Binding force and admissibility in construction cost expert assessment of three kinds of documents: cost consultancy opinions jointly commissioned by both parties, facts admitted as compromises for mediation or settlement during litigation, and cost opinions unilaterally commissioned by one party (Fa Shi [2020] No. 25 Article 30; SPC Interpretation on the Civil Procedure Law Article 107; GB/T 51262-2017 Articles 5.11.5-5.11.6; SPC Evidence Provisions Article 41)
The three kinds of documents differ in effect. (1) An opinion issued by a cost consultancy institution jointly commissioned by both parties is in principle not binding under Article 30 of the SPC Interpretation (I) on Construction Contract Disputes (Fa Shi [2020] No. 25): where one party does not accept it in litigation and applies for construction cost expert assessment, the people's court shall permit the application, except where both parties have expressly stated that they accept being bound by that opinion. (2) Facts that a party admitted as a compromise in order to reach a mediation or settlement agreement during litigation may not, under Article 107 of the SPC Interpretation on the Civil Procedure Law, be used in subsequent litigation as grounds adverse to that party; a written compromise-based opinion reached during the assessment shall be incorporated into the definitive opinion but must be noted as such (GB/T 51262-2017 Article 5.11.5), and on re-assessment it may not be used directly as the basis of the assessment unless the parties again unanimously agree (Article 5.11.6). (3) For an opinion issued on one party's unilateral commission, where the other party has evidence or reasons sufficient to rebut it and applies for assessment, the application shall be permitted (SPC Evidence Provisions Article 41).
Applicable Codes
- 法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第三十条
- 法释〔2020〕25号 第二十九条
- 法释〔2015〕5号《民诉法解释》(2022修正)第一百零七条
- GB/T 51262-2017 · Code for Construction Cost Appraisal 第5.11.5条
- GB/T 51262-2017 · Code for Construction Cost Appraisal 第5.11.6条
- 法释〔2019〕19号《最高人民法院关于民事诉讼证据的若干规定》(2019修正)第四十一条
Scope
This card distinguishes the evidentiary force and the admissibility for expert assessment in litigation of three kinds of cost documents that look like settlement bases but are not settlement agreements: cost consultancy opinions issued by an institution jointly commissioned by both parties (Fa Shi [2020] No. 25 Article 30); facts admitted as compromises for mediation or settlement during litigation (SPC Interpretation on the Civil Procedure Law Article 107; GB/T 51262-2017 Articles 5.11.5 and 5.11.6); and opinions issued on one party's unilateral commission (SPC Evidence Provisions Article 41).
Key conclusions
1. A jointly commissioned consultancy opinion does not bind the parties by default; assessment is available.
Article 30 of Fa Shi [2020] No. 25 reads: 'Where the parties jointly commissioned an institution or professionals before litigation to issue a consultancy opinion on the construction cost of the project, and in litigation one party does not accept that opinion and applies for expert assessment, the people's court shall permit the application, except where both parties have expressly stated that they accept being bound by that consultancy opinion.'
That is: (1) joint commission plus an issued opinion, without an express statement of being bound, means one party's non-acceptance suffices to apply for assessment, and the court shall permit it; (2) where both parties expressly stated that they are bound by the opinion, the opinion becomes a price fixed by mutual consent, and only then is Article 29 applied (assessment not permitted); (3) the mere act of joint commission does not amount to an express statement of being bound.
2. Facts admitted as compromises for mediation or settlement during litigation may not be used against the admitting party.
Article 107 of the SPC Interpretation on the Application of the Civil Procedure Law (Fa Shi [2015] No. 5, 2022 revision) reads: 'In litigation, facts that a party admitted as a compromise in order to reach a mediation agreement or a settlement agreement may not be used in subsequent litigation as grounds adverse to that party, except as otherwise provided by law or where all parties agree.'
GB/T 51262-2017, the code for construction cost expert assessment, makes two supporting provisions:
- Article 5.11.5: where during the assessment the parties, through mutual consultation, reach a written compromise-based agreement on the assessed project or on part of its content, that agreement shall be incorporated into the definitive opinion, but this shall be noted in the assessment opinion.
- Article 5.11.6: on re-assessment, a written compromise-based agreement reached by the parties may not be used directly as the basis of the assessment unless the parties again unanimously agree; the article also cites Article 107 of Fa Shi [2015] No. 5 as its basis.
So a compromise-based opinion is usable in the current assessment (with a note), but once re-assessment begins it may be used directly only if the parties again unanimously agree.
3. A cost opinion issued on one party's unilateral commission can be rebutted; where the other party rebuts it effectively and applies for assessment, the application shall be permitted.
Article 41 of the SPC Provisions on Evidence in Civil Procedures (Fa Shi [2019] No. 19): 'Where one party has, on a specialized issue, unilaterally commissioned an institution or professionals to issue an opinion, and the other party has evidence or reasons sufficient to rebut it and applies for expert assessment, the people's court shall permit the application.'
That is, a unilaterally commissioned review report or settlement statement can neither serve directly as the basis of the decision nor produce the effect that a settlement agreement has been reached; a bare objection by the other party, without evidence or with insufficient reasons, is not enough to open the door to assessment.
4. How the three are characterised side by side.
- Settlement agreement, or expressly bound by the consultancy opinion -> price fixed by mutual consent; an application for construction cost expert assessment in litigation is not permitted (Article 29).
- Jointly commissioned consultancy opinion without a statement of being bound -> not binding; an assessment applied for by a non-accepting party shall be permitted (Article 30).
- Facts admitted as compromises for mediation or settlement during litigation -> may not be used as adverse grounds (Article 107); written compromise-based opinions formed in the assessment are usable with a note, and on re-assessment require renewed unanimous consent (Articles 5.11.5 and 5.11.6).
- Opinion on one party's unilateral commission -> can be rebutted and trigger assessment (SPC Evidence Provisions Article 41).
Application boundaries
- Article 30 addresses joint commission before litigation, and the key is whether there was an expression of intent expressly accepting to be bound by that consultancy opinion; whether an oral statement or a later ratification constitutes such an expression must be established by provable evidence, and a commission contract or payment vouchers alone do not prove being bound.
- Article 107 protects only facts admitted as compromises in order to reach a mediation agreement or a settlement agreement; statements, admissions and confirmations in correspondence that are not of a compromise nature are outside it, except as otherwise provided by law or where all parties agree.
- Under GB/T 51262-2017 Article 5.11.5, incorporation into the definitive opinion does not give the agreement final effect; its compromise origin must still be noted in the assessment opinion; Article 5.11.6 restricts direct use in the re-assessment scenario.
- A unilaterally commissioned opinion may still be admitted as evidence where the other party has not rebutted it effectively, so it is not invalid in all cases.
- Where the result of a jointly commissioned cost review has been absorbed into a later settlement agreement, the settlement agreement prevails.
Further reading
- Fa Shi [2020] No. 25, Interpretation (I) on Construction Contract Disputes: Article 30 (jointly commissioned opinions and admissibility of assessment); Article 29 (no assessment after a settlement agreement).
- Fa Shi [2015] No. 5, SPC Interpretation on the Civil Procedure Law (2022 revision): Article 107.
- GB/T 51262-2017 code for construction cost expert assessment: Articles 5.11.5 and 5.11.6.
- Fa Shi [2019] No. 19, SPC Provisions on Evidence in Civil Procedures (2019 revision): Article 40 (statutory grounds for re-assessment); Article 41 (rebuttal of unilaterally commissioned opinions and assessment).
Keywords
- 共同委托咨询意见
- 造价咨询意见
- 法释〔2020〕25号第三十条
- 妥协性意见
- 调解和解
- 民诉法解释第一百零七条
- 单方委托造价意见
- 重新鉴定