The priority mechanism for migrant worker wages over project funds under the Regulation on Guaranteeing Wage Payment to Migrant Workers (State Council Decree No. 724): the employer's funding arrangement and payment-security duties, labour-cost transfer as a separate line not blocked by disputes, closed dedicated accounts, advance payment and first repayment ranks, and the penalty clauses
The Regulation sets no general ranking of 'wage claims over works-payment recovery' - instead five layers make wage payment independent of works settlement: no funds arrangement, no commencement and no construction permit (Article 23); labour-cost transfer cycles at most 1 month plus a payment security (Article 24); quantity, quality or cost disputes may not stop labour transfers or proxy payment (Article 35); where the employer's failure to remit causes arrears, it advances wages up to the unpaid works payment (Article 29); subcontract or re-letting arrears are first repaid by the main contractor, then recovered (Article 30); dedicated-account funds and the wage security deposit may not be seized, frozen or transferred for non-wage reasons (Article 33). Breaches: Article 54 fines RMB 20,000-50,000 on the unit and 10,000-30,000 on the responsible persons; Articles 55-57 fine RMB 50,000-100,000 and may order suspension, restrict new projects, downgrade or revoke qualifications.
Applicable Codes
- 《保障农民工工资支付条例》(国务院令第724号)第二十三条
- 《保障农民工工资支付条例》第二十四条
- 《保障农民工工资支付条例》第二十六条
- 《保障农民工工资支付条例》第二十七条
- 《保障农民工工资支付条例》第二十九条
- 《保障农民工工资支付条例》第三十条
- 《保障农民工工资支付条例》第三十一条
- 《保障农民工工资支付条例》第三十二条
- 《保障农民工工资支付条例》第三十三条
- 《保障农民工工资支付条例》第三十五条
- 《保障农民工工资支付条例》第三十六条
- 《保障农民工工资支付条例》第三十七条
- 《保障农民工工资支付条例》第四十九条
- 《保障农民工工资支付条例》第五十三条
- 《保障农民工工资支付条例》第五十四条
- 《保障农民工工资支付条例》第五十五条
- 《保障农民工工资支付条例》第五十六条
- 《保障农民工工资支付条例》第五十七条
- 《保障农民工工资支付条例》第五十九条
Positioning
The priority mechanism for migrant worker wages relative to works payments under the Regulation on Guaranteeing Wage Payment to Migrant Workers (State Council Decree No. 724, published 2019-12-30, effective 2020-05-01): on what basis wages are "prioritised" in the works-payment relationship, to what degree, who bears the first-payment duty, and the statutory consequences of breach.
Core conclusions
1. Priority is not achieved through a claim-ranking clause
The Regulation has no general clause ranking wage claims ahead of works-payment recovery, and is no substitute for the priority of payment for the works under the Civil Code Article 807. Its priority effect is built from five stacked layers: funds arranged up front - labour costs transferred separately - disputes do not block - advance payment / first repayment - closed funds and administrative liability.
2. The employer's funding duties (Articles 23-24)
Article 23: "The employer shall have funds arrangements meeting the needs of construction. Without them, the project may not commence; where a construction permit is required, the competent department shall not issue it. Funds for government-invested projects shall be in place per state rules - contractors may not finance construction by advancing funds." Article 24: "The employer shall provide the contractor security for payment of works funds. The written construction contract shall fix the measurement cycle, the progress settlement method and the labour-cost transfer cycle, and shall agree labour costs as required to guarantee wages paid in full and on time. The labour-cost transfer cycle shall not exceed 1 month. The parties shall keep the contract on file." Key point: labour costs are the part of works payment that must be listed separately with its own cycle (up to 1 month) - not the residue at settlement.
3. Dedicated use and closure of wage funds (Articles 26, 27, 31, 32, 33)
- Article 26: the main contractor opens a dedicated migrant wage account, used solely to pay wages on that project, with records kept.
- Article 27: financial institutions streamline account services and daily management; on funds not remitted as agreed they notify the main contractor, which reports to the human resources and construction authorities - feeding the arrears early-warning system. On completion without arrears, the main contractor may cancel the account after 30 days' publicity; the balance belongs to the main contractor.
- Article 31: proxy payment by the main contractor is promoted - subcontractors assess monthly the workers' output, prepare wage sheets confirmed by signature by the workers themselves and pass them to the main contractor with the monthly progress; the main contractor pays wages from the dedicated account straight into each worker's own bank account and issues payment vouchers to the subcontractor. The social security card or bank card bound to the account may not be withheld or covertly withheld by any unit or person.
- Article 32: the main contractor deposits a wage security reserve dedicated to wages owed for work on its projects, stored differentially - reduced or waived for units without arrears, at a higher ratio for units with arrears; a financial institution guarantee may substitute; ratios, forms and waivers are set by the State Council HR/social security department with others.
- Article 33 (priority at enforcement): "Save as provided otherwise by law, funds in migrant wage dedicated accounts and wage security reserves may not be sealed, frozen or transferred for reasons other than paying wages for work performed on this project."
4. Ranking of works payment and wages
- Disputes do not block (Article 35): "Where the employer and the main contractor, or a contractor and its subcontractor, dispute over quantity, quality or cost, the employer may not withhold the labour costs of the works payment, and the main contractor may not withhold proxy payment." Labour costs are remitted ahead of the dispute's outcome - the most direct normative expression of ranking.
- Employer under-remittance causing arrears (Article 29(2)): "Where the employer's failure to remit works payment as agreed causes wage arrears, the employer shall advance the unpaid wages up to the unpaid works payment." The advance cap = unpaid works payment. Paragraphs 1 and 3 add timely remittance, full transfer of labour costs to the dedicated account, per-project coordination and arrears-prevention mechanisms, and joint handling of collective wage claims with reporting.
- Subcontract and re-letting arrears (Article 30): "The subcontractor bears direct responsibility for real-name management and wage payment of the workers it engages; the main contractor supervises its labour use and wage payment. Where a subcontractor falls into arrears, the main contractor first repays and then recovers at law. Where the project is re-let and arrears arise, likewise."
- Unlawful awarding, affiliation, unlawful projects (Articles 36-37): awarding or subcontracting to individuals or unqualified units causing arrears - the employer or main contractor pays; affiliation (working in the contractor's name) - the contractor pays; projects breaching spatial planning or construction laws - the employer pays.
5. Penalties
- Article 54 (order to correct; on expiry, fine RMB 20,000-50,000 on the unit and 10,000-30,000 on the legal representative, principals and directly responsible persons): paying wages in kind or securities; failing to keep wage ledgers or issue wage slips; withholding the social security card or bank card bound for wage payment.
- Article 55 (order to correct; on expiry, order suspension and fine RMB 50,000-100,000; serious cases - restriction on new projects, qualification downgrade or revocation): not opening or using the dedicated account as required; not storing the wage reserve or providing a guarantee; no real-name labour management.
- Article 56 (fine RMB 50,000-100,000 on expiry): subcontractors not assessing output monthly and preparing signed wage sheets; main contractor not supervising subcontractor labour use; subcontractors not cooperating; no site rights-information publicity.
- Article 57 (suspension plus fine RMB 50,000-100,000): employer not providing payment security; not remitting labour costs in full to the dedicated account as agreed; refusing to produce the contract or account records.
- Article 53: wage arrears are handled under the relevant laws (no separate fine here). Article 49: employers failing to provide payment security or government projects in arrears - local governments restrict new projects and record the breach in the credit system. Article 59: government projects with funds in arrears - recovery by order, interviews, notification and administrative sanctions.
Applicable boundaries
- The "priority" here is procedural and financial - separate transfer, closed accounts, advance payment, first repayment, administrative penalties - not a ranking of wage claims over works-payment mortgages in bankruptcy or enforcement distribution; the works-payment priority follows Civil Code Article 807 and its judicial interpretation.
- The employer's advance is capped at unpaid works payment; the main contractor's first repayment for subcontract or re-letting arrears shifts only the timing - final liability is unchanged and recovery follows.
- Fines are banded: Article 54 RMB 20,000-50,000 (unit) and 10,000-30,000 (persons); Articles 55-57 RMB 50,000-100,000; suspension appears in 55 and 57; only 55 carries the escalation measures.
- Reserve ratios, forms and waivers are set by the State Council HR department with others - check the current local rules.
Further reading
Decree No. 724: Articles 23-24, 26-27, 31-33, 29-30, 35-37, 49, 53-57, 59. Implementation details (real-name ledgers, reserve ratios, account closure) in the companion card.