Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-29

Initiation and procedural rules of judicial construction cost expert assessment: timing of the application in litigation/arbitration; admissibility review of 'specialised issues'; the competent court; selection of the expert by agreement or by appointment; bearing of the assessment fee; the expert's duty to appear in court and the consequences of refusal; determination of the assessment time limit

Judicial cost assessment cannot be initiated unilaterally before litigation; it can only be sought within litigation or arbitration: in litigation, a written application must be filed before the evidence period expires, and the matter applied for must be relevant and meaningful to the facts to be proven, otherwise the court will not permit it (Civil Procedure Law Article 79; SPC Civil Procedure Interpretation Article 121); in arbitration, apply to the arbitral tribunal (Arbitration Law (2025 revision) Article 56). The expert is determined by agreement of both parties, failing which the court appoints; in arbitration, by the parties' agreement or the tribunal's appointment. The assessment fee follows 'whoever asserts, bears': the court orders the party to pay the institution directly, and may not collect or disburse on its behalf (Measures for Payment of Litigation Fees Article 12). Where the expert refuses to appear after being notified by the court, the opinion may not serve as the basis for finding facts, and the party that paid the fee may demand its return (Civil Procedure Law Article 81). Construction contract disputes are governed by the jurisdiction rules for real-property disputes (SPC Civil Procedure Interpretation Article 28(2)).

Applicable Codes

  • 《中华人民共和国民事诉讼法》(2023修正)第七十九条、第八十一条
  • 《最高人民法院关于适用〈中华人民共和国民事诉讼法〉的解释》(法释〔2015〕5号,2022修正)第二十八条、第一百二十一条
  • 《中华人民共和国仲裁法》(2025修订)第五十六条
  • 《诉讼费用交纳办法》(国务院令第481号)第十二条
  • 《建设工程造价鉴定规范》GB/T 51262-2017 第3.7.1条及表3.7.1
  • 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》(法释〔2026〕12号)第十三条、第二十三条
  • 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》(法释〔2020〕25号)第二十一条

Topic Positioning

How this 'procedural weapon' - judicial construction cost assessment - is initiated, where, by whom the assessment is made, who pays first, and what happens if the expert refuses to appear. For settlement disputes that have entered litigation or arbitration and require the construction cost to be quantified; independent of the substantive questions of 'whether a settlement basis was agreed' or 'whether settlement must follow the audit result'.

Core Conclusions

1. It can only be initiated within proceedings - not unilaterally before litigation. A review opinion issued by a cost consultancy unilaterally engaged before litigation is not a judicial assessment and can only be submitted as the party's own evidence.

  • Civil Procedure Law Article 79: 'A party may apply to the people's court for assessment of specialised issues for ascertaining facts. Where a party applies, the expert shall be determined by agreement of both parties; failing agreement, the people's court shall appoint one. Where no party has applied but the people's court deems assessment necessary for a specialised issue, it shall commission a qualified expert.'
  • SPC Interpretation on the Application of the Civil Procedure Law (Fa Shi [2015] No. 5, 2022 amendment) Article 121: 'An application for assessment may be made before the expiry of the evidence period. Where the matter applied for is unrelated to the facts to be proven, or is of no significance for proving them, the people's court shall not permit it. Where the court permits the application, it shall organise both parties to agree on a qualified expert; failing agreement, the court appoints one. Where the conditions for evidence collection by the court of its own motion are met, the court shall commission the assessment of its own motion and, after seeking the parties' opinions, appoint a qualified expert.'
  • Arbitration route: Arbitration Law (2025 revision) Article 56: 'A party may apply to the arbitral tribunal for assessment of specialised issues for ascertaining facts. Where the tribunal, on a party's application or its own judgment, deems assessment of a specialised issue necessary, it may have the assessment made by an expert agreed by the parties or by an expert appointed by the tribunal. At a party's request or the tribunal's requirement, the expert, upon notice by the tribunal, shall attend the hearing. With the tribunal's permission, the parties may question the expert.'

2. Substantive threshold of the application (three points simultaneously): (1) the matter is a 'specialised issue for ascertaining facts' (quantifying the construction cost) - specific, quantifiable and relevant to the facts to be proven; (2) the scope applied for is confined to the disputed part - a blanket application to assess 'the cost of the entire works' is inappropriate; (3) assessment is substantively necessary - for example, where the contract provides that the price is determined by the audit result or the government fiscal review conclusion, and that result or conclusion is not issued within a reasonable period for reasons not attributable to the contractor, or manifestly contradicts the contract, the court shall permit the assessment (Fa Shi [2026] No. 12 Article 13(1)); conversely, where the parties have not agreed to settle by the audit or review conclusion, the employer's request to determine the price by that conclusion is not supported (same Article (3)).

3. Jurisdiction and forum: litigation - SPC Interpretation Article 28(2): 'Disputes over rural land contracting, housing lease, construction contracts and policy housing sales are governed by the jurisdiction rules for real-property disputes'; 'for registered real property, the location recorded in the register is the location of the property; for unregistered real property, the actual location is the location.' The court at the location of the works thus usually has jurisdiction, and it is exclusive - agreement cannot displace it. Arbitration - apply to the agreed arbitral institution, which decides whether assessment is needed and appoints the expert.

4. How the expert (institution) is determined: first, the two parties agree on a qualified institution (cost consultancy qualification / professional qualification of personnel); failing agreement, the court or the tribunal appoints. A consultancy engaged unilaterally, without qualification for assessment or without cross-examination by the other party, cannot act directly as the expert.

5. Bearing and payment route of the assessment fee: Measures for Payment of Litigation Fees (State Council Decree No. 481) Article 12: 'Fees arising during litigation from assessment, public notice, site inspection, translation, valuation, auction, sale, storage, custody, transport, ship custody and the like, which are to be borne by the parties under law, are decided by the people's court under the principle of whoever asserts bears: the party pays the relevant institution or unit directly, and the people's court may not collect or disburse on its behalf.' The applicant thus advances the fee by the size of the disputed amount, pays the institution directly, and the court does not handle the funds; the final bearing is fixed by the court in light of the outcome. In arbitration, the fee is advanced in the amount and proportions fixed by the arbitral rules or the tribunal; failure to advance may mean the assessment does not proceed.

6. The expert's appearance and the consequences of refusal: Civil Procedure Law Article 81: 'Where a party objects to an assessment opinion or the people's court deems it necessary for the expert to appear, the expert shall appear and testify. Where the expert, after notification by the people's court, refuses to appear, the assessment opinion may not serve as the basis for finding facts, and the party that paid the assessment fee may demand its return.' This is the most direct procedural handle for cross-examining a cost assessment opinion: on objection, apply promptly in writing for the expert's appearance, rather than merely recording non-acceptance in the cross-examination submissions.

7. Assessment time limit: GB/T 51262-2017 'Code for Construction Cost Expert Assessment' Clause 3.7.1: the time limit is fixed by the institution and the commissioning party within the periods of Table 3.7.1 of the Code, taking into account the construction cost value in dispute and the complexity of the project; 'where the institution and the commissioning party have otherwise agreed on the time limit for completing the assessment, that agreement governs.'

Scope of Application

  • This card is about procedure; it does not resolve the substantive disputes of 'whether assessment should be allowed' (whether a settlement agreement exists, the validity of an audit clause, whether the submitted price is deemed accepted) - those belong to the 'settlement subject to government audit' and 'deemed acceptance upon failure to respond in time' topics.
  • In litigation the application must be filed before the evidence period expires; whether a late application is permitted is in the court's discretion, and an application 'unrelated to or meaningless for the facts to be proven' will not be permitted.
  • 'Deemed acceptance of the final account documents upon failure to respond in time' (Fa Shi [2020] No. 25 Article 21) and 'judicial assessment upon audit delay' are mutually exclusive in effect; where both types of clause exist, the claims must be pleaded primary and alternative - they cannot both be obtained.
  • The admissibility rule of Fa Shi [2026] No. 12 Article 13 has a strict time boundary: the Interpretation takes effect from 30 June 2026 and applies to first-instance construction contract cases newly accepted after that date, prevailing over earlier inconsistent interpretations (Article 23); cases accepted earlier at first and second instance follow the old rules.
  • GB/T 51262-2017 is a recommended standard; the time limit is first set by agreement or by the bands of Table 3.7.1 - agreement prevails.
  • In arbitration, the rules on selecting the expert, attending the hearing and taking questions follow the Arbitration Law and the institutional rules, and are not fully identical with the Civil Procedure Law provisions cited here.

Further Reading

Civil Procedure Law (2023 amendment) Articles 79 and 81; SPC Interpretation on the Application of the Civil Procedure Law (Fa Shi [2015] No. 5, 2022 amendment) Articles 28 and 121; Arbitration Law (2025 revision) Articles 56 and 57 (production and cross-examination of evidence at the hearing); Measures for Payment of Litigation Fees (State Council Decree No. 481) Article 12; GB/T 51262-2017 'Code for Construction Cost Expert Assessment' Clause 3.7.1 and Table 3.7.1 (time-limit bands) and Chapter 4 (evidence materials submitted); Fa Shi [2026] No. 12 Article 13 (audit/review conclusions and admissibility) and Article 23 (effective date and boundary); Fa Shi [2020] No. 25 Article 21 (deemed acceptance upon failure to respond) and Article 27 (interest start date). For the substantive judgment whether assessment can be sought upon audit delay, see the 'settlement subject to government audit' topic card; for the temporal effect of Interpretation (II), see the impact-map card cited there.

Keywords

  • 工程造价司法鉴定
  • 造价鉴定申请
  • 举证期限届满前
  • 鉴定人协商指定
  • 鉴定人出庭
  • 鉴定费负担
  • 建设工程施工合同纠纷管辖
  • GB/T 51262-2017 鉴定期限

Cited By