-deposit concept - repair costs fall on the contractor only in the four 11.2 cases, otherwise treated as a variation payable; the employer's remedies are 11.4's repair-by-cost-deduction/price reduction, not deposit retention.
- ←
Full process of construction payment: advance payment, safety-measures fee, progress payment, interim settlement by construction stage, final account, retention money and final settlement (GB/T 50500-2024 Chapters 9-10)
Payment along the timeline in six segments: advance payment (for works with contractor-procured materials, neither below 10% nor above 30% of the contract price after deducting provisional sums etc., prepaid before commencement, recovered as agreed) → statutory safety provisions (at least 50% prepaid within 28 days after commencement; not deducted from progress payments, recovered once at the final account) → progress payments (amount due = cumulative completed − cumulative paid − deductions; not less than 80% of the cumulative completed value where the contract is silent) → interim settlement by construction stage (new in 2024: signed stage settlements enter the final account without re-pricing; stage payments not below 80%) → final account (thirteen heads; failure to check or to certify in time is deemed acceptance) → retention money (3% cap) and final closure (defects liability period generally 1 year, 2 at most). The chain runs on contract-agreed time limits with a 28-day backstop; judicial enforcement of "accepted at the submitted price" requires an express contractual provision.