Payment time limits under the 2025 revision of the Regulation on Ensuring Payment to Small and Medium-sized Enterprises: 30 days (60 days at most) for state organs and public institutions, 60 days for large enterprises, when the period starts (acceptance and settlement), the ban on back-to-back clauses, the four permitted securities, and interest on overdue payment (1-year LPR floor / 0.05% per day)

Under the Regulation on Ensuring Payment to Small and Medium-sized Enterprises (2025 revision, State Council Decree No. 802): where state organs and public institutions procure works and the like from small and medium-sized enterprises, payment must be made within 30 days from delivery, and any contractual agreement may not extend the limit beyond 60 days; large enterprises must pay within 60 days and may agree periods reasonably per industry norms, but may not make payment conditional on receipt of third-party payment; where payment is by progress or periodic settlement, the payment period runs from the date the parties confirm the settled amount, and where acceptance is a payment condition, from the date of passing acceptance - or, where acceptance is delayed, from the expiry of the agreed acceptance period. Late payment attracts interest on overdue payment: an agreed rate may not be lower than the 1-year LPR at the time of contracting; absent agreement, 0.05% per day.

Applicable Codes

  • 《保障中小企业款项支付条例》(2025修订,国务院令第802号)第八条、第九条、第十条、第十一条、第十二条、第十三条、第十四条、第十五条、第十七条、第十八条
  • 《保障中小企业款项支付条例》(2020年版,国务院令第728号)
  • 《中华人民共和国民法典》第五百一十一条(履行期限)

Subject Positioning

Payment periods and ancillary restrictions in Chapter II 'Payment Provisions' of the Regulation on Ensuring Payment to Small and Medium-sized Enterprises (2025 revision, State Council Decree No. 802): how long state organs, public institutions and large enterprises may take to pay SMEs for goods, works and services, from which day the period runs, whether non-cash payment and audit-based settlement may be used to delay, which kinds of security may be collected, and how interest on overdue payment is computed. Applies to SMEs in construction and supply chasing payment, and to employers setting payment conditions compliantly.

Core Conclusions

I. Payment period: 30 days for organs and institutions, 60-day maximum; 60 days for large enterprises (Article 9)

Where state organs and public institutions procure goods, works or services from SMEs, payment shall be made within 30 days from delivery of the goods, works or services; where the contract provides otherwise, the contract governs, but the payment period shall not exceed 60 days at most. Where large enterprises procure goods, works or services from SMEs, payment shall be made within 60 days from delivery; where the contract provides otherwise, the contract governs, but the payment period shall be agreed reasonably in line with industry norms and trading practices and paid in time, and it shall not be agreed that receipt of third-party payment is a condition for paying the SME, nor that SMEs are paid in proportion to the progress of third-party payment. Where laws, administrative regulations or other state provisions prescribe otherwise for the payment periods of the first and second paragraphs, those provisions govern. Where the contract adopts settlement by performance progress, periodic settlement or the like, the payment period runs from the date the parties confirm the settled amount.

Key points: the payment period for organs and public institutions has a 60-day ceiling (not breakable by agreement); large enterprises may agree otherwise but must be reasonable, and 'back-to-back' clauses are prohibited (conditioning payment on third-party payment or paying in proportion to it). For progress or periodic settlement, the period runs from the date the parties confirm the settled amount.

II. Where acceptance is the payment condition, the period runs from passing acceptance (Article 10)

Where an organ, public institution or large enterprise agrees with an SME that payment is conditional on the goods, works or services passing inspection or acceptance after delivery, the payment period shall run from the date of passing inspection or acceptance. The parties shall agree in the contract a clear and reasonable inspection or acceptance period and complete inspection or acceptance within it, unless laws, administrative regulations or other state provisions provide otherwise. Where the organ, public institution or large enterprise delays inspection or acceptance, the payment period runs from the expiry of the agreed inspection or acceptance period.

Key points: conditioning payment on acceptance requires also agreeing an acceptance period; if acceptance is delayed, the payment period runs from expiry of the agreed period - sitting on acceptance cannot indefinitely postpone the starting point.

III. No forcing non-cash payment, no disguised extension of the payment period (Article 11)

Where organs, public institutions or large enterprises pay SMEs by non-cash means such as commercial bills or electronic receivables vouchers, this shall be clearly and reasonably agreed in the contract; SMEs shall not be forced to accept commercial bills, electronic receivables vouchers and other non-cash means, nor shall such means be used to disguise an extension of the payment period.

IV. No forcing audit results as the settlement basis (Article 12)

Organs, public institutions and state-owned large enterprises shall not force the audit conclusion of an audit organ to be taken as the settlement basis, except where laws or administrative regulations provide otherwise.

V. Securities limited to four kinds, no cash-only requirement, prompt release on expiry (Article 13)

Apart from the lawfully established tender security, performance security, retention money for works quality and migrant worker wage security, no other security may be collected in any form in project construction. The collection ratios and methods of securities shall comply with laws, administrative regulations and state provisions. Organs, public institutions and large enterprises shall not limit securities to cash. Where an SME provides security by a bond issued by a financial institution or the like, the organ, public institution or large enterprise shall accept it. Organs, public institutions and large enterprises shall, according to law or the contract, promptly reconcile with the SME the securities collected and return them after the security period expires.

VI. No delay citing internal processes, change of legal representative or final-account audit (Article 14); partial disputes do not affect payment of undisputed parts (Article 15)

Organs, public institutions and large enterprises shall not refuse or delay payment to SMEs on the grounds of a change of legal representative or principal person in charge, performance of internal payment procedures, or - absent contractual agreement - awaiting completion acceptance filing or final-account audit. In transactions between organs, public institutions and large enterprises on one side and SMEs on the other, where part is in dispute but the rest can be performed, the undisputed part shall be paid promptly.

VII. Interest on overdue payment (Article 17)

Where an organ, public institution or large enterprise pays an SME late, it shall pay interest on overdue payment. Where the parties agree the rate of interest on overdue payment, the agreed rate shall not be lower than the 1-year loan prime rate at the time the contract is concluded; absent agreement, interest on overdue payment is paid at a daily rate of 0.05%.

Key points: the floor of an agreed rate is the 1-year LPR at the time of contracting; absent agreement, 0.05% per day (about 18.25% per annum) - a potent pricing basis for chasing construction arrears.

VIII. Ancillary duties (Article 8 and Articles 18 to 20)

  • Article 8: procurement by organs and public institutions using fiscal funds shall strictly follow the approved budget, and no procurement may proceed without a budget or beyond the budget; the funds needed for government-invested projects shall be secured in place under the relevant state provisions, and contractors shall not be made to finance construction by advancing funds.
  • Article 18: by 31 March each year, organs and public institutions shall publish, by website, newspapers or other means easily known to the public, the number and amounts of contracts with overdue unpaid SME amounts for the preceding year; large enterprises shall include that information in their annual reports and publish it through the National Enterprise Credit Information Publicity System.
  • Article 19: large enterprises shall incorporate the assurance of payment to SMEs into their risk control and compliance management systems and urge their wholly-owned or controlled subsidiaries to pay promptly.
  • Article 20: organs, public institutions, large enterprises and their staff shall not, in any form, intimidate or retaliate against SMEs or their staff that raise payment requests or complaints.

Scope of Application

  1. Scope of parties and transactions: applies to procurement of goods, works and services by organs, public institutions and large enterprises from SMEs; SME status follows the state SME classification standards, and the SME declaration should be proactively provided at contracting. Transactions between SMEs themselves do not fall under these period and interest rules.
  2. The payment period allows contractual agreement, but for organs and public institutions 60 days is the maximum; large enterprises' agreements must fit industry norms and trading practices and may not set back-to-back conditions of the 'upon receipt of third-party payment' type.
  3. Relation between interest on overdue payment and contractual liquidated damages: the floor of the 1-year LPR at the time of contracting is statutory, and an agreement below that floor is invalid; absent agreement, 0.05% per day. The rule is the pricing measure of interest on overdue payment, not the entirety of liquidated damages or compensation for loss.
  4. Version note: the clause numbers here are those of the 2025 revision (State Council Decree No. 802), in which interest on overdue payment is Article 17; materials citing the 2020 version (State Council Decree No. 728; e.g. old Article 15 for overdue interest, old Article 8 for payment periods) must first be checked for version and clause numbering and must not be mixed with the revised numbering.
  5. The Article 12 bar on forcing audit results as the settlement basis is limited to organs, public institutions and state-owned large enterprises, and subject to laws and administrative regulations; civil settlement still follows the contract - the validity of 'settlement subject to audit' clauses and the fallback period are covered in the settlement topic.

Further Reading

Regulation on Ensuring Payment to Small and Medium-sized Enterprises (2025 revision, State Council Decree No. 802), Articles 8 to 20, notably Article 9 (30/60-day payment periods and settlement commencement), Article 10 (acceptance commencement and delayed acceptance), Article 11 (commercial bills, electronic receivables vouchers), Article 12 (audit-based settlement), Article 13 (four securities, bond substitution), Article 14 (no delay via internal processes or final-account audit), Article 15 (undisputed part paid first), Article 17 (interest on overdue payment); check the Provisions on SME Classification Standards for SME status, and Article 511 of the Civil Code on the supplementary rules where the performance period is unclear.