Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-29

The legal basis for the employer's claim to the (self-performed or third-party) cost of repair after the contractor refuses to repair quality defects, the repair pre-procedure, the constitutive requirements and the old-new judicial interpretation transition (Fa Shi [2026] No. 12, Articles 16 and 23)

Yes, but three conditions must be met simultaneously: 'non-conformity with the agreed quality attributable to the contractor + notice given with a reasonable period + repair actually carried out at reasonable cost'. Fa Shi [2026] No. 12, Article 16, paragraph 2: where the contractor refuses to repair or fails within a reasonable period to repair to conformity, and the employer, having carried out the repair, requests the contractor to bear the reasonable repair cost, the people's court shall support it; paragraph 1: where the employer requests an order that the contractor pay the repair cost in advance without notifying the contractor to repair, the people's court shall not support it. The old Fa Shi [2020] No. 25, Article 12, supported only a 'request to reduce the project price'; Article 16 of the 2026 interpretation additionally allows a counterclaim for the reasonable cost of repair, rework or alteration with consolidated hearing; the new interpretation takes effect on 30 June 2026, applies only to first-instance cases newly accepted after it takes effect, and prevails over prior interpretations where inconsistent (Article 23).

Applicable Codes

  • 法释〔2026〕12号 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)第十六条、第二十三条
  • 法释〔2020〕25号 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)第十二条、第十六条
  • 中华人民共和国民法典第五百七十七条、第五百八十二条、第五百九十一条、第七百九十三条、第八百零一条
  • GB/T 50500-2024 建设工程工程量清单计价标准 第10.3.13条、第10.5.2~10.5.4条、第8.11.18条
  • 建质〔2017〕138号 建设工程质量保证金管理办法 第九条
  • 建设工程质量管理条例(国务院令第714号,2019修订)第四十一条、第六十六条
  • https://www.court.gov.cn/fabu/xiangqing/504221.html
  • https://www.court.gov.cn/zixun/xiangqing/282111.html

Topic Positioning

This card answers a core dispute at the performance and warranty stages of a construction contract: where the contractor refuses to repair a quality defect (or delays repair without reaching conformity), can the employer hold it liable for the cost of repair carried out by the employer itself or an entrusted third party - the legal basis, the repair pre-procedure, the constitutive requirements, the exclusions, and the temporal divide between the 2026 new interpretation and the old one.

Core Conclusion

One-sentence conclusion: yes, but not unconditionally - the three preconditions of 'attributable to the contractor + notified and given a reasonable period + actually repaired at reasonable cost' must coexist.

1. Current rule (Fa Shi [2026] No. 12, Article 16)

SPC Interpretation (II) on Construction Contract Disputes, Article 16:

  • Paragraph 1: 'Where the construction quality fails to conform to the agreement due to reasons attributable to the contractor, and the employer requests that the contractor pay the repair cost in advance without notifying the contractor to repair, the people's court shall not support it.'
  • Paragraph 2: 'Where the contractor refuses to repair or fails within a reasonable period to repair to conformity, and the employer, having carried out the repair, requests the contractor to bear the reasonable repair cost, the people's court shall support it.'

The actionable path thus formed is: defect attributable to the contractor -> the employer gives written notice to repair with a reasonable period -> the contractor refuses to repair, or repairs but fails to reach conformity within the reasonable period -> the employer repairs itself or entrusts a third party and actually incurs the cost -> the employer claims the reasonable repair cost from the contractor. What is barred is 'suing for an advance repair payment without notice'.

2. Old rule and transition

Fa Shi [2020] No. 25, Article 12, reads: 'Where the construction quality fails to conform to the agreement due to reasons attributable to the contractor, and the contractor refuses to repair, rework or alter, the people's court shall support the employer's request to reduce the project price.' - the remedy under the old line was 'reduction of the price', not an independent claim for the repair cost; Article 16 of the same interpretation opened another channel: 'Where, in a construction contract dispute case brought by the contractor, the employer files a counterclaim on the ground that the construction quality fails to conform to the contract or the law, claiming that the contractor pay liquidated damages or compensate losses including the reasonable cost of repair, rework or alteration, the people's court may hear the claims together.' The 2026 interpretation detaches 'repair cost' from the price-reduction track; where the two are inconsistent, the new interpretation prevails.

3. Layered legal bases

  • Contract liability layer: Civil Code Article 801 - 'where the construction fails to conform to the agreed quality due to reasons attributable to the constructor, the employer has the right to request the constructor to repair, rework or alter free of charge within a reasonable period; where delivery is delayed after the repair, rework or alteration, the constructor shall bear liability for breach'; Article 577 (liability for breach includes continued performance, remedial measures or compensation of losses); Article 582 (where the agreement on liability for breach is unclear, the injured party may reasonably elect to request repair, redoing, replacement, return, or reduction of price or remuneration).
  • Judicial interpretation layer: Fa Shi [2026] No. 12, Article 16 (new); Fa Shi [2020] No. 25, Articles 12 and 16 (old, applying only to cases accepted before the new interpretation took effect).
  • Invalid contract layer: Civil Code Article 793(2), item (1) - 'where the repaired construction passes acceptance, the employer may request the contractor to bear the repair cost'; paragraph 3 of the same article - 'where the employer is at fault for the losses caused by the unqualified construction, it shall bear the corresponding liability'.
  • Pricing and security layer: within the defects liability period, deduction may be made from the retention money or the quality warranty security, and the excess is claimed separately (GB/T 50500-2024, Article 10.5.3); at the settlement stage, deduction is made in the final account under Article 10.3.13 (see the dedicated card on repair cost within the defects liability period / warranty period).

4. Typical scenarios where the claim fails

  • Claiming advance payment without notice of repair -> not supported (Article 16(1)); the correct action is a written demand leaving a record and a sufficient reasonable period.
  • Defect not attributable to the contractor (defects in the design documents provided by the employer, unqualified employer-supplied (free-issue) materials, components or plant, specialist works directly nominated by the employer to a subcontractor, etc.) -> the repair cost is borne by the employer, which organises the repair, and no deduction may be made from the retention money (GB/T 50500-2024, Article 10.5.4).
  • The employer itself at fault -> it bears the corresponding liability for the losses caused by the unqualified works (Civil Code, Article 793(3)).
  • Not yet repaired, suing on an estimated cost -> the factual element 'after the employer repaired' is missing.
  • Allowing the loss to expand -> Civil Code Article 591: 'After one party breaches, the other party shall take appropriate measures to prevent the enlargement of the loss; where no appropriate measures are taken and the loss is enlarged, no compensation may be claimed for the enlarged part. The reasonable expenses incurred by the party in preventing the enlargement of the loss shall be borne by the breaching party.'

Scope and Limits

  • Temporal divide: Fa Shi [2026] No. 12, Article 23 - 'This Interpretation takes effect on 30 June 2026. First-instance construction contract dispute cases newly accepted by the people's courts after this Interpretation takes effect are governed by this Interpretation. Where judicial interpretations previously issued by the Supreme People's Court are inconsistent with this Interpretation, this Interpretation prevails.' That is, first-instance cases newly accepted after 30 June 2026 apply the new Article 16; cases accepted earlier still follow the old Interpretation's Article 12 (reduction of price) and Article 16 (consolidated hearing of counterclaims).
  • 'Reasonable repair cost': it must be actually incurred and proportionate to the scope of the defect, not a pre-repair estimate; where the retention money or the security is insufficient, the excess is claimed separately (GB/T 50500-2024, Articles 10.5.3 and 8.11.18).
  • Bearing the repair cost does not exempt compensation: after the contractor carries out the repair and bears the corresponding cost, its liability to compensate for the losses of the works is not exempted (Jian Zhi [2017] No. 138, Article 9).
  • Within the warranty period, warranty obligations and compensation may further be claimed under Article 41 of the Regulation on Quality Management of Construction Projects, and Article 66 separately imposes an administrative fine of not less than RMB 100,000 and not more than RMB 200,000; administrative liability and the civil claim for repair cost do not affect each other.
  • This applies only where the quality fails to conform to the agreed (or statutory) standard and the defect is repairable; unrepairable defects go to the price-reduction / acceptance track and are outside the scope of this card.

Further Reading

  • Fa Shi [2026] No. 12, Articles 16 and 23, official text: https://www.court.gov.cn/fabu/xiangqing/504221.html
  • Fa Shi [2020] No. 25, Articles 12 and 16, official text: https://www.court.gov.cn/zixun/xiangqing/282111.html
  • Civil Code Articles 577, 582, 591, 793 and 801
  • GB/T 50500-2024 Articles 10.3.13, 10.5.2~10.5.4 and 8.11.18
  • Jian Zhi [2017] No. 138, Measures for Administration of Construction Quality Retention Money, Article 9; Regulation on Quality Management of Construction Projects (State Council Order No. 714, 2019 Revision), Articles 41 and 66

Keywords

  • 修复费用
  • 承包人拒绝修复
  • 未修复至符合约定
  • 先行支付修复费用
  • 修复前置程序
  • 法释〔2026〕12号
  • 法释〔2020〕25号第十二条
  • 民法典第八百零一条