Engineering Knowledge Cards.
Confidence HighUpdated 2026-10-29

Commencement of the defects liability period in all scenarios: where the employer uses the works prematurely without completion acceptance, the period runs from transfer of possession, distinguished from the 90-day automatic-entry rule and from the contractor's exit on termination or invalidity of the contract (Jian Zhi [2017] No. 138, Article 8 + Fa Shi [2020] No. 25, Article 9 + Fa Shi [2026] No. 12, Article 14)

Where the employer uses the works prematurely without completion acceptance, the defects liability period runs from 'the date of transfer of possession of the works' (expressly so provided in GF-2017-0201, Clause 15.2.1, and GF-2020-0216, Clause 11.2; under Fa Shi [2020] No. 25, Article 9(3), the date of transfer of possession is deemed the completion date); the duration follows the contract, generally one year and at most two years. Jian Zhi [2017] No. 138, Article 8, provides only three commencement points - 'the date of passing completion acceptance / the date of actually passing completion acceptance / 90 days after submission of the completion report' - and does not list premature use, so the 90-day rule cannot be transplanted to premature use. Where the contract is terminated, or is void and the works are incomplete, Fa Shi [2026] No. 12 (effective from 30 June 2026), Article 14, instead runs the time limit for return of the retention money from the date of the contractor's exit from site (or from the date of termination where the contract is terminated after exit).

Applicable Codes

  • 《建设工程质量保证金管理办法》(建质〔2017〕138号,2017修订)第二条、第三条第(四)项、第八条、第十一条
  • 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(一)》(法释〔2020〕25号)第九条、第十四条
  • 《最高人民法院关于审理建设工程施工合同纠纷案件适用法律问题的解释(二)》(法释〔2026〕12号)第十四条、第二十三条(自2026年6月30日起施行)
  • 《建设工程施工合同(示范文本)》GF-2017-0201 第15.1条、第15.2.1条、第15.2.2条、第15.3.3条、第15.4.1条
  • 《建设项目工程总承包合同(示范文本)》GF-2020-0216 第11.2条
  • 《中华人民共和国民法典》(主席令第45号)第七百九十九条
  • 《中华人民共和国建筑法》(2019修正)第六十一条
  • 《建设工程质量管理条例》(2019修订,国务院令第714号)第四十条
  • 《中华人民共和国民事诉讼法》(2023修正)第六十七条

Topic Positioning

This card answers systematically 'from what point in time the defects liability period commences'. It focuses on the scenario that the Measures for the Administration of Construction Quality Retention Money (Jian Zhi [2017] No. 138), Article 8, does not list - the employer using the works prematurely without completion acceptance - and aligns, line by line against the provisions, the commencement points of eight categories of scenario: passing acceptance, contractor-caused delay in acceptance, employer-caused delay in acceptance (the 90-day rule), the employer delaying acceptance, section works accepted first, termination of the contract, a void contract with the works incomplete, and extension of the period; for direct use in drafting contract clauses, retention-return disputes and defects-liability defences.

Core Conclusions

1. Conclusion first: premature use = the period runs from 'the date of transfer of possession of the works'. Three grounds confirm one another:

  • SPC Interpretation (I) on Construction Contract Disputes (Fa Shi [2020] No. 25), Article 9: 'Where the parties dispute the actual completion date of the construction works ... (3) where the works have not passed completion acceptance and the employer uses them prematurely, the date of transfer of possession of the works is the completion date.' The defects liability period is benchmarked to the completion date, so the date of transfer of possession is the commencement point.
  • Model Construction Contract GF-2017-0201, Clause 15.2.1, as enacted: 'Where the employer uses the works prematurely without completion acceptance, the defects liability period commences on the date of transfer of possession of the works.'
  • Model Project EPC Contract GF-2020-0216, Clause 11.2: 'Where the employer uses the works prematurely without completion acceptance, the defects liability period commences on the date of transfer of possession of the works.'

Duration: the defects liability period is 'generally one year and at most two years, as agreed by the employer and the contractor in the contract' (Jian Zhi [2017] No. 138, Article 2); the model text, Clause 15.2.1, states it as 'the period shall not exceed 24 months at most'. The manner of computation must be agreed in the contract (Jian Zhi [2017] No. 138, Article 3(4): the duration and the manner of computation of the defects liability period).

2. A normative gap that must be flagged (the most error-prone point). Article 8 of Jian Zhi [2017] No. 138, as enacted, lists only three commencement points: 'The defects liability period runs from the date the works pass completion acceptance. Where the works cannot pass completion acceptance within the prescribed period for reasons attributable to the contractor, the defects liability period runs from the date the works actually pass completion acceptance. Where the works cannot pass completion acceptance within the prescribed period for reasons attributable to the employer, the works automatically enter the defects liability period 90 days after the contractor submits the completion report.' - this provision contains no premature-use scenario. Hence: (1) premature use cannot directly borrow any sentence of Article 8; (2) the '90-day' rule targets 'the works being unable to pass completion acceptance within the prescribed period for reasons attributable to the employer' (the works not yet possessed or used) and must not be transplanted to premature use (transfer of possession usually occurs before the 90 days expire; the legal consequences differ, and premature use is governed by the specific rules of the SPC interpretations and the model texts).

3. Comparison table of commencement scenarios

Scenario Commencement point / duration Basis in the provisions
The works pass completion acceptance normally Date of passing completion acceptance; duration as agreed (generally 1 year, at most 2 years) Jian Zhi [2017] No. 138, Article 8, sentence 1, and Article 2; GF-2017-0201, Clause 15.2.1
Acceptance impossible on schedule for contractor reasons Date the works actually pass completion acceptance No. 138, Article 8, sentence 2; GF-2017-0201, Clause 15.2.1
Acceptance impossible on schedule for employer reasons (works not possessed or used) The works automatically enter the defects liability period 90 days after the contractor submits the completion report No. 138, Article 8, sentence 3; GF-2017-0201, Clause 15.2.1; GF-2020-0216, Clause 11.2
The employer delays acceptance but the works pass acceptance Date the contractor submits the completion report (that date deemed the completion date) Fa Shi [2020] No. 25, Article 9(2); GF-2020-0216, Clause 11.2 ('where the works pass acceptance, the period runs from the date the contractor submits the completion report')
No completion acceptance; the employer uses the works prematurely Date of transfer of possession of the works Fa Shi [2020] No. 25, Article 9(3); GF-2017-0201, Clause 15.2.1; GF-2020-0216, Clause 11.2
Section or zone works accepted and delivered before the whole works Runs from the date that section (zone) of works passes acceptance GF-2017-0201, Clause 15.2.1; GF-2020-0216, Clause 11.2
Extension of the defects liability period (contractor-caused defects needing re-inspection and repair) Extended on the original period, the extension included, not exceeding 24 months in total; the extension notice must be given before the original period expires GF-2017-0201, Clause 15.2.2; GF-2020-0216, Clause 11.2
The construction contract is terminated The retention-return period runs from the date of the contractor's exit from site; where the contract is terminated after the exit, from the date of termination; the retention is computed on the price payable to the contractor Fa Shi [2026] No. 12, Article 14(1)
The contract is void and the works are incomplete The retention is computed on the converted-value compensation payable; the return period runs from the date of the contractor's exit from site Fa Shi [2026] No. 12, Article 14(2)

4. The warranty period runs in parallel but does not coincide. Regulation on Quality Management of Construction Projects (2019 revision), Article 40: minimum warranty periods - for infrastructure works and the foundation and principal-structure works of building works, the reasonable service life stated in the design documents; for roof waterproofing, bathrooms with waterproofing requirements, rooms and external walls with waterproofing requirements, 5 years; for heating and cooling systems, 2 heating periods and 2 cooling periods; for electrical wiring, water supply and drainage piping, equipment installation and finishing works, 2 years; 'the warranty period of construction works runs from the date of passing completion acceptance'. For premature use, GF-2017-0201, Clause 15.4.1, provides otherwise: 'Where the employer uses the works prematurely without completion acceptance, the warranty period runs from the date of transfer of possession.' Clause 15.1: on expiry of the defects liability period, the contractor remains bound to perform its warranty duties for the periods agreed in the contract for each part - expiry of the defects liability period does not mean the end of warranty liability; the two periods are not interchangeable and cannot be set off against each other.

5. The link, after commencement, to the retention-return procedure. Where the contractor performs diligently during the defects liability period, it may apply for return of the retention after the period expires; on receiving the application, the employer shall, within 14 days, verify jointly with the contractor under the contract and, if there is no objection, return it as agreed; where no return period is agreed or the agreement is unclear, return shall be made within 14 days after verification, and late return incurs liability for breach under the law; failure to reply within 14 days of receiving the application, and continued failure within 14 days after a demand, is deemed approval of the contractor's application for return of the retention (Jian Zhi [2017] No. 138, Article 11; GF-2017-0201, Clause 15.3.3, same text).

6. Practical pointers (points of proof). The party arguing that the period runs from transfer of possession should fix the date of actual possession with evidence: key handover or handover sheets, records of premises delivered to owners for decoration and occupation, records of opening, production or grid connection, entry notices for third parties engaged to continue the works, records of utility-meter activation, site photographs and the supervising engineer's monthly reports; a party arguing for the 90-day rule or commencement on the acceptance date must prove that the works were not then fit for use and that possession had not passed. In litigation, 'he who asserts must prove' is the basic allocation (Civil Procedure Law, Article 67: a party has the responsibility to provide evidence for its own claims). Note also: after premature use, a claim by the employer, on the ground that the quality of the parts used does not conform to the agreement, will not be upheld by the people's court, but the contractor remains liable in civil law within the reasonable service life for the quality of the foundation and principal-structure works (Fa Shi [2020] No. 25, Article 14) - which directly affects the attribution of repair costs during the defects liability period and the direction of proof.

Boundaries of Application

  1. Temporal effect (conduct-time / acceptance-time threshold): Fa Shi [2026] No. 12 takes effect on 30 June 2026; 'for construction contract dispute cases newly accepted by the people's courts after this Interpretation takes effect, this Interpretation applies'; after it takes effect, where judicial interpretations previously issued by the Supreme People's Court are inconsistent with it, this Interpretation prevails (Article 23). So, for the commencement points on termination and on a void incomplete contract, first check whether the first-instance case was accepted after 30 June 2026 (as at October 2026, the current intake is within the post-effectiveness cohort); first-instance cases accepted before 30 June 2026 do not apply the exit-date rule of Article 14.
  2. Hierarchy of the provisions: Jian Zhi [2017] No. 138 is a departmental normative document; its Article 8 governs only the withholding and return of quality retention money and is not an adjudication basis for the commencement of the defects liability period; the adjudication bases are Fa Shi [2020] No. 25, Article 9 / Fa Shi [2026] No. 12, Article 14, and the agreement in the contract (including the particular conditions of the model texts). The model texts are reference texts for contracting, binding only once the parties choose and incorporate them; where the particular conditions expressly provide otherwise, those provisions govern.
  3. Non-application: the 90-day automatic-entry rule applies only to the situation where, for reasons attributable to the employer, the works cannot pass completion acceptance within the prescribed period and the works have not yet been possessed or used by the employer; if the employer has in fact taken possession and used the works, the transfer-of-possession date governs, and the two must not be played off against each other for advantage.
  4. Finding the 'date of transfer of possession' requires evidentiary support (handover, entry, actual control); in practice it may fall earlier or later than the date of submitting the completion report, so within the same project the two approaches yield different dates, and the date must be fixed case by case.
  5. This card does not expand on payment for the works, the limits on quality objections, or administrative fines (Regulation on Quality Management of Construction Projects, Article 58) following premature use, nor the cap on the retention proportion; see the cross-referenced cards.

Further Reading

  • Measures for the Administration of Construction Quality Retention Money (Jian Zhi [2017] No. 138, 2017 revision), Article 2 (definitions of defect and defects liability period; 1 year / at most 2 years), Article 3(4) (the contract shall state the duration and manner of computation of the defects liability period), Article 8 (three commencement scenarios; note that premature use is not listed), Article 11 (verification of return and 14-day deemed approval).
  • Fa Shi [2020] No. 25, SPC Interpretation (I) on Construction Contract Disputes, Article 9 (three scenarios for determining the completion date), Article 14 (limits on quality objections after premature use; liability for foundations and the principal structure).
  • Fa Shi [2026] No. 12, SPC Interpretation (II) on Construction Contract Disputes, Article 14 (the retention base and the return period from the exit date on termination or on a void incomplete contract), Article 23 (effect from 30 June 2026 and the application threshold for newly accepted first-instance cases).
  • GF-2017-0201, Model Construction Contract, Clause 15.1 (principles of defects liability and warranty), Clause 15.2.1 (commencement and the 24-month cap), Clause 15.2.2 (extension of the defects liability period and the 24-month cap), Clause 15.3.3 (procedure for return of the retention), Clause 15.4.1 (commencement of the warranty period, including from transfer of possession on premature use).
  • GF-2020-0216, Model Project EPC Contract, Clause 11.2 (commencement and extension of the defects liability period).
  • PRC Civil Code, Article 799 (completion acceptance and 'works may not be delivered for use before passing acceptance or where acceptance is not passed'), and PRC Construction Law (2019 revision), Article 61 (delivery for use only after passing acceptance) - the predicate norms making premature use unlawful.
  • Regulation on Quality Management of Construction Projects (2019 revision), Article 40 (minimum warranty periods; the warranty period runs from the date of passing completion acceptance).
  • PRC Civil Procedure Law (2023 revision), Article 67 (allocation of the burden of proof).

Keywords

  • 缺陷责任期起算
  • premature use of the works without taking-over
  • 转移占有之日
  • 90天自动进入缺陷责任期
  • 建质〔2017〕138号第八条
  • 法释〔2020〕25号第九条
  • 建工解释二第十四条 退场之日
  • 质量保证金返还期限