Works in use but final account not processed: quality disputes go to warranty, final account proceeds (GB/T 50500-2024, Clause 10.3.14)
Works already in use cannot have the final account delayed on grounds of "not taken over / quality objections": GB/T 50500-2024, Clause 10.3.14 provides that for works having passed taking-over (completion acceptance) or subject to premature use of the works without taking-over by the employer, quality disputes are handled under the warranty contract/clauses and the final account is processed as agreed in the contract; the supporting path is notice of demand -> overdue non-check deemed acceptance (Order No. 107, Article 16; 28 days absent agreement) -> interest on overdue payment (Decree No. 728, Article 15; 0.05% per day absent agreement) -> negotiation/arbitration/litigation.
Applicable Codes
- GB/T 50500-2024 建设工程工程量清单计价标准 第10.3.14条
- 建设部令第107号 建筑工程施工发包与承包计价管理办法 第十六条
- 国务院令第728号 保障中小企业款项支付条例 第十五条
- 法释〔2020〕25号 建工司法解释一 第9、14条
Topic Positioning
Responding when the works have been delivered into use (including premature use of the works without taking-over by the employer) but the final account has not been processed. Core: the final account and quality disputes are decoupled — the final account proceeds, quality goes to warranty.
Core Conclusions
(1) Use does not extinguish the final account obligation: per GB/T 50500-2024, Clause 10.3.14, for works having passed taking-over (completion acceptance) or subject to premature use of the works without taking-over, quality disputes are handled under the warranty clauses and the final account is processed as agreed in the contract — the employer may not delay the final account on grounds of non-taking-over or quality objections. (2) Procedural fallback: after the contractor submits the final account documents and complete materials, the employer's failure to check or comment within the agreed time (28 days absent agreement, Order No. 107, Article 16) is deemed acceptance (Clause 10.3.8); overdue failure to verify or issue the payment certificate is deemed acceptance of the payment application (Clause 10.3.16). (3) Recovery and interest: where the employer fails to pay the final account amount as agreed, the contractor may give notice of demand and pursue a claim; any agreed rate of interest on overdue payment may not be below the 1-year LPR, and absent agreement interest accrues at 0.05% per day (Decree No. 728, Article 15). (4) Quality liability: with premature use of the works without taking-over, the date of transfer of possession is the completion date, and quality liability shifts to the employer except for the foundations and the main structure (Fa Shi [2020] No. 25, Articles 9 and 14).
Applicable Boundaries
Applies where the works are already in use and the final account is unsettled; it does not exempt the contractor's statutory quality liability for the foundations and the main structure. In litigation over deemed acceptance, some courts may turn to construction cost expert assessment (judicial appraisal) — demand letters and proof of service must be retained.
Further Reading
GB/T 50500-2024, Clauses 10.3.5, 10.3.7, 10.3.8, 10.3.14, 10.3.16, 10.3.17 and Chapter 11 (11.1.1, 11.4.1); Ministry of Construction Order No. 107, Article 16; Decree No. 728, Article 15; Fa Shi [2020] No. 25, Articles 9 and 14.