The statutory red lines on the permissible range of security deposits in construction works and identification of violation types: only four categories may be collected -- tender security, performance security, works quality retention and migrant worker wage security -- and any other deposit collected under any name is unlawful; restriction to cash is banned, guarantees from financial institutions must be accepted, and deposits must be accounted for and refunded at expiry; plus unreasonable deposit restrictions at the levels of tender documents and policy documents, with the matching liability clauses
Article 13 of the Regulation on Ensuring Payment to Small and Medium-sized Enterprises (State Council Order No. 802): apart from the lawfully established tender security deposit, performance security deposit, works quality retention money and migrant worker wage security deposit, no other security deposit may be collected in any form in construction; deposits may not be restricted to cash, and where an SME provides security by a guarantee issued by a financial institution or the like it must be accepted; after the security period expires, timely accounting with the SME and refund are required. Violations are pursued under Article 31(5) (on refusal to correct, responsible leaders and directly liable personnel are sanctioned); at the policy-document level, Article 11 of the Fair Competition Review Rules for the Tendering and Bidding Field applies in addition -- no demands for deposits beyond the four categories, no restriction of the form of payment, no requirement that guarantees (insurance) be issued by a specified institution, and no refund preconditions set outside the tender documents.
Applicable Codes
- 《保障中小企业款项支付条例》(2025修订,国务院令第802号,2025年6月1日施行)第13、14、15、17、31、33、34、36条
- https://www.mee.gov.cn/zcwj/gwywj/202503/t20250325_1104643.shtml
- 《招标投标领域公平竞争审查规则》(国家发展改革委等八部门令第16号)第11条
- 《中华人民共和国招标投标法实施条例》(2018修订)第22条、第58条、第60条、第66条
- 最高人民法院法释〔2020〕25号第十七条
- 最高人民法院法释〔2026〕12号第十四条、第二十三条
- 建质〔2017〕138号第二条、第七条
- GB/T 50500-2024 第10.5节
Topic Positioning
The substantive red lines in construction on 'which security deposits may be collected, at what rates and in what form, and when they must be refunded', and how to map a charge heading actually encountered onto a violation type and the matching provision. It serves contractors' and subcontractors' compliance review of tender documents and contract clauses, and the characterisation of violations where a guarantee is refused or a deposit is occupied long-term.
Core Conclusions
1. The range red line (the positive list is the whole list) Article 13(1) of the Regulation on Ensuring Payment to Small and Medium-sized Enterprises (State Council Order No. 802): apart from the lawfully established tender security deposit, performance security deposit, works quality retention money and migrant worker wage security deposit, no other security deposit may be collected in any form in construction. The rates and methods of collection must comply with laws, administrative regulations and the relevant state provisions. Any fifth heading therefore -- an 'integrity deposit', a 'clean-government deposit', a 'performance assurance fund', a 'coordination fee', wage-type deposits other than the migrant worker wage security deposit, and the like -- is unlawful regardless of whether it sits in the tender documents or in special contract clauses, and regardless of amount.
2. Form and refund red lines Article 13(2): government organs, public institutions and large enterprises shall not restrict security deposits to cash. Where an SME provides security by a guarantee issued by a financial institution or the like, government organs, public institutions and large enterprises shall accept it. Article 13(3): government organs, public institutions and large enterprises shall, in accordance with law or the contract, promptly account with the SME for the security deposits collected and refund them after the security period expires. Policy documents constrain in the same direction (Fair Competition Review Rules for the Tendering and Bidding Field, Order No. 16 of eight departments, Article 11): policy-making organs, when formulating deposit-related policy measures, shall not impose the following unreasonable restrictions -- (1) restricting tenderers from lawfully collecting security deposits; (2) requiring business entities to pay security deposits other than the tender security deposit, performance security deposit, works quality retention money and migrant worker wage security deposit; (3) restricting the form in which business entities pay security deposits; (4) requiring business entities to obtain the guarantee (insurance) from a specified institution; (5) setting preconditions for the refund of security deposits outside the tender documents; (6) other unreasonable deposit-related restriction measures.
3. A four-way taxonomy of violations and the matching provisions
- Out-of-range collection (extra headings): Article 13(1); liability under Article 31(5), 'unlawful collection of security deposits'.
- Unlawful form (cash only, refusal of bank guarantees or construction guarantee insurance, a designated issuer): Article 13(2); at the policy-document level, Order No. 16 Article 11(3) and (4).
- Non-refund at expiry (no accounting; delay on grounds of an unfinished final-account audit or a change of leadership): Article 13(3); Article 14 forbids refusal or delay of payment on the ground of a change of the legal representative or principal responsible person, the running of internal payment processes, or -- where the contract is silent -- awaiting completion-acceptance filing or the final-account audit; Article 15 requires the undisputed parts to be paid first; delay attracts overdue interest (Article 17: the agreed rate may not be lower than the 1-year Loan Prime Rate at the time of contract conclusion; absent agreement, 0.05% per day).
- Preset in the tender documents (cash payment demanded, a designated issuer of the guarantee, refund conditions outside the documents): at the tendering stage, objection first, then complaint -- Implementing Regulations of the Tendering and Bidding Law Article 22 (objections to the tender documents must be raised no later than 10 days before the tender submission deadline; the tenderer answers within 3 days of receipt and suspends the tendering activities before answering) and Article 60 (a party believing that the tendering activities breach laws or administrative regulations may complain to the relevant administrative supervision department within 10 days of knowing or being expected to know; a complaint on a matter under Article 22 must first be raised with the tenderer as an objection, and the objection-answer period is excluded from the time limit).
4. Where liability lands Government organs and public institutions: Article 31(5) -- unlawfully collecting security deposits, refusing the security provided by an SME through a guarantee issued by a financial institution or the like, or failing to promptly account with the SME for the security deposit and refund it: the superior organ or the supervisory department orders correction; on refusal to correct, the responsible leaders and directly liable personnel are sanctioned under law. State-owned large enterprises: Article 33(1) -- delaying payments to SMEs with adverse consequences or impact: the responsible state-enterprise managers are sanctioned under law. Large enterprises as a whole: the Regulation sets no fine for unlawfully collected security deposits; the administrative penalties under Article 34 target only the failure to publish overdue payment information in the annual report, or concealing the truth or falsification (handled by the market regulation department under law); in practice, reliance is placed on complaint referral, supervision letters, interviews and notifications, bad-faith publicity and civil remedies. These red lines depend on the status of the parties: the claiming party must be an SME by its size type at contract conclusion, and procurement by organisations using fiscal funds follows the rules for government organs and public institutions by reference (Article 36).
Boundaries of Application
- The positive list answers 'whether a deposit may be collected', not 'how much': the caps on performance security, the retention percentage cap, the length of the defects liability period, and the pre-completion exclusivity of performance security versus retention follow the Implementing Regulations of the Tendering and Bidding Law Articles 58 / 66, Jian Zhi [2017] No. 138 and the corresponding clauses of GB/T 50500-2024.
- 'Lawfully established' for the four deposits means that collection requires a basis in law, administrative regulation or the relevant state provisions; local documents, trading-platform rules and a tenderer's internal rules cannot create a fifth category.
- The right to the return of retention money on expiry: Article 17 of Fa Shi [2020] No. 25 lists three refund situations (the agreed refund period expires; absent agreement, two years from completion acceptance; where acceptance is delayed for reasons attributable to the employer, counted from 90 days after submission of the completion acceptance report); Article 14 of Fa Shi [2026] No. 12, effective from 30 June 2026, further provides that where the construction contract is terminated, the retention refund period runs from the contractor's withdrawal from site (where termination occurs after withdrawal, from the date of termination), and where the contract is void and the works are unfinished, the base is the discounted compensation payable and the period likewise runs from withdrawal; cases newly accepted at first instance after that interpretation takes effect apply it (Article 23), and where it conflicts with the former interpretation, the new one prevails.
- Determining violations and the remedy channels (complaint platforms, letters of inquiry and interviews, supervision and notification, bad-faith penalties, litigation/arbitration) are procedural matters at another level and are not developed in this card.
Further Reading
- Regulation on Ensuring Payment to Small and Medium-sized Enterprises (2025 revision, State Council Order No. 802, effective 1 June 2025, revising and replacing State Council Order No. 728 of 2020), Articles 13, 14, 15, 17, 31, 33, 34 and 36. Original text: https://www.mee.gov.cn/zcwj/gwywj/202503/t20250325_1104643.shtml
- Fair Competition Review Rules for the Tendering and Bidding Field (Order No. 16 of the NDRC and seven other departments), Article 11.
- Implementing Regulations of the Tendering and Bidding Law of the PRC (2018 revision), Articles 22, 58, 60 and 66.
- Supreme People's Court, Fa Shi [2020] No. 25 Article 17; Fa Shi [2026] No. 12 Articles 14 and 23.
- Caps and periods in detail: Jian Zhi [2017] No. 138 Article 2 (defects liability period generally 1 year, no more than 2 years at most) and Article 7 (retention cap 3%); GB/T 50500-2024 Section 10.5.