payment certificate
- 01
Determining the progress-payment ratio and the payment sign-off procedure (GB/T 50500-2024 §9.1/§9.4 + GB/T 50319-2013 §5.3.1)
The ratio is set by three layers — "contract agreement first -> national…
GB/T 50500-2024 建设工程工程量清单计价标准GB/T 50319-2013 建设工程监理规范2026-09-25 - 02
The relation between measurement and payment: quantities fixed before payment (the causal chain of GB/T 50500-2024 Chapters 7 and 9)
Measurement is the precondition and quantitative basis of payment, and p…
GB/T 50500-2024 建设工程工程量清单计价标准 Ch. 7/Ch. 9/Ch. 10GB/T 50319-2013 建设工程监理规范 第5.3.1条DB13(J)/T 8161-2019 建设工程监理工作标准 第8.2.2条2026-09-25 - 03
Calculation of progress payments (GB/T 50500-2024 §9.1/§9.4): the cumulative-difference method, the 11-item composition of cumulative completed value, and payment/deduction rules
Current payable progress payment = cumulative completed value to date −…
GB/T 50500-2024 建设工程工程量清单计价标准 Ch. 9GB/T 50319-2013 建设工程监理规范 第5.3.1条保障农民工工资支付条例(国务院令第724号)2026-09-25 - 04
Legal consequence chain when the employer fails to check the final account or pay on time: GB/T 50500-2024 cl. 10.3.8/10.3.16/10.3.17/10.5.8/10.5.9 “deemed acceptance + liability for breach of contract” and the 28-day fallback
The consequences of the employer failing to check the final account on t…
GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第10.3.8、10.3.16、10.3.17、10.5.8、10.5.9条原建设部令第107号《建筑工程施工发包与承包计价管理办法》第十六条(已被住建部令第16号废止,内容由第十八条承继)住建部令第16号《建筑工程施工发包与承包计价管理办法》第十八条(现行)2026-09-25