Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

When the employer withholds project payments, the construction general contractor may not stop paying migrant workers' wages (compliance conclusion under the Regulations on Ensuring Wage Payment to Migrant Workers)

Wages may not be stopped. The wage-payment obligation is independent of project settlement disputes: under Article 35 of the Regulations, even where disputes exist between the parties, the general contractor may not suspend wage payment on that account; where arrears result from the employer's non-payment, the employer advances payment up to the amount of unsettled project payments (Article 29); arrears caused by subcontractors or illegal subcontracting are cleared first by the general contractor (Article 30). The correct course is a dual track: keep paying wages while pursuing the project payment.

Applicable Codes

  • 《保障农民工工资支付条例》(国务院令第724号)

Topic Positioning

Resolves a high-frequency compliance question in the engineering construction sector: when the employer (construction client) withholds project payments, may the construction general contractor suspend payment of migrant workers' wages? Gives a clear legal conclusion, the liability chain and lawful remedial paths, for general contractors, subcontractors and upstream employers.

Core Conclusions

Wages may not be stopped; the migrant-wage payment obligation is independent of project settlement disputes:

  1. Article 35: where the parties have disputes over quantities, quality, cost, etc., the employer may not on that account withhold remittance of labor costs, nor may the general contractor on that account suspend wage payment as regulated - neither arrears nor disputes constitute a lawful ground for stopping wage payment.
  2. Article 29: where wage arrears arise because the employer failed to remit project payments as agreed, the employer advances payment up to the amount of unsettled project payments. Upstream funding risk is borne by the employer through its advancement duty; the general contractor should keep paying wages and then claim the advancement from the employer.
  3. Article 30: where a subcontractor withholds wages, or illegal subcontracting causes arrears, the general contractor clears them first and recovers according to law - the general contractor stands in the backstop position for wage payment.
  4. Article 24 requires the contract to stipulate a labor-cost remittance cycle not exceeding 1 month; Article 57 provides that failure to remit labor costs in full, etc., draws an order to correct, work stoppage and a fine of RMB 50,000-100,000. Correct actions: keep paying wages, demand in writing that the employer advance payment up to the unsettled project payments, and pursue the project payments separately through legal channels (priority right of payment for construction project prices, litigation or arbitration). The right to suspend work is a contractual right exercisable as agreed, but it does not discharge the wage-payment obligation for labor already performed.

Applicable Boundaries

Applies to the question of whether payment disputes among employers, general contractors and subcontractors can be passed downstream as stopping wages. Does not cover the wage-deposit utilization process, real-name management details, or the elements of the crime of refusing to pay labor remuneration (see the card on execution points of the four systems). Where the dedicated account is truly exhausted, the path is advancement, the retention deposit and administrative complaints - not stopping payment.

Further Reading

Regulations on Ensuring Wage Payment to Migrant Workers (State Council Decree No. 724): Article 24 (labor-cost remittance cycle not exceeding 1 month; payment security), Article 29 (employer's advancement duty), Article 30 (general contractor's first-clearance duty), Article 35 (disputes do not affect remittance and payment), Article 36 (clearance liability for illegal contracting-out/subcontracting), Article 49 (restrictions on new government-invested projects and credit recording), Article 57 (penalties); see also the Labor Security Supervision Regulations, Article 26 (50%-100% additional compensation for overdue payment), and the Criminal Law, Article 276-1 (crime of refusing to pay labor remuneration).

Keywords

Cited By