The undisputed-portion-first payment principle in price disputes: progress payment, final account, and wage protection
Where the project price is disputed, the undisputed portion must be paid first: at the progress payment stage, payment certificates are issued and paid for undisputed BOQ items per GB/T 50500-2024, Clause 9.4.11; where final account re-checking raises objections, the unobjected portion undergoes a partial final account (incomplete final account) first (10.3.7); additional works (10.1.8) and quality disputes (10.3.14) may not delay the undisputed portions; and labor costs may never be withheld under any dispute per Article 35 of the Regulations on Wage Payment for Migrant Workers. The disputed portion itself goes negotiation -> review/mediation -> arbitration/litigation.
Applicable Codes
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.1.5、9.4.11、10.1.8、10.3.7、10.3.14、11.2.7、11.4.3条
- 《中华人民共和国民法典》(主席令第45号)第五百二十五条、第五百二十六条、第五百三十一条、第七百九十九条、第八百零七条
- 《保障中小企业款项支付条例》(2025修订,国务院令第802号)第九、十、十三、十四、十五、十七、十八条 https://www.mee.gov.cn/zcwj/gwywj/202503/t20250325_1104643.shtml
- 《保障农民工工资支付条例》(国务院令第724号)第二十四条、第三十五条
- 财建〔2004〕369号《建设工程价款结算暂行办法》第十六条、第十八条、第十九条、第二十条
- 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》(法释〔2026〕12号)第二十三条 https://www.court.gov.cn/fabu/xiangqing/504221.html
Topic Positioning
When the project price is disputed, must the undisputed portion be paid first — yes. This card compiles the "undisputed (unobjected) portion first" clauses of GB/T 50500-2024 at interim payment, final account, additional works, and quality disputes, plus the special protection of labor costs under the Regulations on Ensuring Wage Payment to Migrant Workers — a direct basis for contractor payment demands and compliant employer payment.
Core Conclusions
- Progress payment stage (9.4.11): where measurement and pricing of some BOQ items are disputed, the employer shall issue the progress payment certificate and pay per the undisputed portion's results — it may not refuse payment wholesale on grounds of dispute.
- Final account stage (10.3.7): where re-checking raises objections, the unobjected portion undergoes a partial final account (incomplete final account); the objected portion is resolved by negotiation, failing which Chapter 11 dispute resolution applies.
- Special situations: additional works and contract-scope works (10.1.8) — settlement and payment of contract-scope works may not be delayed by disputes over additional works; quality disputes (10.3.14) — works having passed acceptance or used by the employer follow the warranty clauses, and portions without quality objections are settled per the contract.
- Absolute priority of labor costs (State Council Decree No. 724, Article 35): where quantities, quality, or cost are disputed, the owner may not withhold the labor costs within the project payment, nor may the general contractor withhold wage disbursement on that account.
- The disputed portion itself (11.1.1): amicable negotiation -> supplementary (settlement) agreement -> dispute review or mediation -> arbitration or litigation.
Applicable Boundaries
Applies to price disputes between employer and contractor; each clause leaves room for "unless otherwise agreed by the contract" — check the contract's special conditions first in practice; 9.4.11 targets progress payment certificates, 10.3.7 targets final account re-checking objections; quality disputes require first distinguishing whether the works have passed acceptance or entered use. First payment of undisputed portions does not alter substantive rights on the disputed portions — the contractor must still object or claim in writing within the agreed periods, overdue silence possibly deemed acceptance.
Further Reading
GB/T 50500-2024, Clause 9.4.11 (interim payment), Clause 10.3.7 (final account review), Clause 10.1.8 (additional works), Clause 10.3.14 (quality disputes), Clause 10.1.9 (final account dispute resolution interface), Clause 11.1.1 (dispute resolution); State Council Decree No. 724 "Regulations on Ensuring Wage Payment to Migrant Workers", Articles 24, 29, 35; supporting procedures: GB/T 50319-2013 "Code for construction project supervision", Clause 5.3.1 (measurement and payment certification procedure).
Keywords
- 无争议部分先行支付
- 拒付工程款
- 部分争议
- 不完全竣工结算
- 进度款支付证书
- 履行抗辩权的相当性
- 保障中小企业款项支付条例第十五条
- 人工费用不得因争议停拨