The base for computing works retention money under a fixed lump-sum construction contract: the total settled project price (including contractually adjustable items and excluding unused provisional sums) rather than the signed contract price, capped at 3%; on rescission or void incomplete works the base shifts to the price due to the contractor or the discounted compensation due
For a fixed lump-sum contract the retention money base is 'the total settled project price', not the signed contract price: total settled price = the fixed contract price + contractually adjustable additions (variations, site instruction records, claims, provisional price adjustments, provisional sums actually incurred, cost fluctuation adjustment, changes in laws and policies, etc.) - deductions such as unused provisional sums; both the retention percentage and the guarantee amount are capped at 3% of that total (Jian Zhi [2017] No. 138 Article 7; GB/T 50500-2024 Clause 10.5.1), not computed on the signed price, the audit conclusion or the unpaid balance. Exception: in first-instance cases newly accepted after 30 June 2026, where the construction contract is rescinded the base is the price due to the contractor, and where the contract is void and the works incomplete the base is the discounted compensation due, with the return period running from site demobilisation (Fa Shi [2026] No. 12 Article 14).
Applicable Codes
- 建质〔2017〕138号《建设工程质量保证金管理办法》第三、六、七、十、十一条
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.3.1、8.3.5、10.3.2、10.3.15、10.5.1条
- GF-2017-0201《建设工程施工合同(示范文本)》第15.2.1、15.3、15.3.2条(2017-10-01施行)https://www.mohurd.gov.cn/gongkai/zc/wjk/art/2017/art_17339_233757.html
- GF-2020-0216《建设项目工程总承包合同(示范文本)》第14.6.2、14.6.3条
- 法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第十七条、第二十八条
- 法释〔2026〕12号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》第十条、第十四条、第二十三条(2026-06-30施行)https://www.court.gov.cn/fabu/xiangqing/504221.html
- T/ZBD 100.5-2023 · Work Guideline for Settlement Audit of Construction Works 第1.4.10条
Scope and Positioning
This card answers what base applies to the works retention money under a fixed lump-sum construction contract: whether the base is 'the total settled project price' or 'the signed contract price', how the total settled price is assembled item by item and which items must be excluded, and the rules shifting the base to 'the price due to the contractor / the discounted compensation due' upon rescission, incomplete works or contract invalidity, together with the conduct-time boundary between the new and old rules.
Core Conclusion
1. At final account: the base is the total settled project price, capped at 3%
Jian Zhi [2017] No. 138, Measures for Administration of Construction Works Retention Money, Article 7: 'The employer shall retain the retention money in the manner agreed in the contract, and the total retention percentage shall not exceed 3% of the total settled project price. Where the contract provides for the contractor to substitute a bank guarantee for the retained money, the guarantee amount shall not exceed 3% of the total settled project price.'
GB/T 50500-2024 Clause 10.5.1: 'The employer shall retain the retention money in the quality assurance manner agreed in the contract; the cumulative retention money, or the guarantee amount where a guarantee bond substitutes for the retention money, shall not exceed 3% of the total settled price of the works. Where the contractor has provided performance security, the employer shall not retain works retention money before completion of the project. Where works quality guarantee bonds, works quality insurance or other assurance methods are adopted, the employer shall not further retain the money.'
A fixed lump-sum contract fixes only the starting 'price' and the quantity and price risks within the agreed bands; it does not alter the statutory rule of 'the total settled price as the base'. The retention must therefore not be computed as 3% of the signed contract price, the audit (government fiscal review) conclusion, or the paid or unpaid balance.
2. Assembling the total settled price (item list in GB/T 50500-2024 Clause 10.3.2)
The items of the final account price are listed in order: (1) total price of the contract bill; (2) adjustment for BOQ errors and omissions; (3) adjustment of provisional sums; (4) adjustment of provisional prices (provisional prices for materials and for nominated specialist subcontract works); (5) adjustment of main contractor's attendance and coordination provisions; (6) dayworks adjustment; (7) adjustment for changes in costs; (8) adjustment for changes in laws, regulations and policies; (9) variation additions and omissions; (10) additional works price; (11) claims price; (12) liquidated damages for non-performance of the contract; (13) other price (if any).
The payment formula (Clause 10.3.15): 'payable final account price = final account total price - retained retention money - cumulative amounts actually paid earlier', and it clarifies that 'where the works adopt other works quality assurance methods, the retained retention money in the formula shall not be computed'; the payment application shall state four items: the total final account price, the cumulative amount actually paid, the retention money to be retained (unless other works quality assurance has been provided), and the final account payment actually due.
3. Items that must be excluded from the base
- Unused provisional sums. Clause 8.3.1: 'Provisional sums within the total contract price are at the employer's disposal and used per the instructions issued by the employer. Though included in the total contract price, provisional sums do not belong to the contractor and may not occur; only when actually incurred per the contract do they become payment due to the contractor and enter the settled price of the works; unused provisional sums revert to the employer at final account.' Clause 8.3.5: 'Where no provisional-sum adjustment event occurs during performance, the provisional sums included in the total contract price shall be wholly deducted at settlement; where such events occur, the parties shall declare, verify and determine the adjusted provisional-sum prices under the relevant provisions of Clause 8 of this standard, and pay the corresponding price under Clauses 9 and 10. Provisional sums within the total contract price for works or services not yet specified or not describable in detail shall be computed on the actual works or work completed by the contractor at the employer's request; provisional sums for such works or services not requested by the employer shall be deducted from the total contract price at final account.' - Only provisional sums actually incurred enter the total settled price and may count in the base.
- Advance payments (only in the successive-retention case). GF-2017-0201 Clause 15.3.2: '(1) retained successively when progress payments are made, in which case the base of the retention money excludes advance payments made and recovered and price adjustment amounts; (2) the retention money retained in one sum at the final account of the works; (3) other retention methods agreed by the parties. Unless the particular conditions of the contract provide otherwise, the retention of the retention money adopts method (1) above in principle. The retention money cumulatively withheld by the employer shall not exceed 3% of the total settled project price. Where the contractor submits a retention money bond within 28 days after the employer issues the final payment certificate, the employer shall concurrently refund the sums withheld from the works price as retention money; the bond amount shall not exceed 3% of the total settled project price. On refunding the retention money the employer pays interest at the benchmark rate for similar loans of the same period published by the People's Bank of China.' (GF-2020-0216 Clause 14.6.2 agrees the same retention method and 28-day bond substitution rule, with refund interest at the benchmark rate for similar deposits of the same period.)
4. Adjustment boundaries at final account under fixed lump-sum (setting the ceiling of the base)
Lump-sum settlement adjusts only what is agreed as adjustable: T/ZBD 100.5-2023 Guideline for Final Account Review Practice Clause 1.4.10: 'For lump-sum contracts with a clearly agreed scope and conditions, the contract price shall be adjusted on the basis of the total price only for the variations and claims that have occurred.' Fa Shi [2020] No. 25 Article 28: 'Where the parties agree to settle the project price at a fixed price, and one party requests expert assessment of the construction cost, the people's court will not support it.' - That is, the total settled price cannot be back-derived by re-measuring quantities or through cost expert assessment; base adjustments run only along the contractually adjustable items.
5. Exceptions: rescission, incomplete works, contract invalidity (re-anchoring the base)
Fa Shi [2026] No. 12 Article 14: 'Where a construction contract is rescinded and the contractor claims that the works retention money be computed on the price due to it, the people's court shall support the claim. The return period of the works retention money runs from the date the contractor demobilises from site; where the construction contract is rescinded after the contractor demobilises, it runs from the date of rescission.' 'Where the construction contract is void and the works are incomplete, and the contractor claims that the works retention money be computed on the discounted compensation due to it, the people's court shall support the claim. The return period of the works retention money runs from the date the contractor demobilises from site.'
Conversion of the completed part's price after rescission of a fixed lump-sum contract (Article 10 of the same interpretation): 'After a fixed lump-sum construction contract is rescinded, where the parties have no agreement on the price of the completed part of conforming quality and cannot reach agreement, the people's court may, by reference to the pricing standards and methods published by the construction administrative authority at the place of the works at the time the contract was concluded, or relevant norms in the engineering construction field, determine the proportion of the price of the part completed by the contractor to the total price of the works, and multiply that proportion by the fixed total price agreed in the contract to determine the price of the part completed by the contractor.' In incomplete-works cases the base is thus no longer the full contract price but the proportionally converted price due (for void contracts, the discounted compensation due).
The conduct-time boundary (Article 23): 'This interpretation takes effect on 30 June 2026. It applies to first-instance construction contract dispute cases newly accepted by the people's courts after it takes effect. After it takes effect, SPC judicial interpretations previously issued that are inconsistent with this interpretation are superseded by it.'
6. Baseline rules for the return period (companion to the base)
Fa Shi [2020] No. 25 Article 17: 'In any of the following situations, the people's court shall support the contractor's request that the employer return the works retention money: (1) the return period of the works retention money agreed by the parties expires; (2) where the parties have not agreed a return period, two years elapse from the date the works pass completion acceptance; (3) where completion acceptance of the works is not carried out within the agreed period due to the employer, the return period agreed by the parties expires 90 days after the contractor submits the completion acceptance report; where the parties have not agreed a return period, two years elapse 90 days after the contractor submits the completion acceptance report. The employer's return of the works retention money does not affect the contractor's performance of its works warranty obligations under the contract or under law.'
Jian Zhi [2017] No. 138 Article 10: 'Within the defects liability period, where the contractor duly performs the responsibilities agreed in the contract, upon expiry the contractor applies to the employer for return of the retention money.' Article 11: 'Upon receiving the contractor's return application, the employer shall, within 14 days, verify it jointly with the contractor per the content agreed in the contract. If there is no objection, the employer shall return the retention money to the contractor as agreed. Where no return period is agreed or the agreement is unclear, the employer shall return the retention money within 14 days after verification, bearing liability for breach under law if it fails. Where the employer gives no reply within 14 days after receiving the application and still gives no reply within 14 days after demand, it is deemed to have approved the contractor's return application.'
7. Practical computation sequence (fixed lump-sum + final account)
- Lock the price form and the retention method (agreed in the particular conditions; successive retention by default). 2. Assemble the total settled price from the final account statement or settlement agreement signed off by both parties (the 13 items of Clause 10.3.2), adjusting only the contractually adjustable content. 3. Exclude unused provisional sums and, in the successive-retention case, the advance payments made and recovered. 4. Cap the base at 3% of the excluded total settled price, with cash plus bonds not exceeding the cap. 5. Where performance security has been paid before completion or quality guarantee bonds/quality insurance adopted, no further retention. 6. Apply for return per the Article 11 procedure when the defects liability period expires.
Applicable Boundaries
- 3% is a ceiling, not a mandatory retention percentage; the specific percentage, period, interest and the other items (Jian Zhi [2017] No. 138 Article 3: retention and return methods, retention percentage and period, whether interest is paid and how computed, defects liability period and its computation, dispute-handling procedure, defect claim method, late-return liquidated damages and liability) must be agreed in the tender documents and contract clauses.
- 'Base = total settled price' applies where the works are completed and a final account is processed; rescission, incomplete works and void incomplete works are statutory exception bases, and Interpretation (II) Article 14 applies only to first-instance cases newly accepted by the people's courts after 30 June 2026 - cases accepted earlier still follow Interpretation (I) and the contract.
- Successive retention and one-sum retention at final account use different base conventions (the former: current progress payments, cumulatively capped at 3% of the total settled price, and excluding advance payment and price adjustment amounts); do not mix them.
- The defects liability period runs from completion acceptance; where an individual work is accepted and delivered first, from that work's acceptance; where acceptance is delayed by the contractor, from actual passing of completion acceptance; where due to the employer, it starts automatically 90 days after the contractor submits the completion acceptance report; including any extension it shall not exceed 24 months (GF-2017-0201 Clauses 15.2.1, 15.2.2). Expiry ends only defects liability, not warranty obligations.
- For government-invested projects, treasury centralised payment or third-party escrow, the return procedure follows the relevant separate regulations.
Further Reading
- Jian Zhi [2017] No. 138, Measures for Administration of Construction Works Retention Money: Articles 3, 6, 7, 10, 11 (revised 20 June 2017, superseding Jian Zhi [2016] No. 295).
- GB/T 50500-2024, China national pricing standard for BOQ: Clauses 8.3.1, 8.3.5 (deduction of provisional sums), 10.3.2 (final account items), 10.3.15 (payment formula), 10.5.1 (retention cap and bond substitution).
- GF-2017-0201 Model Construction Contract: Clauses 15.2.1, 15.2.2, 15.3, 15.3.1, 15.3.2 (effective 2017-10-01, text at https://www.mohurd.gov.cn/gongkai/zc/wjk/art/2017/art_17339_233757.html ); GF-2020-0216 Model EPC Contract: Clauses 14.6.2, 14.6.3 (return period 7 days).
- Fa Shi [2020] No. 25 Interpretation (I): Article 17 (three return-period situations), Article 28 (no expert assessment under fixed pricing).
- Fa Shi [2026] No. 12 Interpretation (II): Article 10 (proportional conversion of the completed part after rescission of a lump-sum contract), Article 14 (retention base and start at demobilisation), Article 23 (effective 2026-06-30, applying to newly accepted first-instance cases), text at https://www.court.gov.cn/fabu/xiangqing/504221.html .
- T/ZBD 100.5-2023 Guideline for Final Account Review Practice: Clause 1.4.10 (settlement methods for the three pricing forms).
Keywords
- retention money
- 质保金计算基数
- 工程价款结算总额
- 固定总价合同
- 3%上限
- 暂列金额扣除
- 应得折价补偿款
- 建工解释二