final closure of accounts after the defects period
- 01
Model Contract for Construction Projects (EPC) (GF-2020-0216), General Conditions Clause 19 [Claims]: the claims procedure - Notice of Claim within 28 days, claim report within 28 days, deemed approval where no reply is given within 42 days, and expiry of the right to claim after the completion payment certificate
Under GF-2020-0216 Sub-Clause 19.1, the claiming party shall submit a No…
建市〔2020〕96号《建设项目工程总承包合同(示范文本)》GF-2020-0216 通用合同条件第19条(19.1~19.4)GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第8.11.2、8.11.3、8.11.4、8.11.5、8.11.6、8.11.21条GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works 第9.13.2、9.13.3条(已废止)2026-11-01 - 02
Start point and time chain of final account handling: starts once taking-over is passed; deadlines for each link and the 28-day fallback
Final account handling starts once the whole contract works pass taking-…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第2.0.35、10.1.4、10.1.5、10.3.1、10.3.4~10.3.10、10.3.16、10.3.17、10.5.8条及Ch. 11住建部令第16号《建筑工程施工发包与承包计价管理办法》第十八条(承继原建设部令第107号第十六条,原107号令已废止)财建〔2004〕369号《建设工程价款结算暂行办法》第十六条2026-09-26 - 03
Full process of construction payment: advance payment, safety-measures fee, progress payment, interim settlement by construction stage, final account, retention money and final settlement (GB/T 50500-2024 Chapters 9-10)
Payment along the timeline in six segments: advance payment (for works w…
GB/T 50500-2024 建设工程工程量清单计价标准(第9.1~9.4、10.1~10.3、10.5节)财建〔2004〕369号 建设工程价款结算暂行办法建质〔2017〕138号 建设工程质量保证金管理办法2026-09-25 - 04
Return of the quality retention money: timing, procedure, and the final account interface (Jian Zhi [2017] No. 138 + GB/T 50500-2024 §10.5)
The retention money is returned when the defect liability period (genera…
建质〔2017〕138号 建设工程质量保证金管理办法GB/T 50500-2024 建设工程工程量清单计价标准 第10.5节2026-09-25 - 05
The FIDIC Performance Certificate (Red Book Clauses 11.9/11.10) mapped against the domestic completion acceptance - defect liability period - final settlement system: correspondences and differences
Performance Certificate is not Performance Bond. FIDIC Red Book 11.9: th…
FIDIC 红皮书 1999 第 11.9~11.10 条FIDIC 红皮书 2017 第 2 版第 11.9~11.10 条GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第 10.5.5、10.5.8 条2026-09-25 - 06
Legal consequence chain when the employer fails to check the final account or pay on time: GB/T 50500-2024 cl. 10.3.8/10.3.16/10.3.17/10.5.8/10.5.9 “deemed acceptance + liability for breach of contract” and the 28-day fallback
The consequences of the employer failing to check the final account on t…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第10.3.8、10.3.16、10.3.17、10.5.8、10.5.9条原建设部令第107号《建筑工程施工发包与承包计价管理办法》第十六条(已被住建部令第16号废止,内容由第十八条承继)住建部令第16号《建筑工程施工发包与承包计价管理办法》第十八条(现行)2026-09-25