Attribution of the rework and repair period after completion acceptance fails: whether it counts as contractor delay, and in what situations an extension of time may be granted (Civil Code Article 801 + Fa Shi [2020] No. 25 Articles 9-11 + Fa Shi [2026] No. 12 Article 16 + GF-2017-0201 clauses 5.3.4 and 5.4)

In principle the period counts against the contractor's time and no extension is granted: where completion acceptance fails for reasons attributable to the contractor, the period of rework, repair and strengthening up to acceptance rests on the contractor, and the completion date is the date of passing re-acceptance after repair (Fa Shi [2020] No. 25, Article 9(1)); any part falling after the contract completion date is late delivery, for which the contractor bears liability for breach (Civil Code Article 801: 'where overdue delivery results after repair or rework or reconstruction, the constructor shall bear liability for breach'). The only reversal valves lie in the cause: where the failure is due to the employer, or a pre-completion quality dispute is resolved by appraisal finding the quality compliant (Fa Shi [2020] No. 25, Article 11), or the employer delays acceptance or puts the works to premature use without taking-over (Article 9(2) and (3) of the same interpretation), the period is not counted as contractor delay and the time is extended accordingly.

Applicable Codes

  • 《中华人民共和国民法典》(主席令第45号)第五百七十七条、第五百八十四条、第五百八十五条、第七百九十九条、第八百零一条、第八百零三条
  • 法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第九条、第十条、第十一条
  • 法释〔2026〕12号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》第十六条、第二十三条
  • GF-2017-0201《建设工程施工合同(示范文本)》通用合同条款 5.3.3、5.3.4、5.4、5.5、13.2.4
  • 建市〔2020〕96号 GF-2020-0216《建设项目工程总承包合同(示范文本)》通用合同条件 10.1
  • GB 50300-2013 · Unified Standard for Constructional Quality Acceptance of Building Engineering 第5.0.6条
  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.11.10条、第8.11.19条
  • 《建设工程质量管理条例》(国务院令第714号,2019修订)第三十二条
  • 《中华人民共和国建筑法》(主席令第91号)第六十一条

Topic Positioning

After completion acceptance (including acceptance of unit works or sections) fails, the calendar period during which the contractor reworks, repairs and strengthens the works up to acceptance: how is that period attributed in law - does it occupy contract time, is it 'the contractor's' delay, and what liability follows; and in what situations can the period be extended. Applies to time-for-completion disputes arising from the 'failed acceptance -> repair -> re-acceptance' sequence under construction contracts and EPC contracts.

Core Conclusions

1. The principle: it counts against the contractor's time, with no extension.

Article 801 of the Civil Code: 'Where the quality of a construction project fails to meet the agreed requirements due to the constructor's fault, the employer is entitled to require the constructor to repair or rework or reconstruct free of charge within a reasonable period. Where overdue delivery results after repair or rework or reconstruction, the constructor shall bear liability for breach.' The statute ties the chain 'repair -> overdue delivery -> liability for breach' directly to the precondition 'due to the constructor's fault'; the repair period caused by the contractor therefore occupies the contractor's own contract time.

Supporting rules:

  • Article 32 of the Regulation on Quality Management of Construction Projects (State Council Decree No. 714, 2019 revision): 'The construction unit is responsible for repair of construction projects in which quality problems arise during construction or which fail completion acceptance.'
  • GF-2017-0201 Model Construction Contract, general conditions 5.4.1: 'Where the works fail to meet the requirements due to the contractor's fault, the employer is entitled at any time to require the contractor to take remedial measures until the quality standard required by the contract is met; the costs thereby increased and/or the time thereby delayed are borne by the contractor. Where the defects cannot be remedied, clause 13.2.4 [rejection of the whole or part of the works] applies.'
  • GB 50300-2013 Unified Standard for Constructional Quality Acceptance of Building Engineering, Article 5.0.6, gives four outlets for failed work: (1) inspection lots that have been reworked or repaired must be re-accepted; (2) inspection lots that testing and appraisal by a qualified testing agency show can meet the design requirements must be accepted; (3) inspection lots that testing and appraisal show cannot meet the design requirements but which the original designer confirms by check calculation can satisfy safety and service function may be accepted; (4) sub-item and divisional works that have been repaired or strengthened may, where safety and service function requirements are met, be accepted in accordance with the technical treatment scheme and the agreed documents. The commentary stresses that outlet (4) 'must not serve as a route for lowering quality requirements or passing acceptance in disguise'.

2. The completion date is the date of passing re-acceptance after repair; delay runs from there.

Article 9 of Fa Shi [2020] No. 25: 'Where the parties dispute the actual completion date of a construction project, the people's court shall determine it as follows: (1) where the project has passed completion acceptance, the date of passing completion acceptance is the completion date; (2) where the contractor has submitted a completion acceptance report and the employer delays acceptance, the date of the contractor's submission of the acceptance report is the completion date; (3) where the employer uses the project without completion acceptance, the date of transferring possession is the completion date.'

On this basis: where repair is followed by passing re-acceptance, the completion date is the date of passing re-acceptance; the whole period from the day after the agreed completion date to that date (including cumulative second-round rework and demolition and redoing) is the delay period. Under Article 799 of the Civil Code and Article 61 of the Construction Law, a construction project may be delivered for use only after passing acceptance; it may not be delivered without acceptance or where acceptance has failed - until the works pass acceptance, no completion effect arises.

3. Affirmative situations (the repair period counts against the contractor; no extension).

  1. Where completion acceptance (including unit/section acceptance) fails due to the contractor's workmanship, the period of repair up to acceptance counts against the contractor; the repair costs and the delay liability both rest on the contractor (Civil Code Article 801; the Regulation Article 32; GF-2017-0201 clause 5.4.1; GB 50300-2013 Article 5.0.6).
  2. The contractor covers concealed parts without notifying the supervising engineer to attend and inspect, and is instructed to drill or uncover for inspection - GF-2017-0201 general conditions 5.3.4: 'Where the contractor covers a concealed part of the works without notifying the supervising engineer to inspect, the supervising engineer is entitled to instruct the contractor to drill or uncover for inspection; regardless of whether the concealed part is of acceptable quality, the costs thereby increased and/or the time thereby delayed are borne by the contractor.' (Compare 5.3.3: where inspection proves the quality compliant with the contract, the employer bears the increased costs and/or delay and pays a reasonable profit; where non-compliant, the contractor bears them.)
  3. The contractor fails to apply for an extension within the agreed period without reasonable excuse - Fa Shi [2020] No. 25 Article 10(2): 'Where the parties agree that failure by the contractor to apply for an extension of time within the agreed period means no extension is granted, the agreement governs, except where the employer agrees to an extension after the period expires or the contractor shows a reasonable excuse.' Conversely, Article 10(1) allows a contractor to claim an extension where, although it did not obtain confirmation of the extension, it can prove that it applied to the employer or the supervising engineer for an extension within the period agreed in the contract and the grounds for extension meet the contract, likewise where the contract requires confirmation by a site instruction record.
  4. The contractor refuses to repair, or fails to repair to the agreed standard within a reasonable period - Fa Shi [2026] No. 12 Article 16: 'Where the quality of a construction project fails to meet the agreed requirements due to the contractor, and the employer, without notifying the contractor to repair, requests that the contractor first pay the repair costs, the people's court will not support the request. Where the contractor refuses to repair or fails to repair to the agreed standard within a reasonable period, and the employer, having repaired, requests the contractor to bear the reasonable repair costs, the people's court will support the request.' Where the employer repairs itself or engages another to repair, the period still counts against the contractor's delay and the costs are borne by the contractor.
  5. Where re-acceptance after repair again fails and a second round of rework is needed up to final acceptance - the cumulative period all counts.
  6. Realising liability for delay: GB/T 50500-2024 Article 8.11.19: 'Where losses to the employer arise from the contractor's fault, the employer may choose one or more of the following for compensation: 1 extending the defects warranty period; 2 requiring the contractor to pay the additional costs incurred by the affected party; 3 requiring the contractor to pay delay damages; 4 requiring the contractor to pay liquidated damages as agreed in the contract.' Adjustment of liquidated damages follows Article 585 of the Civil Code (increase where below the loss, appropriate reduction where grossly excessive; where liquidated damages are agreed for delayed performance, the debt must still be performed after payment); the scope of damages follows Article 584 (losses caused by the breach, including the benefits obtainable after performance of the contract, but not exceeding what the breaching party foresaw or should have foreseen at the time of conclusion); the choice among continued performance, remedial measures and damages follows Article 577.
  7. EPC contract (GF-2020-0216) item 10.1.2: 'Where completion acceptance fails, the engineer shall issue instructions per the acceptance opinions requiring the contractor to rework, repair or take other remedial measures for the failed works; the costs thereby increased and/or the time thereby delayed are borne by the contractor. After completing the rework, repair or other remedial measures, the contractor shall re-submit the completion acceptance application and re-acceptance follows the procedure agreed in this item.'

4. Negative situations (the repair period is not counted as contractor delay; time extended).

  1. The failure is due to the employer (employer-supplied (free-issue) materials or plant of failing quality, employer instructions or specified methods causing rework) - GF-2017-0201 general conditions 5.4.2: 'Where the works fail due to the employer's fault, the increased costs and/or delayed time are borne by the employer, which also pays the contractor a reasonable profit.' Where the employer fails to provide raw materials, equipment, the site, funds or technical documents at the agreed time and to the agreed standard, the contractor may, under Article 803 of the Civil Code, extend the construction date and claim losses from suspension and idle resources.
  2. A pre-completion quality dispute where appraisal proves the quality compliant - Fa Shi [2020] No. 25 Article 11: 'Where, before completion, the parties dispute the quality of the project and the quality is proven compliant by appraisal, the appraisal period is a period of extension of time.'
  3. Delayed acceptance by the employer - the completion date is the date the contractor submitted the acceptance report (Fa Shi [2020] No. 25 Article 9(2)); GF-2020-0216 item 10.1.2 further provides that where, due to the employer, completion acceptance is not completed within 42 days of the engineer receiving the contractor's completion acceptance application, the date the contractor submitted the application is the actual completion date; and where the employer delays organising acceptance and issuing the taking-over certificate, it pays liquidated damages per day of delay at the LPR on the contract price.
  4. The employer uses the works without completion acceptance - the completion date is the date of transfer of possession (Fa Shi [2020] No. 25 Article 9(3); GF-2020-0216 item 10.1.2); time thereafter is not counted against the contractor.
  5. The employer-fault claim scope (including profit): GB/T 50500-2024 Article 8.11.10 lists the situations in which profit may be claimed, including 'delay by the employer in providing construction drawings or the construction site', 'failed work caused by the failing quality, delayed provision or changed delivery point of employer-provided materials', and 'errors in setting out or rework of the works caused by the employer', and lists the four components of standby and standdown losses (idle labour costs, material losses, plant standing idle, other cost losses); the same article makes clear that 'for economic loss and/or delay events caused by government authorities, the time is extended accordingly and the economic losses suffered by the employer and the contractor are borne by each party separately'.

5. Keep the three layers apart.

  • The factual time layer: whether repair occupies calendar time - yes; until acceptance passes, no completion effect arises.
  • The attribution layer: whether the period is 'the contractor's' delay - depends on who caused the quality failure.
  • The remedy layer: what the contractor bears - its own repair costs plus delay damages / liquidated damages / damages (chosen per the contract and GB/T 50500-2024 Article 8.11.19); where the employer is at fault, it bears the costs and the time and pays a reasonable profit.

Scope and Limits

  • This card covers only the attribution of rework and repair periods caused by quality failure; extension-of-time (EOT) claims for other events (design changes, force majeure, delayed payment by the employer) are assessed separately under the critical path (whether the event affects total duration) and the contractual claim time limits (typically a Notice of Claim within 28 days of the event, followed by a detailed claim within a further 28 days).
  • An extension claim needs evidence and procedure: where the contract requires confirmation by the employer or the supervising engineer by site instruction record, the contractor may still claim on the basis of 'applied within the period + grounds meeting the contract' without confirmation (Fa Shi [2020] No. 25 Article 10(1)); where the contract deems failure to apply in time a waiver of extension, the agreement governs, unless the employer later consents or the contractor has a reasonable excuse (paragraph 2).
  • Interface between old and new interpretations: Fa Shi [2026] No. 12 Article 23: 'This Interpretation takes effect on 30 June 2026 and applies to first-instance construction contract dispute cases newly accepted by the people's courts after that date. Where earlier SPC interpretations conflict with this Interpretation, this Interpretation prevails.' The application of Article 16 (prior notice of repair and reasonable repair costs) turns on when the first-instance case was newly accepted; but the root of the attribution rule is Civil Code Article 801, unchanged by the change of interpretation.
  • 'May be accepted' under GB 50300-2013 Article 5.0.6(4) requires acceptance per the technical treatment scheme and the agreed documents without prejudice to safety and main service functions; the responsible party still bears the corresponding economic liability under laws and regulations and remains subject to penalties; it must not be used to pass acceptance in disguise.
  • 'Whether the repair period counts against time' and 'warranty liability' run on separate tracks: even where premature use by the employer is deemed approval of quality, and even after the defects liability period expires, the contractor's warranty obligation and its quality liability for the foundations and the main structure are not thereby discharged.

Further Reading

  • Civil Code of the PRC (Presidential Decree No. 45), Articles 577, 584, 585, 799, 801 and 803.
  • Fa Shi [2020] No. 25, SPC Interpretation (I) on Construction Contract Disputes: Article 9 (determining the completion date), Article 10 (application for extension and deemed non-extension), Article 11 (extension during quality appraisal).
  • Fa Shi [2026] No. 12, SPC Interpretation (II) on Construction Contract Disputes: Article 16 (prior notice of repair and reasonable repair costs), Article 23 (effective date and application to newly accepted first-instance cases).
  • GF-2017-0201 Model Construction Contract, general conditions 5.3.3 [quality inspection by the supervising engineer], 5.3.4 [contractor covering work without notice], 5.4 [treatment of failed work], 5.5 [testing of quality disputes], 13.2.4 [rejection of the whole or part of the works].
  • Jian Shi [2020] No. 96, GF-2020-0216 Model Project EPC Contract, general conditions clause 10.1 [completion acceptance], item 10.1.2 [completion acceptance procedure].
  • GB 50300-2013 Unified Standard for Constructional Quality Acceptance of Building Engineering, Article 5.0.6 and its commentary.
  • GB/T 50500-2024, China national pricing standard for BOQ: Article 8.11.10 (employer-fault claims and profit) and Article 8.11.19 (compensation for employer losses caused by the contractor).
  • Regulation on Quality Management of Construction Projects (State Council Decree No. 714, 2019 revision) Article 32; Construction Law of the PRC (Presidential Decree No. 91) Article 61.