Application requirements and admissibility review for judicial construction cost expert assessment: the party bearing the burden of proof applies within the specified period and prepays the fee; the matter must be a specialised issue for ascertaining facts; only disputed facts are assessed; the 9 categories of matters for which assessment is not commissioned; cross-examination review of assessment materials and assessment opinions; and special admissibility where pricing is agreed by audit or government fiscal review conclusions
Construction cost expert assessment may be applied for, but the following must be satisfied together: within litigation / arbitration, the party bearing the burden of proof for the facts to be assessed applies in writing before the evidence production period expires or within the period specified by the court and prepays the assessment fee (failure to apply in time, failure to prepay, or refusal to provide materials resulting in the facts being unascertainable leads to the consequence of failure of proof - Fa Shi [2020] No. 25, Article 32; Fa Shi [2019] No. 19, Article 31); the matter is a 'specialised issue for ascertaining facts' and is connected to and meaningful for the facts to be proved (Civil Procedure Law Article 79; Fa Shi [2015] No. 5 Article 121); only disputed facts are assessed (Fa Shi [2020] No. 25, Article 31); the case does not fall into the 9 categories of non-commission under Article 1 of Fa [2020] No. 202 (including determinations on allocation of liability, issues of application of law, lie detection, etc.); the assessment materials must be cross-examined in court (Fa Shi [2019] No. 19, Article 34).
Applicable Codes
- 《中华人民共和国民事诉讼法》(2023修正)第七十九条、第八十一条
- 《最高人民法院关于适用〈中华人民共和国民事诉讼法〉的解释》(法释〔2015〕5号,2022修正)第一百二十一条
- 《最高人民法院关于民事诉讼证据的若干规定》(法释〔2019〕19号,2019修正)第三十条至第三十九条
- 《最高人民法院关于人民法院民事诉讼中委托鉴定审查工作若干问题的规定》(法〔2020〕202号)第1—5条
- 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》(法释〔2020〕25号)第三十一条、第三十二条、第三十三条、第三十四条
- 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》(法释〔2026〕12号,自2026年6月30日起施行)第十三条、第二十三条
- 《中华人民共和国仲裁法》(2025修订)第五十六条
- 《诉讼费用交纳办法》(国务院令第481号)第十二条
- 《建设工程造价鉴定规范》GB/T 51262-2017 第3.3.1条、第3.3.5条
Topic positioning
This card answers 'under what conditions construction cost expert assessment may be applied for': the substantive thresholds, procedural requirements and negative exclusions for starting a construction cost expert assessment in litigation / arbitration, and the cross-examination review requirements for assessment materials and assessment opinions, organised as an item-by-item checklist. How the procedure advances (court of jurisdiction, how the assessors are agreed or designated, who pays the assessment fee directly, consequences of the assessor not appearing in court, assessment time limits) - see the knowledge cards on the commencement procedure and procedural rules cited by this card.
Core conclusions
Bottom line: an application may be made, but assessment cannot be started at will. Construction cost expert assessment is a means of evidence within litigation (arbitration); the following six requirements must be satisfied together, and the case must not fall into the nine categories of non-commission:
I. Requirements checklist (requirement x legal basis x proof / practice points)
| # | Requirement | Legal basis | Proof / practice points |
|---|---|---|---|
| 1 | Setting: raised within litigation or arbitration proceedings; no unilateral start before filing | Civil Procedure Law (2023 revision) Article 79; Arbitration Law (2025 revision) Article 56 | Submit the written application after filing / acceptance; in arbitration apply to the arbitral tribunal, which decides on the commission |
| 2 | Party: applied for by the side bearing the burden of proof for the facts to be assessed; where the court deems assessment necessary it should clarify this to that side | Fa Shi [2020] No. 25 Article 32(1); Fa Shi [2019] No. 19 Article 30 | The application states the claimed cost amount, the disputed difference, the pricing basis (contract pricing method / quota norms / BOQ) and the list of evidence |
| 3 | Time limit: raised before the evidence production period expires or within the court-specified period, with the assessment fee prepaid | Fa Shi [2015] No. 5 Article 121(1); Fa Shi [2019] No. 19 Article 31(1) | Submit in writing immediately on receipt of the clarification / evidence notice (keep proof via EMS or system receipt); do not apply orally |
| 4 | Fee: the assessment fee is prepaid on application; failure to prepay is deemed waiver; the fee follows 'whoever claims bears it', ordered by the court to be paid by the party directly to the assessment institution; the court may not collect or pay it on the party's behalf | Fa Shi [2019] No. 19 Article 31(1); Measures on Payment of Litigation Fees (State Council Order No. 481) Article 12 | Reserve the funds and obtain an official receipt; the final bearing of the assessment fee is determined by the court in light of the outcome of the judgment |
| 5 | Object: a 'specialised issue for ascertaining facts', connected to and meaningful for the facts to be proved | Civil Procedure Law (2023 revision) Article 79; Fa Shi [2015] No. 5 Article 121(1) | Phrase the matter as 'the cost of the works of unit X is how much' or 'the payable price of variation X or claim X is how much'; do not phrase 'who breached' or 'whether payment is owing' |
| 6 | Materials: assessment materials must be cross-examined in court | Fa Shi [2019] No. 19 Article 34(1); Fa [2020] No. 202 Articles 4 and 5 | Disputed materials are first determined by the court and may not be handed directly to the assessment institution for selection; supplement with cross-examined additional materials |
II. Negative requirements: nine categories of non-commission. Article 1 of Fa [2020] No. 202: 'Strictly review whether the proposed matter for assessment is a specialised issue for ascertaining the facts of the case; under any of the following circumstances the people's court shall not commission an assessment: (1) facts that can be presumed from common knowledge of life or empirical rules; (2) issues unrelated to the facts to be proved; (3) issues meaningless for proving the facts to be proved; (4) non-specialised issues that should be proven by the parties; (5) facts that can be ascertained through court investigation, inspection and other methods; (6) determinations on the allocation of liability between the parties; (7) issues of application of law; (8) lie detection; (9) other circumstances unsuitable for commissioning an assessment.' Article 2 of the same provisions: 'Where the assessment techniques and methods involved in the proposed matter are seriously disputed, their scientific reliability should first be reviewed. If the assessment techniques and methods involved lack scientific reliability, no assessment shall be commissioned.'
III. Scope requirement: only disputed facts are assessed. Fa Shi [2020] No. 25 Article 31: 'Where the parties dispute part of the facts of the case, only the disputed facts are assessed, except where the scope of disputed facts cannot be determined, or both parties request assessment of all the facts.' In practice, first fix the undisputed part (signed-off settlement, signed-off quantities and rates) and narrow the application to the disputed items, which reduces the assessment fee and the cycle.
IV. Consequences of late application (failure of proof). Fa Shi [2019] No. 19 Article 31: 'A party applying for assessment shall apply within the period specified by the people's court and prepay the assessment fee. Failure to apply within the time limit or failure to prepay the assessment fee is deemed waiver of the application. Where the party bearing the burden of proof for the facts to be proved, without justified reason, fails to apply for assessment within the court-specified period or fails to prepay the assessment fee, or refuses to provide relevant materials, so that the facts to be proved cannot be ascertained, it shall bear the legal consequence of failure of proof.' Fa Shi [2020] No. 25 Article 32(1) restates this for the construction field: 'Where the parties dispute specialised issues such as the cost of the works, the quality or the repair costs, and the people's court deems assessment necessary, it should clarify this to the party bearing the burden of proof. A party that, after clarification, does not apply for assessment, or applies but does not pay the assessment fee or refuses to provide relevant materials, shall bear the legal consequence of failure of proof.' Paragraph 2: 'Where the party bearing the burden of proof did not apply for assessment in first instance, or applied but did not pay the assessment fee or refused to provide relevant materials, and applies for assessment in second instance, and the people's court deems it truly necessary, it shall handle the matter per Article 170(1)(iii) of the Civil Procedure Law' (i.e. second-instance handling of a judgment based on unclear basic facts: remand for retrial, or amendment after the facts are ascertained).
V. Cross-examination review of assessment materials. Fa Shi [2019] No. 19 Article 34: 'The people's court shall organise the parties to cross-examine the assessment materials. Materials not cross-examined may not serve as the basis of the assessment. With the permission of the people's court, the assessor may access evidence, inspect material evidence and the site, and question parties or witnesses.' Fa [2020] No. 202 Article 3 requires the court to inform the parties of the legal consequences of not providing assessment materials that meet the requirements; Article 4: 'Materials (including supplementary materials) not cross-examined in court may not serve as assessment materials. Where a party cannot be contacted, is served by public notice or waives cross-examination, the assessment materials shall be confirmed by the collegial panel.' Article 5: 'For materials disputed between the parties, the people's court shall determine them and may not hand them directly to the assessment institution or the assessor for selection.' Fa Shi [2020] No. 25 Article 33: 'After permitting a party's application for assessment, the people's court shall, according to the application and the needs of ascertaining the facts of the case, determine the matters, scope and time limit of the commissioned assessment, and organise the parties to cross-examine the disputed assessment materials.' Article 34: 'The people's court shall organise the parties to cross-examine the assessment opinion. Where the assessor has used materials disputed by the parties and not cross-examined as the basis of assessment, the people's court shall organise the parties to cross-examine those materials. If on cross-examination they are found unfit to serve as the basis of assessment, the assessment opinion made on the basis of those materials may not serve as the basis for ascertaining the facts of the case.'
VI. Acceptance thresholds on the institution side. GB/T 51262-2017 clause 3.3.1: the assessment institution shall decide within 7 working days of receiving the commission letter whether to accept the commission and reply in writing to the commissioning party; the reply should include the expression of willingness to accept the commission, the evidence materials needed for the assessment, the person in charge of the assessment work and contact details, and the assessment fee and how it is collected. Clause 3.3.5 lists the circumstances in which the commission should not be accepted: the commissioned matter exceeds the institution's business scope; the assessment requirements do not conform to the practice rules of the industry or the relevant technical standards; the commissioned matter exceeds the institution's professional capability and technical conditions; other circumstances not conforming to laws and regulations - where the commission is not accepted, the institution should notify the commissioning party within the period of clause 3.3.1, state the reasons and return the assessment materials.
VII. Objections to the assessment opinion and the assessor appearing in court. Fa Shi [2019] No. 19 Article 36 lists the seven items of the assessment report to be reviewed (name of the commissioning court, content and requirements of the commission, assessment materials, principles and methods relied on, explanation of the assessment process, the assessment opinion, and the letter of commitment), and requires the assessors to sign or seal and attach proof of qualification; Article 37 requires the court, on receiving the assessment report, to promptly send copies to the parties, who should raise objections in writing within the specified period, and the court should require the assessors to explain, clarify or supplement; Article 38: where a party still objects after receiving the written reply, the court notifies the objecting party to prepay the assessor's court appearance fee and notifies the assessor to appear in court; failure to prepay is deemed waiver of the objection, and where both parties object the prepayment is shared; Article 39: the assessor's appearance fee is calculated at the standard for witnesses appearing in court and borne by the losing party; where the appearance is needed because the assessment opinion is unclear or defective, the appearance fee is borne by the assessor. The consequence of refusing to appear follows Civil Procedure Law (2023 revision) Article 81: where the assessor, after being notified by the court, refuses to appear in court to give the opinion, the assessment opinion may not serve as the basis for finding facts, and the party that paid the assessment fee may demand its refund.
VIII. Special admissibility where pricing is agreed by audit results or government fiscal review conclusions. Fa Shi [2026] No. 12 Article 13(1): 'Where the employer and the contractor agree that the price of the works is determined by the audit result of the audit authority or the review conclusion of the government fiscal review institution, but the audit result or review conclusion is not issued within a reasonable period for reasons not attributable to the contractor, or the contractor has evidence that the audit result or review conclusion obviously contradicts the construction contract, and the contractor applies for judicial assessment of the construction cost, the people's court shall permit it.' Paragraph 2: the reasonable period follows any agreement; absent agreement it is determined by the court in light of the scale of the works, the cost amount and the complexity, but may not exceed one year from the date the contractor submits the final account documents. Paragraph 3: where there is no agreement to determine the price by audit result or review conclusion, a request by the employer to determine the price of the works by such conclusion is not supported. This article only gives the contractor a 'right of access to assessment'; the price is still verified by the assessment on the basis of the pricing standard and method agreed in the contract.
Scope of application
- This card addresses 'whether an application can be made and whether the requirements are met', not the substantive pricing question of 'how much of the assessment conclusion should be adopted'; pricing rules are covered by the topic cards on quantities, site instruction records, valuation of variations, settlement basis, etc.
- A review opinion issued before filing by a cost consultancy unilaterally commissioned is not judicial assessment but private documentary evidence submitted by a party; where the other side has sufficient evidence or grounds to rebut it and applies for assessment, the court should permit the application, and the report is superseded by the judicial assessment.
- Determinations on allocation of liability, issues of application of law, and lie detection are not objects of assessment: the same dispute must be split into 'factual issues (quantities, rates, on-costs)' and 'legal issues (validity of the contract, breach and liability)', applying for assessment only on the former.
- Time marker: Article 13 of Fa Shi [2026] No. 12 is provided in the Construction Contract Interpretation (II), effective from 30 June 2026; that interpretation applies to first-instance construction contract dispute cases newly accepted after its implementation and prevails over earlier judicial interpretations in case of inconsistency (Article 23); first- and second-instance cases accepted before implementation are handled under the original rules.
- In arbitration proceedings the assessment is applied for to the arbitral tribunal; the assessor is agreed by the parties or designated by the tribunal; the assessor's appearance is notified by the tribunal; the Civil Procedure Law provisions on court-commissioned assessment do not apply directly.
- GB/T 51262-2017 is a recommended standard; the 7-working-day reply and the non-acceptance circumstances are the institution's duty of reply to the commissioning party, not statutory requirements for a party's application; assessment time limits follow any agreement.
- Whether a late application is permitted lies in the court's discretion; matters 'unrelated to or meaningless for the facts to be proved' are still not permitted; the main risk of not applying in time is losing the case through failure of proof, not inevitable rejection after cure.
Further reading
Civil Procedure Law of the PRC (2023 revision) Articles 79 and 81; Interpretation of the Supreme People's Court on the Application of the Civil Procedure Law of the PRC (Fa Shi [2015] No. 5, 2022 revision) Article 121; Provisions of the Supreme People's Court on Several Issues Concerning Evidence in Civil Procedure (Fa Shi [2019] No. 19, 2019 revision) Articles 30 to 39 (clarification and specified period, prepayment and waiver, content of the commission letter, letter of commitment, cross-examination of assessment materials, review of the assessment report, objection replies and appearance fees); Provisions of the Supreme People's Court on Several Issues Concerning the Review of Commissioned Assessment in Civil Procedure (Fa [2020] No. 202) Articles 1 to 5; Interpretation of the Supreme People's Court on the Application of Law in the Trial of Construction Contract Dispute Cases (I) (Fa Shi [2020] No. 25) Articles 31 to 34; Interpretation (II) (Fa Shi [2026] No. 12, effective 30 June 2026) Articles 13 and 23; Arbitration Law of the PRC (2025 revision) Article 56; Measures on Payment of Litigation Fees (State Council Order No. 481) Article 12; GB/T 51262-2017 Code for Construction Cost Expert Assessment clauses 3.3.1 and 3.3.5.
Keywords
- 工程造价鉴定
- 申请鉴定要件
- 不予委托鉴定
- 专门性问题
- 鉴定材料质证
- 举证不能
- 鉴定意见异议
- 建工解释一第三十二条