The boundary between the defects liability period (secured by retention money) and the warranty period: differences of length and start, whether funds are held, and refunding retention does not release the warranty duty
Retention money secures only the defects liability period (normally 1 year, 2 years at most, Jian Zhi [2017] No. 138 Article 2); the warranty period follows Article 40 of the Quality Management Regulation for Construction Works: foundations and main structure for the reasonable service life in the design documents; roof waterproofing, watertight bathrooms, rooms and external walls 5 years; heating and cooling 2 heating/cooling seasons; electrical wiring, water supply and drainage pipes, equipment installation and fit-out 2 years - all from the date of passing completion acceptance. Expiry of the defects liability period and refund of retention do not affect the contractor's continuing warranty duty; within the warranty scope and period the contractor performs repairs and compensates losses caused (Article 41).
Applicable Codes
- 建质〔2017〕138号《建设工程质量保证金管理办法》第二条、第八条、第九条、第十条、第十一条
- 《建设工程质量管理条例》(2017修订)第四十条、第四十一条
- GB 55032-2022 · General Code for Construction Quality Control of Building and Municipal Engineering 第5.0.2条
- GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第10.5.5条
- 法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第十七条
Positioning
Two often-confused periods: the defects liability period (what retention money secures - normally 1 year, 2 at most) and the warranty period (statutory minimums, up to the reasonable service life). The core: three differences - timeline, start point, whether funds are held - and the boundary that refunding retention never releases the warranty duty.
Core conclusions
1) Definitions and lengths (No. 138 Article 2) "The works quality retention money (retention) means money agreed in the construction contract between employer and contractor, withheld from payable works payment, to secure the contractor's repair of defects arising in the defects liability period. A defect is non-conformity of the works with the mandatory standards, the design documents and the contract. The defects liability period is normally 1 year and may not exceed 2 years, as agreed by the parties." - retention covers only up to the end of the defects liability period.
2) Start of the defects liability period (Article 8) "The defects liability period runs from the date the works pass completion acceptance. Where completion acceptance cannot be held on schedule for reasons attributable to the contractor, it runs from the date actually passed; for reasons attributable to the employer, the works automatically enter the defects liability period 90 days after the contractor submits the completion acceptance report."
3) Statutory minimum warranty (Regulation Article 40) "Under normal use, the minimum warranty periods are: (1) foundation works and the main structure of infrastructure and buildings - the reasonable service life stated in the design documents; (2) roof waterproofing and watertight bathrooms, rooms and external walls - 5 years; (3) heating and cooling systems - 2 heating/cooling seasons; (4) electrical wiring, water and drainage pipes, equipment installation and fit-out - 2 years. Other items as agreed. The warranty period runs from the date of passing completion acceptance."
4) Refund does not release warranty Regulation Article 41: "For quality problems within the warranty scope and period, the contractor shall perform repairs and compensate the losses caused." Fa Shi [2020] No. 25 Article 17(2): the employer's refund of retention does not affect the contractor's warranty duty under the contract or law (verify the text before citing - not held in this library). In practice: when the defects liability period (up to 2 years) ends the money returns, but waterproofing for 5 years and the structure for its service life stay warrantied - retention is a deposit, not a cap or end of warranty liability.
5) Cost boundary during the defects liability period (Article 9) "Defects caused by the contractor: the contractor repairs and bears the appraisal and repair costs; if it neither repairs nor pays, the employer may deduct from the retention or bank guarantee per the contract, claim the excess beyond the retention, and repair with costs borne does not release liability for losses. Defects caused by others: the employer organises the repair, the contractor bears no cost, and no deduction from retention."
6) The warranty letter is mandatory GB 55032-2022 clause 5.0.2 (mandatory): "The employer shall maintain quality follow-up and complaint handling. The contractor shall perform its warranty duty and sign a works quality warranty letter with the employer stating the warranty scope, period and liability." The letter fixes the cost method for the warranty stage after the defects liability period.
7) Timeline Passing completion acceptance - defects liability period starts (1-2 years, retention held, refunded on expiry) - warranty period starts (same point, lengths 2 years / 2 seasons / 5 years / service life by element). The defects liability period usually sits inside the warranty period; they run in parallel, not in substitution.
Applicable boundaries
The minimum warranty periods are statutory floors - contracts may extend but not shorten; "other items" as agreed, a dispute risk if silent. The defects liability period is contractual (1 year normal, 2 maximum) - never back-derived from the warranty length, and expiry or refund is no defence against warranty claims within the warranty period. Material and equipment purchase contracts follow their own terms and product-quality rules, not this table. Quality-liability shifts from premature use without acceptance form a separate regime (the warranty duty itself stands).
Further reading
Quality Management Regulation (2017 revision) Articles 40-41; Jian Zhi [2017] No. 138 Articles 2, 8, 9, 10-11; GB 55032-2022 clause 5.0.2; GB/T 50500-2024 clause 10.5.5 (refund of remaining retention on expiry, interest-free); Fa Shi [2020] No. 25 Article 17.