premature use of the works without taking-over
- 01
After termination of the construction contract, the boundary of the payment defence for parts of the works the employer has actually taken over and put to use (without completion acceptance): a blanket refusal to pay on the ground of 'not accepted' is barred; refusal is allowed only 'to the corresponding extent' for undelivered parts and for foundation and main structure defects; repair costs require prior notice of repair
No blanket refusal. Termination only ends the unperformed part; for comp…
法释〔2020〕25号 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)第九条、第十四条、第二十六条、第二十七条法释〔2026〕12号 最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)第十条、第十四条、第十六条、第二十三条(2026年6月30日施行)中华人民共和国民法典(主席令第45号)第五百二十六条、第七百九十三条、第七百九十九条、第八百零六条2026-10-29 - 02
Whether the contractor may claim the works price where the works are in use but completion taking-over was not obtained: maturity of the payment obligation (Fa Shi [2020] No. 25 Article 9(3), transfer of possession deemed completion; Article 14 cutting off the quality defence) and determination of the amount (Article 27 deemed due dates, Article 21 the submitted price, GB/T 50500-2024 Clause 10.3.14 final account proceeds, retention deducted), the situations barring the claim (Civil Code Articles 799 and 793(2)) and the cut-over point of the 2026 Interpretation (II)
The claim lies and the payment obligation is already due: where the work…
法释〔2020〕25号《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》第九条、第十四条、第二十一条、第二十六条、第二十七条、第四十一条《中华人民共和国民法典》第七百九十三条、第七百九十九条、第八百零七条《中华人民共和国建筑法》(2019修正)第六十一条2026-10-29 - 03
Commencement of the defects liability period in all scenarios: where the employer uses the works prematurely without completion acceptance, the period runs from transfer of possession, distinguished from the 90-day automatic-entry rule and from the contractor's exit on termination or invalidity of the contract (Jian Zhi [2017] No. 138, Article 8 + Fa Shi [2020] No. 25, Article 9 + Fa Shi [2026] No. 12, Article 14)
Where the employer uses the works prematurely without completion accepta…
《建设工程质量保证金管理办法》(建质〔2017〕138号,2017修订)第二条、第三条第(四)项、第八条、第十一条《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》(法释〔2020〕25号)第九条、第十四条《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》(法释〔2026〕12号)第十四条、第二十三条(自2026年6月30日起施行)2026-10-29 - 04
Splitting the final account for staged completion acceptance, deferred-item completion and the employer's premature use of unaccepted works: settlement basis, determination of the actual completion date, start of the warranty period and defects liability period, and tiered handling of quality objections (GB/T 50500-2024 clauses 10.1.5 and 10.3.14)
Works accepted in stages are settled stage by stage: once each stage pas…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第10.1.5、10.3.14、10.5节GF-2017-0201《建设工程施工合同(示范文本)》第13.2.3、13.4、14.3、14.4款GB/T 51262-2017 · Code for Construction Cost Appraisal 第5.7.3条2026-10-25 - 05
Works in use but final account not processed: quality disputes go to warranty, final account proceeds (GB/T 50500-2024, Clause 10.3.14)
Works already in use cannot have the final account delayed on grounds of…
GB/T 50500-2024 建设工程工程量清单计价标准 第10.3.14条建设部令第107号 建筑工程施工发包与承包计价管理办法 第十六条国务院令第728号 保障中小企业款项支付条例 第十五条2026-09-25 - 06
Works put into use before completion acceptance: payment, quality liability and warranty rules (the employer's unauthorized use deemed acceptance of quality)
The employer's unauthorized use of un-accepted works equals deemed accep…
法释〔2020〕25号 第9条、第14条、第27条《建筑法》(2019修正)第61条《建设工程质量管理条例》(2019修订)第40条、第58条2026-09-25 - 07
Can payment be made when acceptance fails: measurement-and-payment preconditions, the repair route, and the unauthorized-use exception
Qualified quality is the precondition of measurement and payment: work f…
GB/T 50500-2024 建设工程工程量清单计价标准 第10.3.14条建设工程质量管理条例(2019修订)第16条、第58条DB13(J)/T 8161-2019 建设工程监理工作标准 §8.2.22026-09-25