Execution points of the four systems under the Regulations on Ensuring Wage Payment to Migrant Workers: dedicated wage accounts, real-name employment, payment by the general contractor, and the wage retention deposit

Execution chain: the employer remits labor costs as agreed (remittance cycle not exceeding 1 month) into the general contractor's dedicated wage account, payment is made on the basis of the real-name-verified payroll, the general contractor pays each migrant worker directly through the account, and the wage retention deposit backstops. Failure to open a dedicated account, to store the retention deposit, or to implement real-name management is subject, under Article 55 of the Regulations, to an order to stop work plus a fine of RMB 50,000-100,000, and in serious cases to restrictions on undertaking new projects, downgrade of qualifications, or revocation of qualifications.

Applicable Codes

  • 《保障农民工工资支付条例》(国务院令第724号)
  • 《工程建设领域农民工工资保证金规定》(人社部发〔2021〕65号)

Topic Positioning

Centered on the Regulations on Ensuring Wage Payment to Migrant Workers (State Council Decree No. 724, effective 1 May 2020), this card maps the execution points and statutory penalties of the four wage-protection systems - the dedicated wage account, real-name employment management, payment by the general contractor on behalf of subcontractors, and the wage retention deposit - answering 'how these things are actually executed on projects'.

Core Conclusions

The four systems interlock: the employer remits labor costs (remittance cycle not exceeding 1 month) into the dedicated wage account opened by the general contractor as agreed in the contract - payment is based on the real-name-verified payroll - the general contractor pays each migrant worker's personal bank account directly through the account - the wage retention deposit backstops.

  • Dedicated account: opened by the general contractor per project, for exclusive use, with records kept for inspection; a financial institution that finds labor costs not remitted as agreed must notify the general contractor and feed the result into the wage-arrears early-warning system; after completion of the works without wage arrears, cancellation may be applied for after 30 days of public notice, with the balance going to the general contractor.
  • Real-name management: the general contractor and subcontractors must sign labor contracts and register workers' identities; unregistered persons may not enter the site; the project department assigns a dedicated labor-relations officer; employment ledgers are kept for at least 3 years after completion of the works and full settlement of wages.
  • Payment by the general contractor: subcontractors assess work monthly and compile the payroll, obtain the workers' signed confirmation, and pass it to the general contractor, which pays the workers directly through the account and issues payment vouchers; withholding workers' social-security cards or bank cards is prohibited; where a subcontractor withholds wages, or illegal subcontracting causes arrears, the general contractor clears the arrears first and then recovers.
  • Retention deposit: stored by the general contractor at 1%-3% of the contract sum (cash or a financial-institution guarantee both acceptable); multiple concurrent projects may enjoy a reduced rate but not below 0.5%; contracts below RMB 3 million with no prior arrears may be exempted; 2 consecutive years without arrears cuts the rate for new projects by 50% or more; 3 consecutive years plus real-name and account compliance may be exempted; arrears raise the rate by 50% or more, serious dishonesty by 100% or more.
  • Penalties: no dedicated account, no retention deposit stored, or no real-name management - ordered to correct within a time limit; failing which, work is ordered to stop and a fine of RMB 50,000-100,000 is imposed; serious cases may bring restrictions on undertaking new projects, downgrade of qualifications or revocation of qualifications.

Applicable Boundaries

Applies to migrant-worker wage payment management in the engineering construction sector (buildings, municipal works, transport, water conservancy, etc.); the four systems must be executed jointly and cannot be implemented singly. Storage ratios, exemption thresholds, etc. follow Ren She Bu Fa [2021] No. 65 and other supporting rules; local refinements may exist - always verify the project location's current requirements.

Further Reading

Regulations on Ensuring Wage Payment to Migrant Workers, Articles 24, 26, 27, 28, 30, 31 and 32 (core of the four systems), Article 33 (account protection), Article 35 (disputes do not bar remittance and payment), Articles 55-57 (penalties); supporting document: Rules on Wage Retention Deposits in the Engineering Construction Sector (Ren She Bu Fa [2021] No. 65), Articles 11 and 12, on the specific standards for storage ratios, reductions and exemptions, and dishonesty surcharges.