How the eighteen-month exercise period of the construction price priority right runs when the construction payment is paid by instalments: per-instalment accrual and separate accrual for retention money; the presumption where the payment time is not agreed; accrual where the date is varied by agreement or fixed in a settlement agreement (with the old/new boundary of Articles 21 and 23 of the 2026 Interpretation (II))
The eighteen months (Fa Shi [2020] No. 25, Article 41) is a preclusive period; the limitation rule of Civil Code Article 189 that 'for a debt performed by instalments the limitation period runs from expiry of the last instalment' does not apply. Instalment payment does not change the length of the eighteen months; it merely creates several 'dates on which payment falls due' - for each instalment the period starts on the day that instalment's payment conditions are satisfied, running and expiring instalment by instalment; the priority right for instalments whose period has expired is extinguished. Retention money accrues separately from the expiry of its return period (no agreement = two years after the works passed completion acceptance; failure to carry out acceptance due to the employer = 90 days after submission of the completion acceptance report), and may not serve as the starting point for the whole construction price.
Applicable Codes
- 《中华人民共和国民法典》第八百零七条
- 《中华人民共和国民法典》第一百八十九条
- 法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第十七条、第二十七条、第三十九条、第四十条、第四十一条
- 法释〔2026〕12号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》第十七条、第二十一条、第二十三条
- 《保障中小企业款项支付条例》(国务院令第802号,2025修订)第九条、第十条、第十七条
- 江苏省高级人民法院《建设工程施工合同纠纷案件若干问题的解答》(苏高法〔2018〕)第14~20条
- https://www.court.gov.cn/fabu/xiangqing/34302.html
- http://gongbao.court.gov.cn
Positioning of the topic
How the eighteen-month exercise period of the construction price priority right runs when the payment is by instalments (progress payments by milestone, N instalments after the total is confirmed at settlement, retention held back as the tail): per-instalment or whole-of-price accrual; how retention money accrues; the presumption where the payment time is not agreed; the effect of varying the date by agreement or fixing it in a settlement agreement; and the essential difference between this period and limitation periods.
Core conclusions
Length and nature of the period. Fa Shi [2020] No. 25, Article 41, reads: 'The contractor shall exercise the construction price priority right within a reasonable period, but in no case later than eighteen months, reckoned from the date on which the employer ought to pay the construction price.' The eighteen months is a preclusive period (an unalterable period): suspension, interruption, and extension of limitation periods do not apply; if the right is not exercised within the period, it is extinguished (the construction price claim itself is not extinguished, but drops out of the priority ranking and is paid as an ordinary claim).
Instalment payment creates several 'dates on which payment falls due'. The article anchors on 'the date on which the employer ought to pay the construction price'; instalment payment makes the day each instalment's payment conditions are satisfied that instalment's due date, and the eighteen months run and expire instalment by instalment: instalments whose period has expired are no longer under priority protection, while later instalments not yet due remain within the period. Pleading 'the whole has not been settled' or 'the last instalment is not yet due' against an expired instalment does not extend the preclusive period.
The instalment rule of limitation periods must not be transplanted. Civil Code Article 189 reads: 'Where the parties agree that the same debt is to be performed by instalments, the limitation period runs from expiry of the performance period of the last instalment.' That article governs only limitation periods (interruptible, suspendable, extendable), not the preclusive period of the priority right; pushing the starting point to the last instalment is the classic path to losing the right. When checking the period, take 'the earliest instalment that has fallen due' as the worst-case measure.
Retention money accrues separately. Fa Shi [2020] No. 25, Article 17, reads: 'Under any of the following circumstances, the people's court shall support the contractor's claim for the employer to return the works quality retention money: (1) the return period for the works quality retention money agreed by the parties has expired; (2) where the parties have not agreed a return period for the works quality retention money, two years have elapsed since the works passed completion acceptance; (3) where the works did not undergo completion acceptance within the agreed period for reasons attributable to the employer, the agreed return period for the works quality retention money expires 90 days after the contractor submits the completion acceptance report; where the parties have not agreed a return period, two years elapse 90 days after the contractor submits the completion acceptance report. The employer's return of the works quality retention money does not affect the contractor's performance of the works warranty obligations under the contract or the law.' The retention money is functionally separate from progress payments and settlement payments; its eighteen months run from expiry of the above return period. In judicial practice the retention return date should not be taken as the starting point for the priority right over the whole construction price, nor does retention not yet due extend the period for the settlement payment part.
The presumption where the payment time is not agreed or is unclear. Fa Shi [2020] No. 25, Article 27, reads: 'Interest accrues from the date the construction price is payable. Where the parties have not agreed the payment time or the agreement is unclear, the following dates are deemed the date the price is payable: (1) where the works have been actually delivered, the date of delivery; (2) where the works have not been delivered, the date of submitting the final account documents for the works; (3) where the works are undelivered and the price unsettled, the date the party brings suit.' Although placed among the interest provisions, the 'deemed payable date' equally grounds the 'date on which payment falls due' under Article 41; under instalment payment, the corresponding dates above are checked instalment by instalment.
Payment dates varied by agreement for objective reasons, or fixed in a settlement agreement. Fa Shi [2026] No. 12, Article 21, reads: 'Where the construction contract fixes the date on which the employer ought to pay the construction price, and the parties vary the payment date by agreement for objective reasons such as an extension of the time for completion, and the contractor claims that the exercise period of the construction price priority right runs from the varied date on which the employer ought to pay, the people's court shall support it. Where the construction contract does not fix, or unclearly fixes, the date on which the employer ought to pay, but the parties expressly fix such a date in a settlement agreement, and the contractor claims that the exercise period of the construction price priority right runs from that date, the people's court shall support it.' That is, even where the original payment date has passed, if the date was varied by agreement for objective reasons such as an extension of time, or a payment date was expressly fixed afterwards in a settlement agreement, the period runs from the varied or agreed date and the original date no longer counts; the variation agreement, the settlement agreement, and the correspondence are the core evidence for a starting-point defence.
Termination or cessation of performance. After termination the original instalment milestones lose their meaning; judicial practice takes the date of termination of the contract (or cessation of performance) as the payable date from which the eighteen months run (the approach of SPC Guiding Case No. 73; see the release page on the SPC official website).
Layering the priority scope by instalment. Article 40 reads: 'The scope of the contractor's construction price priority right is determined in accordance with the provisions of the relevant administrative department of the State Council on the scope of construction prices. Where the contractor claims priority for interest on overdue payment of the construction price, liquidated damages, or damages, the people's court shall not support it.' Interest, liquidated damages, and damages on overdue instalments do not enter the priority scope; Fa Shi [2026] No. 12, Article 17 further provides: 'Where the contractor requests confirmation that it enjoys the construction price priority right, the people's court shall ascertain the amount of the construction price enjoying the priority right and the corresponding works, and state them in the operative part of the judgment. Where the contractor claims the construction price priority right for losses from suspension or idle resources caused by the employer, the people's court shall not support it.'
Uncompleted works. Article 39 reads: 'Where an uncompleted construction work is of acceptable quality and the contractor claims priority of payment out of the proceeds of the discount or auction of the part of the works it constructed, the people's court shall support it.' Where work stops mid-way under instalment payment, the period for the completed part can be checked and claimed under the above rules, still on condition that the quality is acceptable.
The statutory cap on payment periods as a fallback benchmark (SMEs). Regulation on Ensuring Payment to SMEs (State Council Decree No. 802, 2025 revision), Article 9: a state organ or public institution procuring goods, works, or services from small and medium-sized enterprises with fiscal funds shall pay within 30 days of delivery; where the contract provides otherwise, the payment period may not exceed 60 days at most; a large enterprise shall pay within 60 days of delivery, and may not agree to condition payment on receipt of payment by a third party or to pay in proportion to the progress of third-party payment. Article 10: where payment is conditioned on passing inspection or acceptance, the payment period runs from the date of passing the inspection or acceptance; where the inspection or acceptance is delayed, it runs from expiry of the agreed inspection or acceptance period. Where the contract is silent or sets an obviously excessive period, this mandatory cap may serve as a benchmark for defining the 'date on which payment falls due'.
Scope of application
- Applies to the contractor's construction price priority right against the employer under a construction contract (the basis of the claim is Civil Code Article 807: notice -> continued non-payment upon expiry -> discount by agreement or request to the court for auction according to law -> priority of payment out of the discounted or auctioned proceeds). It does not apply to computing the limitation period of ordinary claims, nor to the exercise period of a mortgage (which follows the limitation period of the principal claim).
- Eighteen months is the maximum period, running in parallel with the 'reasonable period'; once exceeded, the right is extinguished. The 'six-month' rule in local guidance (e.g. Jiangsu Higher People's Court, Answers to Several Questions on Construction Contract Dispute Cases, Su Gao Fa [2018], Article 14) was the pre-Fa Shi [2020] No. 25 position and has been superseded by the eighteen months - it must no longer be cited as the current period length; but the accrual scenarios it lists, and views such as 'interest on the construction price is outside the priority scope', 'invalidity of the construction contract does not defeat the priority right', and 'assertion by letter is not recognised as effective exercise' (Articles 17, 15, 18), remain of reference value.
- The 30 June 2026 boundary: Fa Shi [2026] No. 12, Article 23, reads: 'This Interpretation takes effect on 30 June 2026. For first-instance construction contract cases newly accepted by the people's courts after this Interpretation takes effect, this Interpretation applies. Where SPC interpretations issued earlier conflict with this Interpretation, this Interpretation prevails.' Hence the accrual rules for varied payment dates and settlement-agreed payment dates apply only to first-instance cases newly accepted after 30 June 2026; cases accepted earlier still fix the payable date under Article 41 together with Article 27.
- Each instalment's 'date on which payment falls due' must be checked instalment by instalment against delivery, acceptance, and settlement confirmation, and findings may differ case by case; this card maps the rules and does not replace case-specific review.
Further reading
- Civil Code Article 807 (the basis and procedure of the priority right), Article 189 (limitation start for instalment debts, for contrast only).
- Fa Shi [2020] No. 25, SPC Interpretation (I) on Construction Contract Disputes, Article 17 (retention return period), Article 27 (presumed payable date), Article 39 (uncompleted works), Article 40 (priority scope), Article 41 (eighteen months and accrual).
- Fa Shi [2026] No. 12, SPC Interpretation (II) on Construction Contract Disputes, Article 17 (stating the priority amount in the judgment; suspension and idle losses not prioritised), Article 21 (accrual from the varied or settlement-agreed payment date), Article 23 (entry into force and transition).
- Regulation on Ensuring Payment to SMEs (State Council Decree No. 802, 2025 revision), Articles 9, 10, and 17 (payment-period caps and overdue interest).
- Jiangsu Higher People's Court, Answers to Several Questions on Construction Contract Dispute Cases (Su Gao Fa [2018]), Articles 14 to 20 (historical reference: the six-month period; availability despite an invalid contract; claims by the actual constructor; interest not prioritised; a letter does not constitute effective exercise; the effect of waiver; transfer together with the claim).
- SPC Guiding Case No. 73 (accrual of the priority right after termination of contract) release page: https://www.court.gov.cn/fabu/xiangqing/34302.html ; SPC Gazette case search portal: http://gongbao.court.gov.cn .
Keywords
- 建设工程价款优先受偿权
- 十八个月
- 除斥期间
- 分期支付
- 应当给付之日
- 质量保证金起算
- 法释〔2020〕25号第四十一条
- 法释〔2026〕12号第二十一条