Rework caused by non-conforming materials: the supplier's (seller's) compensation scope and the recourse chain
The supplier's liability has three tiers: ① Article 40 of the Product Quality Law — the return/exchange obligation (refund on return / price difference on exchange / return freight and miscellaneous); ② direct rework losses (GB/T 50500-2024, Clause 8.11.9: labor, material, and machinery costs of removal and redoing, direct losses of scrapped materials, extra inspection and testing costs); ③ indirect losses (idle labor, plant standby, suspension management fee and profit, statutory fees, schedule loss, liquidated damages). Claim against the seller first; after compensating, the seller recovers from the producer where the producer is liable — premised on fault characterization, timely objection, and a complete evidence chain; other contract terms prevail.
Applicable Codes
- 《民法典》第五百零六条、第五百六十八条、第五百八十二条、第五百八十四条、第五百九十一条、第五百九十二条、第六百一十七条、第六百二十一条、第八百零一条
- 《产品质量法》(2018修正)第二条、第四十条、第四十三条
- 《建筑法》(2019修正)第五十九条
- 《建设工程质量管理条例》(2019修订)第二十九条
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.11.9条
- 法释〔2026〕12号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》第十六条、第二十三条
Topic Positioning
When non-conforming materials cause rework, the claimable cost list, bases of claim, and recourse chain against the supplier (seller) — a three-tier liability framework: return/exchange obligation → direct losses → indirect losses.
Core Conclusions
① The material itself: Article 40 of the Product Quality Law — non-conforming materials shall be repaired, replaced, or returned (including refund on return, price difference on exchange, and return freight and miscellaneous costs). ② Direct rework losses: GB/T 50500-2024, Clause 8.11.9, items 4 and 5 — labor, material, and machinery costs of removing non-conforming work and reconstructing, direct losses of scrapped (damaged) materials, and additionally incurred inspection, checking, and testing costs. ③ Indirect losses: idle labor, plant standby (rented at actual rent, owned at shift quota rates, T/YJXB 0001-2023, Clauses 4.0.3, 5.0.3), suspension management fee (not exceeding the normal construction period, not zero, Clause 4.0.8), suspension profit (daily profit × suspension days, Clauses 4.0.9, 5.0.9), increased statutory fees, schedule delay losses, and contract liquidated damages. Recourse chain: claim against the seller first; after compensating, where the producer is liable the seller has the right of recourse against the producer — no need to chase the manufacturer yourself; special terms of the sales contract prevail. Three preconditions: fault characterization (the rework must be caused by material non-conformity, proven by testing/appraisal), the objection period (raised in writing in time per the contract), and the evidence chain (delivery receipts, quality certificates, on-site re-inspection reports, rework signed instructions, cost ledgers).
Applicable Boundaries
Applies only where the supplier's materials are non-conforming and cause rework; rework caused by the contractor's own operational errors is not covered (costs borne by itself, not measured). Special contract terms on quality liability and liquidated damages prevail. Claims against the employer proceed separately under the 28-day dual-node procedure, running in parallel with the supplier claim without conflict.
Further Reading
Product Quality Law (2018 revision), Article 40; GB/T 50500-2024, Standard for Valuation of Construction Works with Bills of Quantities, Clause 8.11.9; T/YJXB 0001-2023, Standard for Calculating Contractor's Costs upon Work Suspension of Construction Works, Clauses 4.0.3, 4.0.8, 4.0.9, 5.0.3, 5.0.8, 5.0.9; GB 50300-2013, Unified Standard for Constructional Quality Acceptance of Building Engineering, Clause 5.0.6 (re-acceptance path after rework).
Keywords
- 商品混凝土质量不合格
- 供应商赔偿责任
- 民法典第六百一十七条
- 质量瑕疵担保
- 退货减价赔偿
- 因果关系抗辩
- 材料进场检验
- 返工损失赔偿