In-process settlement linked to final account: preliminaries and main-contract service fees are interim payments that must be recalculated at final settlement (GB/T 50500-2024 Clauses 10.2.3/10.2.7/10.3.3)

For projects with in-process settlement, preliminaries costs (and main-contract service fees) must be recalculated at final account - amounts listed in in-process settlements are only "interim payments", not a final-account basis, and are adjusted up or down per the recalculation (GB/T 50500-2024 10.2.3, 10.2.7, 10.3.3). But recalculation does not mean repricing: all preliminaries of the completed works (incl. safety-measures adjustments) are recalculated per Section 7.3 and Chapter 8 against the priced-list amounts, checking the five exceptions of 7.3.1 - absent exceptions, the result still equals the priced-list amount. Substantively consistent with GB 50500-2013's "lump-sum preliminaries per the priced list"; 2024 merely hard-codes the in-process-to-final linkage procedure.

Applicable Codes

  • GB/T 50500-2024 · Standard for bills of quantities and valuation for construction works 第10.2.3、10.2.7、10.3.3、7.3.1条
  • GB 50500-2013 · Code of Valuation with Bill Quantity of Construction Works (已废止,仅对照)第11.2.2、11.2.3条

Topic Positioning

A frequent practical question: with in-process settlement done, must preliminaries costs be recalculated at final account? This card lays out the GB/T 50500-2024 chain 10.2.3 -> 10.2.7 -> 10.3.3: preliminaries and main-contract service fees in in-process settlements are only "interim payments" and must be recalculated per the contract at final account with adjustment both ways; and, against the 2013 baseline, the substance of "recalculation" (7.3.1 non-adjustment plus five exceptions).

Core Conclusions

I. Overall: yes, recalculate - but "recalculate" is not repricing; it is recomputing per the rules: amounts listed in-process do not count, the final account follows the recomputed result upward or downward. Absent exceptions, the result usually still equals the priced-list (lump-sum) amount - substantively as under 2013.

II. The chain (three clauses):

  1. 10.2.3 (locking principle + sole exception): "Except as provided in 10.2.7, the in-process settlement documents signed by both parties form part of the final-account documents, and the final account shall not re-measure or re-price them. The preliminaries costs and main-contract service fees under 10.2.7 may be adjusted per 10.3.3." Commentary: "The preliminaries and main-contract service fees in in-process settlements are interim payments; for convenience they may be computed proportionally in-process, and at final account they shall be re-determined by accurate measurement per the contract." - Signed work-item and other-item quantities/prices are locked; only preliminaries and main-contract service fees are carved out for recalculation.
  2. 10.2.7 (interim characterization): "Preliminaries computed per 10.2.5 and main-contract service fees per 10.2.6 serve only to compute and pay in-process settlement amounts and are not a basis for determining the final-account price. At final account after overall completion, preliminaries and main-contract service fees shall be recalculated per the contract and adjusted up or down per the confirmed result." - The three features: interim, recalculation at completion, two-way adjustment.
  3. 10.3.3 (recalculation rules): at final account, the parties shall recalculate the preliminaries and main-contract service fees of the in-process settlement documents: (1) preliminaries shall be computed per Sections 7.3 and Chapter 8 for all preliminaries of the completed works, including safety-measures cost adjustments; "amounts listed in in-process settlements shall not be a basis for the final account"; (2) main-contract service fees shall be computed per Section 8.5 for all specialist subcontracts, directly awarded specialist works, and employer-supplied materials; likewise not a basis.

III. Substance of recalculation = the 7.3.1 framework: priced-list preliminaries are not re-measured, except for five classes: (1) preliminaries works listed in the work-item list and contractually measurable items (7.2.1/7.2.2); (2) safety-measures costs per contract; (3) variation-induced changes (7.4.4, requiring an employer-approved scheme); (4) BOQ-defect changes (8.2.2/8.2.3); (5) changes from provisional-sum works not fully foreseen or specified (7.7.2). Preliminaries within specialist prime-sum subcontracts are included in those subcontract prices - no double counting. So "recalculate and determine" = start from the priced-list preliminaries, check whether the five exceptions and safety-cost policy adjustments occurred, and compute the final figure per Chapter 8; with no exceptions, the result equals the priced-list amount - even preliminaries omitted at bidding cannot be recovered through "recalculation".

IV. Versus 2013: 2013 had no in-process settlement (only progress payments plus one final settlement); lump-sum preliminaries settled per the priced list with confirmed adjustments. 2024 admits in-process settlement into the national standard (Section 10.2) and states expressly that in-process preliminaries/service fees are interim, may be apportioned proportionally, are not a final basis, and are trued up at completion. "Lump-sum preliminaries per the priced list" is substantively unchanged; 2024 hard-codes the linkage procedure.

Applicable Boundaries

  • For BOQ works under GB/T 50500-2024 adopting in-process settlement; nodes, procedures, and limits per the contract (10.1.3).
  • 2024 is recommended; contrary contractual terms prevail; 2013 (mandatory) is repealed and used for comparison only.
  • "Recalculation" is not repricing or re-competition: without the five exceptions and safety-cost adjustments, the result normally equals the priced list; zero-priced or omitted preliminaries cannot be recovered (except the non-competitive safety cost - see the cited zero-pricing card).
  • Only preliminaries and main-contract service fees go through recalculation; work-item and other-item values are locked by the signed in-process documents (10.2.3 main sentence); this card is a code summary without amount calculations.

Further Reading

  • GB/T 50500-2024: 10.2.3, 10.2.5-10.2.7, 10.3.1, 10.3.3 (the chain); rules relied on: 7.2.1-7.2.2, 7.3.1, 7.4.4, 7.7.2, 8.2.2-8.2.3, 8.5, Chapter 8.
  • The in-process settlement system and the settlement effect of zero-priced preliminaries - see cited cards.
  • 2013 comparison: 11.2.2-11.2.3 (preliminaries settlement), 11.3.2-11.3.4, 11.4.4 (time limits) - repealed.