Checklist of payment compliance obligations under the Regulation on Ensuring Payment to Small and Medium-sized Enterprises (2025 revision, State Council Decree No. 802): 30-day and 60-day-maximum payment terms for state organs and public institutions and 60-day terms for large enterprises, and the starting points of those terms; prohibition of third-party payment conditions; delayed acceptance treated as expiry of the term; prohibition of compulsory commercial bills of exchange; no compelling use of audit conclusions as the settlement basis; security limited to four types and not restricted to cash; overdue interest at 0.05% per day; payment of undisputed portions first; and information disclosure requirements
State organs and public institutions must pay within 30 days of delivery of the goods, works or services, and where the contract provides otherwise, the term may never exceed 60 days; large enterprises must pay within 60 days and may not agree that receipt of payment from a third party is a condition of payment, nor pay SMEs in proportion to the progress of a third party's payment (Article 9). The payment term runs from the date of passing inspection or acceptance, or from the date the parties confirm the settlement amount under progress-based or periodic settlement; where a state organ, public institution or large enterprise delays inspection or acceptance, the term runs from the expiry of the agreed inspection or acceptance period (Article 10). The agreed overdue interest rate may not be lower than the 1-year LPR at the time of conclusion of the contract; failing agreement, interest accrues at 0.05% per day (Article 17). In project construction only four types of security may be collected - tender security, performance security, works quality retention money and migrant worker wage security - and they may not be restricted to cash; guarantee letters from financial institutions must be accepted (Article 13); state organs, public institutions and state-owned large enterprises must not compel the use of the audit authority's audit conclusion as the basis for settlement (Article 12).
Applicable Codes
- 《保障中小企业款项支付条例》(2025修订,国务院令第802号)第2—20条 https://www.gov.cn/gongbao/2025/issue_11966/202504/content_7017465.html
- 《中华人民共和国民法典》第153条第1款、第510条、第511条第4项
- 《最高人民法院关于大型企业与中小企业约定以第三方支付款项为付款前提条款效力问题的批复》(法释〔2024〕11号) http://gongbao.court.gov.cn/Details/a56bf04193752b0ae2dd77152dbeb3.html
Topic Positioning
This card sets out the payment compliance obligations of state organs, public institutions and large enterprises when purchasing goods, works and services from small and medium-sized enterprises under the Regulation on Ensuring Payment to Small and Medium-sized Enterprises (2025 revision, State Council Decree No. 802): payment terms and their starting points, prohibited payment conditions, red lines on collecting security, overdue interest, payment of undisputed portions first, information disclosure and internal compliance requirements. It can be used for reviewing contract payment clauses, pressing payment claims and compliance self-checks.
Core Conclusions
1. Scope of application and the definition of parties
- Scope: state organs, public institutions and large enterprises purchasing goods, works and services and paying small and medium-sized enterprises must comply with this Regulation (Article 2).
- Parties: SMEs means medium, small and micro enterprises established in accordance with law within China and identified under the SME classification standards approved by the State Council; large enterprises means enterprises other than SMEs; size classification is determined as at the conclusion of the contract; when contracting with a state organ, public institution or large enterprise, an SME must proactively disclose that it is an SME (Article 3).
- The basic prohibition (Article 7): 'State organs, public institutions and large enterprises must not require small and medium-sized enterprises to accept unreasonable payment periods, methods, conditions or liability for breach, and must not delay payment for goods, works or services due to small and medium-sized enterprises.'
2. Budget and funds (Article 8) Where a state organ or public institution uses fiscal funds to procure from an SME, it must strictly follow the approved budget and must not procure without a budget or beyond the budget. The funds required for government-invested projects must be secured in place in accordance with relevant state provisions; contractors must not be made to construct on advance financing.
3. Payment terms and their starting points (Articles 9 and 10)
- State organs and public institutions: payment within 30 days of delivery of the goods, works or services; where the contract provides otherwise, that provision governs, but the payment term may never exceed 60 days.
- Large enterprises: payment within 60 days of delivery; where the contract provides otherwise, that provision governs, but the payment term must be agreed reasonably by reference to industry norms and trade practice and payment must be made promptly; they 'must not agree that receipt of third-party payment is a condition for paying an SME, or pay an SME in proportion to the progress of third-party payment'.
- Where laws, administrative regulations or other state provisions provide otherwise on payment terms, those provisions govern.
- Where the contract provides for progress-based settlement, periodic settlement or the like, the payment term runs from the date on which both parties confirm the settlement amount (Article 9).
- Where passing inspection or acceptance is agreed as the condition of payment, the payment term runs from the date the inspection or acceptance passes; the parties must agree in the contract a clear and reasonable inspection or acceptance period and complete it within that period; where a state organ, public institution or large enterprise delays inspection or acceptance, the payment term runs from the expiry of the agreed inspection or acceptance period (Article 10).
4. Non-cash payment, audit and security (Articles 11-13)
- Non-cash payment such as commercial bills of exchange and electronic receivables vouchers: must be clearly and reasonably provided for in the contract; SMEs must not be compelled to accept them, and they must not be used covertly to extend the payment term.
- Audit: 'State organs, public institutions and state-owned large enterprises must not compel the use of the audit conclusion of an audit authority as the basis for settlement, except where laws and administrative regulations provide otherwise' (Article 12).
- Security: apart from the lawfully established tender security, performance security, works quality retention money and migrant worker wage security, no other security may be collected in project construction in any form; the rates and methods of collection must comply with laws, administrative regulations and relevant state provisions; security must not be restricted to cash; where an SME provides security by a guarantee letter issued by a financial institution or the like, the state organ, public institution or large enterprise must accept it; when the security period expires the amounts must be verified and refunded promptly.
5. Prohibited grounds for refusing or delaying payment, and paying undisputed portions first (Articles 14-15) Payment must not be refused or delayed on the grounds of a change of legal representative or principal person in charge, the running of internal payment procedures, or - absent contractual provision - awaiting filing of completion acceptance or final-account audit; where part of the subject matter is disputed but this does not affect the performance of the rest, the obligation to pay the undisputed portion promptly must be performed.
6. Overdue interest (Article 17) Delayed payment carries overdue interest: where the parties agree an overdue interest rate, the agreed rate may not be lower than the 1-year loan prime rate at the time of conclusion of the contract; failing agreement, overdue interest is paid at 0.05% per day.
7. Financing support, information disclosure and compliance management (Article 16, Articles 18-20) Where an SME finances against receivables, the state organ, public institution or large enterprise must confirm the debtor-creditor relationship within 30 days of the SME's request for confirmation. State organs and public institutions must, before 31 March each year, publish by website, newspapers and other means readily accessible to the public information on the number and amounts of contracts with SME payments still overdue from the previous year; large enterprises must include this information in their annual reports and publish it through the National Enterprise Credit Information Publicity System in accordance with law; large enterprises must bring work on ensuring payment to SMEs into their risk control and compliance management systems and urge their wholly owned or controlled subsidiaries to pay promptly. SMEs and their staff who raise payment claims or complaints must not be intimidated or subjected to retaliation.
Scope and Limits
- The classification of parties is fixed as at the conclusion of the contract; where the counterparty is not an SME as defined (a natural person, an individual industrial and commercial household, or an enterprise above the thresholds), the payment-term and overdue-interest provisions of this Regulation do not apply.
- The payment term may be varied by contract (for state organs and public institutions, never exceeding 60 days), but the mandatory rules - 'no third-party payment conditions' and 'no unreasonable payment terms' - may not be contracted around; a clause making payment conditional on third-party payment is invalid under Article 153(1) of the Civil Code (Fa Shi [2024] No. 11, Article 1).
- The articles cited here are those of the 2025 revision (State Council Decree No. 802). The numbering of the old 2019 version (State Council Decree No. 728) differs (old Article 6 and old Article 8 correspond to new Article 7 and Article 9(2) respectively), so a mapping must be made when citing historical replies or precedents by article number.
- Overdue interest: 0.05% per day is the statutory rate absent agreement; with an agreement there is only the floor of 'not lower than the 1-year LPR at the time of conclusion'; the actual claim should still be framed by proof of loss and the basis of the claim (reasonable determination after the clause is invalidated vs direct application of the Regulation).
Further Reading
- Full text of the Regulation on Ensuring Payment to Small and Medium-sized Enterprises (2025 revision, State Council Decree No. 802), State Council Gazette: https://www.gov.cn/gongbao/2025/issue_11966/202504/content_7017465.html (Chapter 1 general provisions, Articles 1-7; Chapter 2 payment provisions, Articles 8-20)
- SPC Reply on the Validity of Clauses by which a Large Enterprise Makes Payment to an SME Conditional on Receipt of Third-party Payment (Fa Shi [2024] No. 11): http://gongbao.court.gov.cn/Details/a56bf04193752b0ae2dd77152dbeb3.html
- SPC Fa Da Wang selected Q&A (26th batch), question 1 (determining the payment term after a third-party payment condition clause is invalidated): https://www.court.gov.cn/zixun/xiangqing/472471.html
- Related: Civil Code Articles 153(1), 510 and 511(4); Regulation on Guaranteeing Wage Payment to Migrant Workers, Articles 29, 30, 36 and 37 (advance payment and discharge of wages)