Engineering Knowledge Cards.
Confidence HighUpdated 2026-09-25

GB/T 50500-2024: both progress payments and process-settlement payments floored at 80% — the wording contrast between 9.1.7 "should not be lower" and 10.2.4 "shall not be lower"

Under GB/T 50500-2024, the payment-ratio floors for progress payments and construction-process settlement payments are both 80%, with different force: Clause 9.1.7 on progress payments — "where the contract does not state a payment ratio for the works value, the ratio should not be lower than 80% of the cumulative completed works value" — "should" is recommendatory: agreement prevails, the 80% floor applies only absent agreement; Clause 10.2.4 on process-settlement payments — "the payment ratio shall be agreed in the contract and shall not be lower than 80% of the current process-settlement total" — "shall not" is a prohibitive hard floor: even an agreed ratio below 80% fails the standard. The bases differ: progress payments on "cumulative completed works value", process-settlement payments on "current process-settlement total".

Applicable Codes

  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第9.1.7条、第10.2.4条(配套第9.2.6、9.3.2、10.1.3、10.2.3条)
  • https://jst.zj.gov.cn/col/col1229129246/art/2023/art_8109b9598e49aa7ca1002670dc7c6011.html
  • https://jst.zj.gov.cn/col/col1229129246/art/2020/art_e5ceb71e605d20f609ffb50549b2e3a7.html
  • http://zjt.shandong.gov.cn/art/2025/4/24/art_102884_10345928.html
  • http://zjj.chifeng.gov.cn/zwgk/zfxxgk/fdzdgknr/zcwj/202502/t20250219_2537553.html
  • https://cjw.ezhou.gov.cn/zfxxgk_4836/zc/wjtz/202311/t20231101_585188.html
  • https://zjw.nanyang.gov.cn/2026/03-04/1388749.html
  • http://zjj.yulin.gov.cn/zwgk/fdzdgk/fggz/t26667872.shtml
  • https://www.mohurd.gov.cn/gongkai/fdzdgknr/zgzygwywj/art/2006/art_402_155475.html

Topic Positioning

This card interprets the texts, computation bases, and wording force of the two 80%-floor clauses of GB/T 50500-2024 "Standard for BOQ pricing of construction works" — "progress payment ratio" (9.1.7) and "construction-process settlement payment ratio" (10.2.4) — directly answering "how low may the payment ratio go, and may the contract agree lower".

Core Conclusions

Both floors are 80%, with different wording force and effect against contract terms:

  1. Progress payments (Chapter 9, Clause 9.1.7, verbatim): "The payment of completed works value and the recovery of advance payments shall follow the contract. Where the contract does not state a payment ratio for the works value, the ratio should not be lower than 80% of the cumulative completed works value; the recovery of advances shall comply with Clause 9.2.6 and the prepayment of the work safety measures fee with Clause 9.3.2. Progress payments are computed from the current cumulative price minus the previous cumulative price, and the prepayment of the work safety measures fee shall not be recovered in progress payments."
  • "Should not be lower" is recommendatory: agreed ratios prevail; only absent agreement does the 80%-of-cumulative-value floor apply.
  1. Process-settlement payments (Chapter 10, Clause 10.2.4, verbatim): "The payment ratio of construction-process settlement payments shall be agreed in the contract and shall not be lower than 80% of the current process-settlement total."
  • "Shall not be lower" is a prohibitive hard floor: even an agreed ratio below 80% fails the standard.
  1. Different bases: progress payments on "cumulative completed works value" (cross-period cumulative); process-settlement payments on "the current process-settlement total" (node-based: monthly/quarterly/annual/physical progress per contract).

  2. Related rules: progress payments are computed as the difference of successive cumulative prices; the safety-fee prepayment is not recovered in progress payments (handled per 9.3.2).

One-line conclusion: progress payments 80% (agreement first, standard as fallback, "should"); process settlement 80% (hard floor, "shall not"). The former is backfilled by the standard only absent agreement; the latter may not fall below 80% even when agreed.

Applicable Boundaries

  • Applies only to the text of GB/T 50500-2024 (issued 2024, replacing GB 50500-2013); the 2013 edition has different numbering and content (and no formal process-settlement system) — verify the edition when citing.
  • GB/T 50500 is a recommended national standard: contracts may agree higher ratios or incorporate the standard as contractual duty; but an agreed process-settlement ratio below 80% conflicts with the "shall not" prohibition.
  • "Should not" allows reasonable deviation (agreement prevails); "shall not" admits no sub-floor agreement — the key compliance distinction, not interchangeable.
  • Process-settlement nodes and procedures are contractual (10.1.3); signed process-settlement documents are folded into final settlement without re-measurement (10.2.3), except measures fees and main-contract services.

Further Reading

Keywords

  • GB/T 50500-2024
  • progress payment percentage
  • 施工过程结算支付比例
  • 不宜低于
  • 不应低于
  • 9.1.7
  • 10.2.4
  • 建设工程工程量清单计价标准

Cited By